Student Success Center Slider
PDC Contacts
Project Manager: Mihai Gavan - 951-827-6959
Planner: Jaime Engbrecht - 951-827-2421
Project Description
- Approximately 62,000 gross square feet / 42,000 assignable square feet
- About 1,000 General Assignment classroom seats in a mix of lecture halls and classrooms
- Lecture Hall in the Round (more information here)
- Informal study/tutoring/mentoring spaces throughout the building
- Multi-purpose student life spaces: large/ small meeting rooms, student lounge, informal study spaces, multi-purpose rooms
- Dining venue
Student Success Center
Construction Progress
UC Riverside’s Student Success Center reached an important milestone Friday, Nov. 6 as construction crews placed the top beam on the new building that is less than a year from completion.
A small ceremony was held to mark the occasion with construction workers and a few campus community members signing their names to the steel beam before a crane lifted it to the top of the structure.
The three-story, 62,000-square-foot building will feature a mix of classrooms, small- to large-sized lecture halls, multipurpose rooms, student study areas, meeting rooms, and a student lounge.
With a seating capacity of 1,100, the new building will provide a significant increase in classroom space to meet the growing campus enrollment and graduation rates in coming years.
In a video celebrating the topping-out ceremony, Chancellor Kim A. Wilcox described the progress as a great moment for the campus. He said the project represents UCR’s long-standing values of education and student growth.
Read More...
“I’m looking forward to having everybody back on campus as soon as this pandemic is over so we can all be in the building and enjoy a brand-new classroom building,” he said.
The project began construction in late 2019 and is expected to be completed by August 2021, said Mihai Gavan, a project manager with the Office of Planning, Design and Construction.
Construction Progress Pictures
Temporary Construction Fence Map
The majority of the construction fence has been removed from the site. The Student Success Center and its neighboring buildings are currently not impacted by any temporary construction fence.
Student Success Center Updates
-
950512 SSC Project Notification #1
950512 SSC Project Notification #1
Please be advised that the following activities will be occurring from 7:00AM to 5:00PM on the Student Success Center Site and adjacent areas during the week of September 3rd through September 6th. The activities will occur in the areas identified in the attached exhibits.
Underground utility location
- Locate underground utilities and make visible with removable paint.
- Pothole designated locations after survey is complete for specific invert elevation determination.
Site survey
- Opening manholes to get bottom of tunnel elevations, bottom of vault elevation, tracing elevations.
- Working with equipment to obtain topographic elevations of existing grades.
- Survey and identify existing utilities, trees, landscape planter areas, walkways, benches, existing buildings, existing walls, fire lanes, etc..
- Survey team will be a crew of two.
Boring samples
- Provide multiple boring samples at the locations specified in the Proposed Boring Locations Exhibit.
The Inspector of Record and PM team will be overseeing these activities with the required support from our Facilities Services partners.
Our team is not anticipating any impact to the adjacent buildings, occupants or any disruptions to the campus activity.
Thank you!
-
950512 SSC Project Notification #2
950512 SSC Project Notification #2
Please be advised that the following activities will be occurring from 6:00AM to 3:00PM on the Student Success Center site and adjacent areas on Monday and Tuesday of next week. The activities will occur in the areas identified in the attached exhibit.
Electrical survey
- Opening manholes.
- Confirm locations of existing campus infrastructure.
Underground utility location
- Locate underground utilities and make visible with removable paint.
- Pothole/trench designated locations for specific invert elevation determination and location confirmation.
The Inspector of Record and PM team will be overseeing these activities with the required support from our Facilities Services partners.
Our team is not anticipating any impact to the adjacent buildings, occupants or any major disruptions to the campus activity.
Thank you!
-
950512 SSC Construction Alert #1
950512 SSC Construction Alert #1
Please be advised that the following activities will be occurring from 6:00AM to 4:00PM on the Student Success Center site and adjacent areas during the week of November 18th through November 22nd.
- Site fence installation (equipment: flatbed truck and trailer, air compressor);
- Live feed camera installation (equipment: truck, ladders);
- Site office trailer delivery and installation (equipment: truck, air compressors, screw guns, hammers, skil-saw, ladders);
- Site control survey (equipment: truck, total station, hammers);
- Selective site demo (equipment: concrete saw, jackhammer, skid steer, dump truck, vibra plates, shovels).
Continuous noises on site: Construction equipment (back-up alarms), delivery trucks (back-up alarms), forklifts, boom lifts, scissor lifts, saws, screw guns, and hammers.
The Student Success Center Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
950512 SSC Construction Alert #2
950512 SSC Construction Alert #2
Please be advised that the following activities will be occurring from 6:00AM to 4:00PM on the Student Success Center site and adjacent areas during the week of November 25th through November 29th.
- Material and equipment deliveries (equipment: trucks and trailers, forklift);
- Concrete sawcut and removal (equipment: gas powered saw, large vacuum);
- Site and utilities excavation (equipment: backhoe);
- Stormwater Pollution Prevention Plan (SWPPP) installation (equipment: delivery truck, forklift, tractor);
- Trailer deck install (equipment: delivery truck, hammers, screw guns);
- Generator install (equipment: delivery truck, back up alarm, hammers, screw guns);
- Selective site demo (equipment: concrete saw, jackhammer, skid steer, dump truck, vibra plates, shovels).
Continuous noises on site: Construction equipment (back-up alarms), delivery trucks (back-up alarms), forklifts, boom lifts, scissor lifts, saws, screw guns, and hammers.
The Student Success Center Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
950512 SSC Construction Alert #3
950512 SSC Construction Alert #3
Please be advised that the following activities will be occurring from 6:00AM to 4:00PM on the Student Success Center site and adjacent areas during the week of December 2nd through December 6th:
- Material and equipment deliveries (equipment: trucks and trailers, forklift);
- Concrete sawcut and removal (equipment: truck, tractor, gas powered saw, jack hammer, large vacuum);
- Site and utilities excavation (equipment: backhoe);
- Trailer deck install and furniture deliveries (equipment: delivery truck, hammers, screw guns);
- Temporary generator install (equipment: delivery truck, back up alarm, hammers, screw guns);
- Data wiring and network connection for trailers (equipment: drills).
Continuous noises on site: Construction equipment (back-up alarms), delivery trucks (back-up alarms), forklifts, boom lifts, scissor lifts, saws, screw guns, and hammers.
The Student Success Center Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
950512 SSC - Construction Alert #4
950512 SSC - Construction Alert #4
Please be advised that the following activities will be occurring from 5:00AM to 4:00PM on the Student Success Center site and adjacent areas during the week of December 9th through December 14th:
- Material and equipment deliveries (equipment: trucks and trailers, forklift);
- Form fabrication (equipment: generators, saws, screw guns, hammers);
- Concrete sawcut and removal – scheduled for early mornings up to 7:00AM (equipment: truck, tractor, gas powered saw, jack hammer, large vacuum);
- Site and utilities excavation (equipment: backhoe);
- Selective site demo (equipment: dump truck, dozer, saws, jackhammer, skid steer, vibra plates, shovels);
- Stormwater Pollution Prevention Plan (SWPPP) installation (equipment: delivery truck, forklift, tractor);
- Trailer deck install and furniture deliveries (equipment: delivery truck, hammers, screw guns).
In addition please be advised and reminded that an Electrical Shutdown/Service Interruption is scheduled for December 15th, as shown in the attached notification.
Continuous noises on site: Construction equipment (back-up alarms), delivery trucks (back-up alarms), forklifts, jackhammers, boom lifts, scissor lifts, saws, screw guns, and hammers.
The Student Success Center Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
950512 SSC - Construction Alert #5
950512 SSC Construction Alert #5
Please be advised that the following activities will be occurring from 5:00AM to 8:00PM on the Student Success Center site and adjacent areas on Saturday December 14th and Sunday, December 15th:
- Concrete sawcut and removal (equipment: truck, tractor, gas powered saw, jack hammer, vacuum);
- Utilities excavation – electrical (equipment: backhoe);
- Electrical Shutdown/Service Interruption is scheduled for December 15th, as shown in the attached notification.
Please be advised that the following activities will be occurring from 5:00AM to 4:00PM on the Student Success Center site and adjacent areas during the week of December 16th through December 21st:
- Material and equipment deliveries (equipment: trucks and trailers, forklift);
- New temporary fence installation for sewer connection along Arts Mall – see revised map below and attached drawing (equipment: flatbed truck and trailer, air compressor). The pathways going East-West will be impacted at times in the new temporary fence areas as required to get the areas ready for the work;
- Form fabrication (equipment: generators, saws, screw guns, hammers);
- Concrete sawcut and removal for utilities connection (equipment: truck, tractor, gas powered saw, jack hammer, large vacuum);
- Site and utilities (electrical, sewer, water, chilled water) excavation (equipment: backhoe);
- Selective site demo (equipment: dump truck, dozer, saws, jackhammer, skid steer, vibra plates, shovels);
- Trailer deck install and furniture deliveries (equipment: delivery truck, hammers, screw guns).
Continuous noises on site: Construction equipment (back-up alarms), delivery trucks (back-up alarms), forklifts, generators, jackhammers, boom lifts, scissor lifts, saws, screw guns, and hammers.
The Student Success Center Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
950512 SSC - Construction Alert #6
950512 SSC Construction Alert #6
Please be advised that the following activities will be occurring from 5:00AM to 4:00PM on the Student Success Center site and adjacent areas on Saturday December 21st:
- Installation of underground chilled water pipe (equipment: forklift, generators, welding machine);
- Utilities excavation – sewer line along Arts Mall (equipment: backhoe).
Please be advised that the following activities will be occurring from 5:00AM to 4:00PM on the Student Success Center site and adjacent areas during the week of December 23rd through December 28th:
- Material and equipment deliveries (equipment: trucks and trailers, forklift);
- Modified temporary fence for sewer connection along Arts Mall – see revised map below. The pathways going East-West will be impacted at times in the new temporary fence areas as required to get the areas ready for the work;
- Concrete sawcut and removal (equipment: truck, tractor, gas powered saw, jack hammer, large vacuum);
- Site and utilities (electrical, sewer, water, chilled water) excavation (equipment: backhoe);
- Pipe installation (equipment: forklift, gas and electric saws);
- Selective site demo (equipment: dump truck, dozer, saws, jackhammer, skid steer, vibra plates, shovels);
- Trailer deck install (equipment: delivery truck, hammers, skill saws, screw guns).
Continuous noises on site: Construction equipment (back-up alarms), delivery trucks (back-up alarms), forklifts, generators, jackhammers, boom lifts, scissor lifts, saws, screw guns, and hammers.
The Student Success Center Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
950512 SSC - Construction Alert #7
950512 SSC Construction Alert #7
Please be advised that the following activities will be occurring from 5:00AM to 4:00PM on the Student Success Center site and adjacent areas on Saturday December 28th and Sunday December 29th:
- Selective site demo (equipment: dump truck, dozer, saws, jackhammer, skid steer, vibra plates, shovels);
- Installation of underground pipe for the high voltage (equipment: forklift, backhoe, generators);
- Utilities excavation – sewer line along Arts Mall (equipment: backhoe);
- Installation of underground pipe for sewer connection (equipment: backhoe, vibra plates, shovels, generators).
Please be advised that the following activities will be occurring from 5:00AM to 4:00PM on the Student Success Center site and adjacent areas during the week of December 30th through January 4th:
- Material and equipment deliveries (equipment: trucks and trailers, forklift);
- Modified temporary fence for sewer connection along Arts Mall – see revised map below. The pathways going East-West will be impacted at times in the new temporary fence areas as required to get the areas ready for the work;
- Temporary construction access road mobilization (equipment: trucks, jack hammer);
- Concrete sawcut and removal (equipment: truck, tractor, gas powered saw, jack hammer, large vacuum);
- Site and utilities (electrical, sewer, water, chilled water) excavation (equipment: dump truck, backhoe);
- Utility pipe installation (equipment: forklift, welding machines, generators, gas and electric saws);
- Selective site demo (equipment: dump truck, dozer, saws, jackhammer, skid steer, vibra plates, shovels);
- Trailer deck install (equipment: delivery truck, hammers, skill saws, screw guns).
Continuous noises on site: Construction equipment (back-up alarms), delivery trucks (back-up alarms), forklifts, generators, jackhammers, boom lifts, scissor lifts, saws, screw guns, and hammers.
The Student Success Center Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
950512 SSC - Construction Alert #8
950512 SSC Construction Alert #8
Please be advised that the following activities will be occurring from 5:00AM to 4:00PM on the Student Success Center site and adjacent areas on Saturday January 4th:
- Temporary construction access road (equipment: trucks, jack hammer);
- Excavation and installation of underground pipe for the high voltage (equipment: forklift, backhoe, generators).
Please be advised that the following activities will be occurring from 5:00AM to 4:00PM on the Student Success Center site and adjacent areas during the week of January 6th through January 11th:
- Material and equipment deliveries (equipment: trucks and trailers, forklift);
- Modified temporary fence for sewer connection along Arts Mall – see revised map below. The pathways going East-West will be impacted at times in the new temporary fence areas as required to get the areas ready for the work;
- Form fabrication (equipment: generators, saws, screw guns, hammers);
- Concrete sawcut and removal (equipment: truck, tractor, gas powered saw, jack hammer, large vacuum);
- Site and utilities (electrical, sewer, water, chilled water) excavation and backfill (equipment: dump truck, backhoe);
- Utility pipe installation (equipment: forklift, welding machines, generators, gas and electric saws);
- Selective site demo (equipment: dump truck, dozer, saws, jackhammer, skid steer, vibra plates, shovels).
Continuous noises on site: Construction equipment (back-up alarms), delivery trucks (back-up alarms), forklifts, generators, jackhammers, boom lifts, scissor lifts, saws, screw guns, and hammers.
The Student Success Center Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
950512 SSC - Construction Alert #9
950512 SSC Construction Alert #9
Please be advised that the following activities will be occurring from 5:00AM to 4:00PM on the Student Success Center site and adjacent areas on Saturday January 11th:
- Backfill of utility trenches (equipment: slurry trucks, backhoe, compactor);
- Excavation for the high voltage (equipment: forklift, backhoe, generators).
Please be advised that the following activities will be occurring from 5:00AM to 4:00PM on the Student Success Center site and adjacent areas during the week of January 13th through January 18th:
- Material and equipment deliveries (equipment: trucks and trailers, forklift);
- Modified temporary fence for sewer connection along Arts Mall – see revised map below. The pathways going East-West will be impacted at times in the new temporary fence areas as required to get the areas ready for the work;
- Concrete sawcut and removal (equipment: truck, tractor, gas powered saw, jack hammer, large vacuum);
- Form fabrication (equipment: generators, saws, screw guns, hammers);
- Site and utilities (electrical, sewer, water, chilled water) excavation and backfill (equipment: dump truck, backhoe);
- Utility pipe installation (equipment: forklift, welding machines, generators, gas and electric saws).
Continuous noises on site: Construction equipment (back-up alarms), delivery trucks (back-up alarms), forklifts, generators, jackhammers, boom lifts, scissor lifts, saws, screw guns, and hammers.
The Student Success Center Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
950512 SSC - Construction Alert #10
950512 SSC Construction Alert #10
Please be advised that the following activities will be occurring from 5:00AM to 4:00PM on the Student Success Center site and adjacent areas during the week of January 20th through January 25th:
- Material and equipment deliveries (equipment: trucks and trailers, forklift);
- Modified temporary fence for sewer connection along Arts Mall – see revised map below. The pathways going East-West will be impacted at times in the new temporary fence areas as required to get the areas ready for the work;
- Concrete sawcut and removal (equipment: truck, tractor, gas powered saw, jack hammer, large vacuum);
- Form fabrication (equipment: generators, saws, screw guns, hammers);
- Site and utilities (electrical, sewer, water, chilled water) excavation and backfill (equipment: dump truck, compactor, tractor, backhoe);
- Utility pipe installation (equipment: concrete trucks, backhoe, forklift, welding machines, generators, gas and electric saws).
Continuous noises on site: Construction equipment (back-up alarms), delivery trucks (back-up alarms), forklifts, generators, jackhammers, boom lifts, scissor lifts, saws, screw guns, and hammers.
The Student Success Center Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
950512 SSC - Construction Alert #11
950512 SSC Construction Alert #11
Please be advised that the following activities will be occurring from 5:00AM to 4:00PM on the Student Success Center site and adjacent areas on Saturday January 25th:
- Backfill of utility trenches (equipment: slurry trucks, backhoe, compactor);
- Form work for V-4D 12kV electrical vault (equipment: generators, saws, screw guns, hammers).
Please be advised that the following activities will be occurring from 5:00AM to 4:00PM on the Student Success Center site and adjacent areas during the week of January 27th through February 1st:
- Material and equipment deliveries (equipment: trucks and trailers, forklift);
- Backfill of utility trenches (equipment: backhoe, compactor);
- Modified temporary fence for sewer connection along Arts Mall – see revised map below. The pathways going East-West will be impacted at times in the new temporary fence areas as required to get the areas ready for the work;
- Concrete demo and removal (equipment: truck, tractor, gas powered saw, jack hammer, large vacuum);
- Vault construction (equipment: concrete trucks, forklifts, generators, saws, screw guns, hammers);
- Form fabrication and stem walls (equipment: generators, saws, screw guns, hammers);
- Over excavation (equipment: excavator, skip loader, compactor). This activity will generate vibration as we detailed in neighborhood meeting this week.
Continuous noises on site: Construction equipment (back-up alarms), delivery trucks (back-up alarms), forklifts, generators, jackhammers, boom lifts, scissor lifts, saws, screw guns, and hammers.
The Student Success Center Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
950512 SSC - Construction Alert #12
950512 SSC Construction Alert #12
Please be advised that the following activities will be occurring from 5:00AM to 4:00PM on the Student Success Center site and adjacent areas on Saturday February 1st:
- Excavation and conduit installation at the new high voltage 12kV switches (equipment: excavator, forklift, compactor, screw guns);
- Spoils removal (equipment: backhoe, dump truck).
Please be advised that the following activities will be occurring from 5:00AM to 4:00PM on the Student Success Center site and adjacent areas during the week of February 3rd through February 8th:
- Material deliveries (equipment: trucks and trailers, forklift);
- Removal of domestic water pipe (equipment: excavator);
- Strip concrete vault (equipment: forklift, hammers, saws, drills);
- Backfill of utility trenches (equipment: tractor, backhoe, compactor);
- Conduit installation and encasement (equipment: concrete truck, backhoe, forklift, saws, hammers);
- Storm drain installation (equipment: backhoe, saws);
- Form fabrication and stem walls (equipment: generators, saws, screw guns, hammers);
- Pad and over excavation (equipment: excavator, skip loader, compactor). This activity will generate vibration;
- Modified temporary fence for sewer connection along Arts Mall – see revised map below. The pathways going East-West will be impacted at times in the new temporary fence areas as required to get the areas ready for the work.
Continuous noises on site: Construction equipment (back-up alarms), delivery trucks (back-up alarms), forklifts, generators, jackhammers, boom lifts, scissor lifts, saws, screw guns, and hammers.
The Student Success Center Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
950512 SSC - Construction Alert #13
950512 SSC Construction Alert #13
Please be advised that the following activities will be occurring from 5:00AM to 4:00PM on the Student Success Center site and adjacent areas on Saturday February 8th:
- Electric cable installation and backfill at the new high voltage switches (equipment: excavator, forklift, compactor, delivery truck, cable puller, screw guns);
- Spoils removal (equipment: backhoe, dump truck).
Please be advised that the following activities will be occurring from 5:00AM to 4:00PM on the Student Success Center site and adjacent areas during the week of February 10th through February 15th:
- Material deliveries (equipment: trucks and trailers, forklift);
- Backfill of utility trenches (equipment: tractor, backhoe, compactor);
- Electric cable installation and conduit encasement (equipment: delivery truck, cable puller, concrete truck, backhoe, forklift, saws, hammers);
- Storm drain installation (equipment: backhoe, saws);
- Form fabrication and stem walls (equipment: generators, saws, screw guns, hammers);
- Over excavation and compaction (equipment: excavator, skip loader, compactor). This activity will generate vibration;
- Concrete removal (equipment: dump truck, concrete saws, jackhammers);
- Concrete placement (equipment: concrete truck);
- Modified temporary fence for sewer connection along Arts Mall – see revised map below. The pathways going East-West will be impacted at times in the new temporary fence areas as required to get the areas ready for the work;
- Proposed power shutdown / interruption on Saturday, February 15 – see attached Notification.
Continuous noises on site: Construction equipment (back-up alarms), delivery trucks (back-up alarms), forklifts, generators, jackhammers, boom lifts, scissor lifts, saws, screw guns, and hammers.
The Student Success Center Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
950512 SSC - Construction Alert #14
950512 SSC Construction Alert #14
Please be advised that the following activities will be occurring from 5:00AM to 7:00PM on the Student Success Center site and adjacent areas on Saturday February 15th:
- Planned power shutdown / interruption on Saturday, February 15 – see attached Reminder Notification;
- Electrical work related to the high voltage connections.
Please be advised that the following activities will be occurring from 5:00AM to 4:00PM on the Student Success Center site and adjacent areas during the week of February 17th through February 22nd:
- Material deliveries (equipment: trucks and trailers, forklift);
- Backfill at utility tunnel (equipment: tractor, backhoe, compactor);
- Communication conduit installation at tunnel (equipment: backhoe, concrete truck, core drilling machine);
- Storm drain installation (equipment: backhoe, skid steer loader);
- Form fabrication and placing (equipment: generators, saws, screw guns, hammers);
- Excavation and compaction (equipment: excavator, skip loader, compactor). This activity will generate vibration to the surrounding buildings;
- Excavate footings (equipment: backhoe);
- Modification of temporary fence along Arts Mall.
Items listed in red: Please note that this activity may potentially disrupt the occupants in adjacent buildings;
Continuous noises on site: Construction equipment (back-up alarms), delivery trucks (back-up alarms), forklifts, generators, jackhammers, boom lifts, scissor lifts, saws, screw guns, and hammers.
The Student Success Center Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
950512 SSC - Construction Alert #15
950512 SSC Construction Alert #15
Please be advised that the following activities will be occurring from 5:00AM to 4:00PM on the Student Success Center site and adjacent areas during the week of February 24th through February 29th:
- Material deliveries (equipment: trucks and trailers, forklift);
- Backfill at utility tunnel (equipment: tractor, backhoe, compactor);
- Excavate footings (equipment: backhoe, skip loader);
- Form fabrication and placing (equipment: generators, saws, screw guns, hammers);
- Excavation and compaction (equipment: excavator, skip loader, compactor). This activity will generate vibration to the surrounding buildings;
- High voltage concrete encasement demolition (equipment: backhoe, jackhammer). This activity can generate noise and vibration;
- Rebar delivery and installation (equipment: delivery truck, forklift).
Items listed in red: Please note that this activity may potentially disrupt the occupants in adjacent buildings;
Continuous noises on site: Construction equipment (back-up alarms), delivery trucks (back-up alarms), forklifts, generators, jackhammers, boom lifts, scissor lifts, saws, screw guns, and hammers.
The Student Success Center Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
950512 SSC - Construction Alert #16
950512 SSC Construction Alert #16
Please be advised that the following activities will be occurring from 5:00AM to 4:00PM on the Student Success Center site and adjacent areas during the week of March 2nd through March 7th:
- Material deliveries (equipment: trucks and trailers, forklift);
- Excavate footings (equipment: backhoe, skip loader);
- Concrete demo (equipment: dump trucks, jackhammers);
- Backfill (equipment: tractor, backhoe, compactor);
- Form placing (equipment: forklift, saws, screw guns, hammers);
- Excavation and compaction (equipment: excavator, skip loader, compactor). This activity will generate vibration to the surrounding buildings;
- Rebar delivery and installation (equipment: delivery truck, forklift);
- Concrete placement (equipment: concrete trucks, concrete vibrators).
Items listed in red: Please note that this activity may potentially disrupt the occupants in adjacent buildings;
Continuous noises on site: Construction equipment (back-up alarms), delivery trucks (back-up alarms), forklifts, generators, jackhammers, boom lifts, scissor lifts, saws, screw guns, and hammers.
The Student Success Center Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
950512 SSC - Construction Alert #17
950512 SSC Construction Alert #17
Please be advised that the following activities will be occurring from 5:00AM to 4:00PM on the Student Success Center site and adjacent areas on Saturday March 7th:
- Excavation and compaction (equipment: excavator, front loader, skip loader, compactor). This activity will generate vibration to the surrounding buildings.
Please be advised that the following activities will be occurring from 5:00AM to 4:00PM on the Student Success Center site and adjacent areas during the week of March 9th through March 14th:
- Material deliveries (equipment: trucks and trailers, forklift);
- Excavation and compaction (equipment: excavator, front loader, skip loader, compactor). This activity will generate vibration to the surrounding buildings;
- Excavate footings (equipment: backhoe, skip loader);
- Form placing (equipment: forklift, saws, screw guns, hammers);
- Rebar delivery and installation (equipment: delivery truck, forklift);
- Underground utilities (equipment: excavator, backhoe).
Items listed in red: Please note that this activity may potentially disrupt the occupants in adjacent buildings;
Continuous noises on site: Construction equipment (back-up alarms), delivery trucks (back-up alarms), forklifts, generators, jackhammers, boom lifts, scissor lifts, saws, screw guns, and hammers.
The Student Success Center Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
950512 SSC - Construction Alert #18
950512 SSC Construction Alert #18
Please be advised that the following activities will be occurring from 5:00AM to 4:00PM on the Student Success Center site and adjacent areas during the week of March 16th through March 21st:
- Material deliveries (equipment: trucks and trailers, forklift);
- Rebar installation (equipment: delivery truck, forklift, torches);
- Form retaining wall and columns (equipment: forklift, drills, hammers, saws);
- Waterproof tunnel (equipment: delivery truck, forklift);
- Concrete placement (equipment: concrete trucks, pump truck, concrete vibrators);
- Strip forms (equipment: forklift, drills, hammers, saws).
Items listed in red: Please note that this activity may potentially disrupt the occupants in adjacent buildings;
Continuous noises on site: Construction equipment (back-up alarms), delivery trucks (back-up alarms), forklifts, generators, jackhammers, boom lifts, scissor lifts, saws, screw guns, and hammers.
The Student Success Center Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
950512 SSC - Construction Alert #19
950512 SSC Construction Alert #19
Please be advised that the following activities will be occurring from 5:00AM to 4:00PM on the Student Success Center site and adjacent areas during the week of March 23rd through March 28th:
- Material deliveries (equipment: trucks and trailers, forklift);
- Rebar installation (equipment: delivery truck, forklift, torches);
- Strip forms (equipment: forklift, drills, hammers, saws);
- Excavate footings (equipment: backhoe, skip loader);
- Backfill and grading (equipment: front loader, skip loader, compactor);
- Slurry pour at the chilled water line connection (equipment: concrete trucks).
Items listed in red: Please note that this activity may potentially disrupt the occupants in adjacent buildings;
Continuous noises on site: Construction equipment (back-up alarms), delivery trucks (back-up alarms), forklifts, generators, jackhammers, boom lifts, scissor lifts, saws, screw guns, and hammers.
The Student Success Center Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
950512 SSC - Construction Alert #20
950512 SSC Construction Alert #20
Please be advised that the following activities will be occurring from 5:00AM to 4:00PM on the Student Success Center site and adjacent areas during the week of March 30th through April 4th:
- Material deliveries (equipment: trucks and trailers, forklift);
- Form placing for footings and columns (equipment: forklift, skill saws, hammers, drills);
- Rebar installation for footings and columns (equipment: delivery truck, forklift, torches);
- Underground conduit installation (equipment: mini excavator, concrete truck, forklift);
- Excavate footings (equipment: backhoe, skip loader);
- Concrete placement for footings, retaining wall and mockups (equipment: concrete trucks, pump truck, concrete vibrators);
- Backfill (equipment: excavator, front loader, skip loader, compactor).
Items listed in red: Please note that this activity may potentially disrupt the occupants in adjacent buildings;
Continuous noises on site: Construction equipment (back-up alarms), delivery trucks (back-up alarms), forklifts, generators, jackhammers, boom lifts, scissor lifts, saws, screw guns, and hammers.
The Student Success Center Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
950512 SSC - Construction Alert #21
950512 SSC Construction Alert #21
Please be advised that the following activities will be occurring from 5:00AM to 4:00PM on the Student Success Center site and adjacent areas on Saturday April 4th:
- Concrete placement for footings and columns (equipment: concrete trucks, pump truck, concrete vibrators);
- Backfill (equipment: excavator, front loader, skip loader, compactor).
Please be advised that the following activities will be occurring from 5:00AM to 4:00PM on the Student Success Center site and adjacent areas during the week of April 6th through April 11th:
- Material deliveries (equipment: trucks and trailers, forklift);
- Form placing (equipment: forklift, skill saws, hammers, drills);
- Rebar deliveries and installation (equipment: delivery truck, forklift, torches);
- Underground utilities installation (equipment: mini excavator, forklift);
- Excavate footings (equipment: backhoe, skip loader);
- Concrete placement for footings, retaining wall and mockups (equipment: concrete trucks, pump truck, concrete vibrators);
- Backfill (equipment: excavator, front loader, skip loader, compactor).
Items listed in red: Please note that this activity may potentially disrupt the occupants in adjacent buildings;
Continuous noises on site: Construction equipment (back-up alarms), delivery trucks (back-up alarms), forklifts, generators, jackhammers, boom lifts, scissor lifts, saws, screw guns, and hammers.
The Student Success Center Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
950512 SSC - Construction Alert #22
950512 SSC Construction Alert #22
Please be advised that the following activities will be occurring from 5:00AM to 4:00PM on the Student Success Center site and adjacent areas on Saturday April 11th:
- Starter forms installation (equipment: forklift, skill saws, hammers, drills);
- Reskin form panels (equipment: forklift, skill saws, hammers, drills);
- Pump rain water from building footprint area (equipment: pumps).
Please be advised that the following activities will be occurring from 5:00AM to 4:00PM on the Student Success Center site and adjacent areas during the week of April 13th through April 18th:
- Material deliveries (equipment: trucks and trailers, forklift);
- Form placing (equipment: forklift, skill saws, hammers, drills);
- Rebar deliveries and installation (equipment: delivery truck, forklift, torches);
- Underground utilities installation (equipment: mini excavator, forklift);
- Dewater footings (equipment: backhoe, pumps);
- Excavate footings (equipment: backhoe, skip loader);
- Concrete placement (equipment: concrete trucks, pump truck, concrete vibrators);
- Building pad grading (equipment: skip loader);
- Backfill footings and building pad (equipment: excavator, front loader, skip loader, compactor).
Items listed in red: Please note that this activity may potentially disrupt the occupants in adjacent buildings;
Continuous noises on site: Construction equipment (back-up alarms), delivery trucks (back-up alarms), forklifts, generators, jackhammers, boom lifts, scissor lifts, saws, screw guns, and hammers.
The Student Success Center Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
950512 SSC - Construction Alert #23
950512 SSC Construction Alert #23
Please be advised that the following activities will be occurring from 5:00AM to 4:00PM on the Student Success Center site and adjacent areas on Saturday April 18th:
- Concrete pour at elevator pit (equipment: concrete trucks, pump truck, concrete vibrators);
- Formwork and scaffold brackets (equipment: forklift, skill saws, hammers, drills).
Please be advised that the following activities will be occurring from 5:00AM to 4:00PM on the Student Success Center site and adjacent areas during the week of April 20th through April 25th:
- Material deliveries (equipment: trucks and trailers, forklift);
- Form building and installation (equipment: forklift, skill saws, hammers, drills);
- Rebar deliveries and installation (equipment: delivery truck, forklift, torches);
- Underground building utilities piping (equipment: excavator, forklift, compactor);
- Waterproofing (equipment: powder activated shot gun, screw guns, saws);
- Footings excavation (equipment: backhoe, skip loader);
- Concrete placement (equipment: concrete trucks, pump truck, concrete vibrators);
- Site storm drain piping (equipment: excavator, compactor, saws);
- Backfill footings and building pad (equipment: excavator, front loader, skip loader, compactor).
Items listed in red: Please note that this activity may potentially disrupt the occupants in adjacent buildings;
Continuous noises on site: Construction equipment (back-up alarms), delivery trucks (back-up alarms), forklifts, generators, jackhammers, boom lifts, scissor lifts, saws, screw guns, and hammers.
The Student Success Center Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
950512 SSC - Construction Alert #24
950512 SSC Construction Alert #24
Please be advised that the following activities will be occurring from 5:00AM to 4:00PM on the Student Success Center site and adjacent areas on Saturday April 25th:
- Form panels installation (equipment: forklift, skill saws, hammers, drills);
- Rebar installation (equipment: forklift, torches).
Please be advised that the following activities will be occurring from 5:00AM to 4:00PM on the Student Success Center site and adjacent areas during the week of April 27th through May 2nd:
- Material deliveries (equipment: trucks and trailers, forklift);
- Form installation and removal (equipment: forklift, skill saws, hammers, drills);
- Rebar deliveries and installation (equipment: delivery truck, forklift, torches);
- Underground building utilities – electrical, plumbing (equipment: excavator, forklift, compactor, saws);
- Waterproofing (equipment: powder activated shot gun, screw guns, saws);
- Concrete placement (equipment: concrete trucks, pump truck, concrete vibrators);
- Site storm drain piping (equipment: excavator, compactor, saws);
- Backfill footings and building pad (equipment: excavator, front loader, skip loader, compactor);
- Proposed power shutdown for CHASS INT North and South on Thursday, May 7 – see attached Notification.
Items listed in red: Please note that this activity may potentially disrupt the occupants in adjacent buildings;
Continuous noises on site: Construction equipment (back-up alarms), delivery trucks (back-up alarms), forklifts, generators, jackhammers, boom lifts, scissor lifts, saws, screw guns, and hammers.
The Student Success Center Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
950512 SSC - Construction Alert #25
950512 SSC Construction Alert #25
Please be advised that the following activities will be occurring from 5:00AM to 4:00PM on the Student Success Center site and adjacent areas during the week of May 4th through May 9th:
- Material deliveries (equipment: trucks and trailers, forklift);
- Form installation (equipment: forklift, skill saws, hammers, drills);
- Excavate footings (equipment: backhoe, skip loader);
- Rebar deliveries and installation (equipment: delivery truck, forklift, torches);
- Underground building utilities – electrical, plumbing (equipment: excavator, forklift, compactor, saws);
- Backfill site storm drain (equipment: excavator, compactor, saws);
- Backfill footings and building pad (equipment: excavator, front loader, skip loader, compactor);
- Power shutdown for CHASS INT North and South on Thursday, May 7 – see attached Notification.
Items listed in red: Please note that this activity may potentially disrupt the occupants in adjacent buildings;
Continuous noises on site: Construction equipment (back-up alarms), delivery trucks (back-up alarms), forklifts, generators, jackhammers, boom lifts, scissor lifts, saws, screw guns, and hammers.
The Student Success Center Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
950512 SSC - Construction Alert #26
950512 SSC Construction Alert #26
Please be advised that the following activities will be occurring from 5:00AM to 4:00PM on the Student Success Center site and adjacent areas on Saturday May 9th:
- Form panels installation (equipment: forklift, skill saws, hammers, drills);
- Rebar installation (equipment: forklift, torches).
Please be advised that the following activities will be occurring from 5:00AM to 4:00PM on the Student Success Center site and adjacent areas during the week of May 11th through May 16th:
- Material deliveries (equipment: trucks and trailers, forklift);
- Form installation (equipment: forklift, skill saws, hammers, drills);
- Rebar deliveries and installation (equipment: delivery truck, forklift, torches);
- Concrete placement – walls and columns (equipment: concrete trucks, pump truck, concrete vibrators);
- Excavate manhole (equipment: concrete truck, backhoe, skip loader);
- Underground building utilities – electrical, plumbing (equipment: excavator, forklift, compactor, saws);
- Backfill underground plumbing (equipment: excavator, compactor, saws);
- Backfill footings and building pad (equipment: excavator, front loader, skip loader, compactor).
Items listed in red: Please note that this activity may potentially disrupt the occupants in adjacent buildings;
Continuous noises on site: Construction equipment (back-up alarms), delivery trucks (back-up alarms), forklifts, generators, jackhammers, boom lifts, scissor lifts, saws, screw guns, and hammers.
The Student Success Center Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
950512 SSC - Construction Alert #27
950512 SSC Construction Alert #27
Please be advised that the following activities will be occurring from 5:00AM to 4:00PM on the Student Success Center site and adjacent areas on Saturday May 16th:
- Form panels installation (equipment: forklift, skill saws, hammers, drills);
- Subgrade prep (equipment: skip loader, vibratory plate, compactor).
Please be advised that the following activities will be occurring from 5:00AM to 4:00PM on the Student Success Center site and adjacent areas during the week of May 18th through May 23rd:
- Material deliveries (equipment: trucks and trailers, forklift);
- Form installation (equipment: forklift, skill saws, hammers, drills);
- Rebar installation (equipment: delivery truck, forklift, torches);
- Strip forms (equipment: crane, hammers, forklift);
- Concrete placement – walls and columns (equipment: concrete trucks, pump truck, concrete vibrators);
- Underground building utilities – electrical, plumbing (equipment: mini-excavator, forklift, compactor, saws);
- Backfill underground utilities (equipment: excavator, compactor, saws);
- Subgrade prep (equipment: skip loader, vibratory plate, compactor).
Items listed in red: Please note that this activity may potentially disrupt the occupants in adjacent buildings;
Continuous noises on site: Construction equipment (back-up alarms), delivery trucks (back-up alarms), forklifts, generators, jackhammers, boom lifts, scissor lifts, saws, screw guns, and hammers.
The Student Success Center Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
950512 SSC - Construction Alert #28
950512 SSC Construction Alert #28
Please be advised that the following activities will be occurring from 5:00AM to 4:00PM on the Student Success Center site and adjacent areas on Saturday May 23rd:
- Underground building utilities – electrical (equipment: mini-excavator, forklift, compactor, saws);
- Subgrade prep (equipment: skip loader, vibratory plate, compactor).
Please be advised that the following activities will be occurring from 5:00AM to 4:00PM on the Student Success Center site and adjacent areas during the week of May 25th through May 30th :
- Material deliveries (equipment: trucks and trailers, forklift);
- Rebar delivery and installation (equipment: delivery truck, forklift, torches);
- Strip forms (equipment: crane, hammers, forklift);
- Concrete placement – slab on grade (equipment: concrete trucks, pump truck, power finishers);
- Under slab building utilities – electrical (equipment: mini-excavator, forklift, compactor, saws);
- Grading (equipment: skip loader, skid steer);
- Backfill underground utilities and building pad (equipment: excavator, compactor).
Items listed in red: Please note that this activity may potentially disrupt the occupants in adjacent buildings;
Continuous noises on site: Construction equipment (back-up alarms), delivery trucks (back-up alarms), forklifts, generators, jackhammers, boom lifts, scissor lifts, saws, screw guns, and hammers.
The Student Success Center Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
950512 SSC Construction Alert #29
950512 SSC Construction Alert #29
Please be advised that the following activities will be occurring from 5:00AM to 4:00PM on the Student Success Center site and adjacent areas during the week of June 1st through June 6th:
- Material deliveries (equipment: trucks and trailers, forklift);
- Subgrade prep (equipment: skip loader, vibratory plate, compactor);
- Rebar installation (equipment: delivery truck, forklift, torches);
- Concrete placement – slab on grade (equipment: concrete trucks, pump truck, power finishers, concrete saws);
- Level 2 deck forms installation (equipment: crane forklift, drills, skill saws, hammers);
- Inserts, deck sleeves and embeds (equipment: drills, saws, hammers).
Items listed in red: Please note that this activity may potentially disrupt the occupants in adjacent buildings;
Continuous noises on site: Construction equipment (back-up alarms), delivery trucks (back-up alarms), forklifts, generators, jackhammers, boom lifts, scissor lifts, saws, screw guns, and hammers.
The Student Success Center Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
950512 SSC Construction Alert #30
950512 SSC Construction Alert #30
Please be advised that the following activities will be occurring from 5:00AM to 4:00PM on the Student Success Center site and adjacent areas on Saturday June 6th:
- Level 2 deck forms installation (equipment: crane, forklift, drills, skill saws, hammers);
Please be advised that the following activities will be occurring from 5:00AM to 4:00PM on the Student Success Center site and adjacent areas during the week of June 8th through June 13th:
- Material deliveries (equipment: trucks and trailers, forklift);
- Level 2 deck forms installation (equipment: crane, forklift, drills, skill saws, hammers);
- Level 2 deck rebar installation (equipment: crane, forklift);
- Inserts, deck sleeves and embeds (equipment: drills, saws, hammers);
- In slab conduit installation (equipment: forklift, band saw, sawzall, drills);
- Site grading and export (equipment: dump trucks, mini excavator, skip loader, skid steer, compactors);
- Reseeding Arts Mall project impacted areas (equipment: delivery trucks, skid steer, tiller).
Items listed in red: Please note that this activity may potentially disrupt the occupants in adjacent buildings;
Continuous noises on site: Construction equipment (back-up alarms), delivery trucks (back-up alarms), forklifts, generators, jackhammers, boom lifts, scissor lifts, saws, screw guns, and hammers.
The Student Success Center Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
950512 SSC Construction Alert #31
950512 SSC Construction Alert #31
Please be advised that the following activities will be occurring from 5:00AM to 4:00PM on the Student Success Center site and adjacent areas on Saturday June 13th:
- Level 2 deck forms installation (equipment: crane, forklift, drills, skill saws, hammers);
- Level 2 in slab conduit installation (equipment: forklift, band saw, sawzall, drills);
- Concrete demolition for storm drain on north side (equipment: truck, gas powered saw, jack hammer, vacuum).
Please be advised that the following activities will be occurring from 5:00AM to 4:00PM on the Student Success Center site and adjacent areas during the week of June 15th through June 20th:
- Material deliveries (equipment: trucks and trailers, forklift);
- Level 2 deck, columns and walls – forms installation (equipment: crane, forklift, drills, skill saws, hammers);
- Level 2 deck, columns and walls – rebar installation (equipment: crane, forklift);
- Inserts, deck sleeves and embeds (equipment: drills, saws, hammers);
- In slab conduit installation (equipment: forklift, band saw, sawzall, drills);
- Level 2 deck concrete placement (equipment: concrete trucks, pump truck, crane);
- Storm drain connections (equipment: truck, mini excavator, cut off saw).
Items listed in red: Please note that this activity may potentially disrupt the occupants in adjacent buildings;
Continuous noises on site: Construction equipment (back-up alarms), delivery trucks (back-up alarms), forklifts, generators, jackhammers, boom lifts, scissor lifts, saws, screw guns, and hammers.
The Student Success Center Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
950512 SSC Construction Alert #32
950512 SSC Construction Alert #32
Please be advised that the following activities will be occurring from 5:00AM to 4:00PM on the Student Success Center site and adjacent areas on Saturday, June 20th:
- Level 2 deck and walls – forms installation (equipment: crane, forklift, drills, skill saws, hammers).
Please be advised that the following activities will be occurring from 5:00AM to 4:00PM on the Student Success Center site and adjacent areas during the week of June 22nd through June 27th:
- Material deliveries (equipment: trucks and trailers, forklift);
- Level 2 deck, columns and walls – forms installation (equipment: trucks, crane, forklift, drills, skill saws, hammers);
- Level 2 deck, beams, vertical columns and walls – rebar installation (equipment: crane, forklift, hammers);
- Inserts, deck sleeves and embeds (equipment: lasers, drills, saws, hammers);
- Column installation – SW corner (equipment: truck, forklift, roto-hammers, hammers, welding machines);
- Embed installation (equipment: crane, forklift, hammers, drills).
Items listed in red: Please note that this activity may potentially disrupt the occupants in adjacent buildings;
Continuous noises on site: Construction equipment (back-up alarms), delivery trucks (back-up alarms), forklifts, generators, jackhammers, boom lifts, scissor lifts, saws, screw guns, and hammers.
The Student Success Center Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
950512 SSC Construction Alert #33
950512 SSC Construction Alert #33
Please be advised that the following activities will be occurring from 5:00AM to 4:00PM on the Student Success Center site and adjacent areas on Saturday, June 27th:
Level 2
- Shear walls – rebar installation (equipment: crane, forklift, drills, skill saws, hammers);
- In slab electrical rough in (equipment: lasers, drills, saws, hammers).
Please be advised that the following activities will be occurring from 5:00AM to 4:00PM on the Student Success Center site and adjacent areas during the week of June 29th through July 4th:
General
- Material deliveries (equipment: trucks and trailers, forklift).
Level 2
- Columns and shear walls – rebar installation (equipment: crane, forklift, hammers);
- Columns and shear walls – forms installation (equipment: trucks, crane, forklift, drills, skill saws, hammers);
- Deck, shear walls and columns – concrete placement (equipment: concrete trucks, pump truck, crane);
- Strip deck forms – West area (equipment: forklift, drills, hammers);
- Strip shear walls and column forms (equipment: crane, forklift, drills, hammers).
Level 3
- Deck and beam forms – West area (equipment: crane, forklift, hammers, drills, skill saws).
Items listed in red: Please note that this activity may potentially disrupt the occupants in adjacent buildings;
Continuous noises on site: Construction equipment (back-up alarms), delivery trucks (back-up alarms), forklifts, generators, jackhammers, boom lifts, scissor lifts, saws, screw guns, and hammers.
The Student Success Center Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
Construction Alert #34
950512 SSC Construction Alert #34
Please be advised that the following activities will be occurring from 5:00AM to 4:00PM on the Student Success Center site and adjacent areas during the week of July 6th through July 11th:
General
- Material deliveries (equipment: trucks and trailers, forklift).
Level 2
- Columns and shear walls – rebar installation (equipment: crane, forklift, hammers);
- Columns and shear walls – forms installation (equipment: trucks, crane, forklift, drills, skill saws, hammers);
- Columns and shear walls – concrete placement (equipment: concrete trucks, pump truck, crane);
- Strip shear walls and column forms (equipment: crane, forklift, drills, hammers).
Level 3
- Deck forms – West area (equipment: crane, forklift, hammers, drills, skill saws).
Items listed in red: Please note that this activity may potentially disrupt the occupants in adjacent buildings;
Continuous noises on site: Construction equipment (back-up alarms), delivery trucks (back-up alarms), forklifts, generators, jackhammers, boom lifts, scissor lifts, saws, screw guns, and hammers.
The Student Success Center Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
Construction Alert #35
950512 SSC Construction Alert #35
Please be advised that the following activities will be occurring from 5:00AM to 4:00PM on the Student Success Center site and adjacent areas during the week of July 13th through July 18th:
General
- Material deliveries (equipment: trucks and trailers, forklift).
Level 2
- Strip shear walls and column forms (equipment: crane, forklift, drills, hammers).
Level 3
- Deck forms installation (equipment: crane, forklift, hammers, drills, skill saws);
- Deck, columns and shear walls – rebar installation (equipment: crane, forklift, hammers);
- Inserts, deck sleeves and embeds (equipment: crane, forklift, drills, saws, hammers);
- In slab rough ins (equipment: drills, hammers);
- Access stair install (equipment: crane, forklift, drills, saws, hammers).
Items listed in red: Please note that this activity may potentially disrupt the occupants in adjacent buildings;
Continuous noises on site: Construction equipment (back-up alarms), delivery trucks (back-up alarms), forklifts, generators, jackhammers, boom lifts, scissor lifts, saws, screw guns, and hammers.
The Student Success Center Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
Construction Alert #36
950512 SSC Construction Alert #36
Please be advised that the following activities will be occurring from 5:00AM to 4:00PM on the Student Success Center site and adjacent areas on Saturday, July 18th:
Fence Line Plans for Alternates
Level 2
- Strip deck forms (equipment: crane, forklift, scissor lifts, drills, hammers).
Level 3
- Deck forms installation (equipment: crane, forklift, scissor lifts, hammers, drills, skill saws);
- In slab electrical rough in (equipment: lasers, drills, saws, hammers).
Please be advised that the following activities will be occurring from 5:00AM to 4:00PM on the Student Success Center site and adjacent areas during the week of July 20th through July 25th:
General
- Material deliveries (equipment: trucks and trailers, forklift).
Level 1
- Strip deck forms (equipment: crane, forklift, scissor lifts, drills, hammers).
Level 2
- Strip shear walls and column forms (equipment: crane, forklift, scissor lifts, drills, hammers).
Level 3
- Deck forms installation (equipment: crane, forklift, hammers, drills, skill saws);
- Deck, columns and shear walls – rebar installation (equipment: crane, forklift, hammers);
- In slab rough ins (equipment: drills, hammers);
- Concrete placement – West Deck (equipment: concrete trucks, pump truck, crane).
In addition, please be advised that we will be starting on some of the site work outside of the current fence line boundary. The upcoming site work is projected to start end of July and projected to last through September. We are currently working with the Swinerton team on a proposed fence plan that has not been approved yet by our project management team. I am attaching a draft of this document so that you are aware of the impact, but will share the final version as part of future construction alerts and also in our neighborhood meeting next week. Below are some of the expected activities that will be part of the work related to Alternate 1 & 2 as well as some of the future fire lane work at the south entry and the west.
- Temporary Fence
- Landscape and Hardscape Demo
- Grading
- Structural Steel
- Concrete Sidewalks
- Concrete Seat Walls
- Lighting
- Landscaping
Items listed in red: Please note that this activity may potentially disrupt the occupants in adjacent buildings;
Continuous noises on site: Construction equipment (back-up alarms), delivery trucks (back-up alarms), forklifts, generators, jackhammers, boom lifts, scissor lifts, saws, screw guns, and hammers.
The Student Success Center Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
Construction Alert #37
950512 SSC Construction Alert #37
Fence Line Plans for Alternates
Please be advised that the following activities will be occurring from 5:00AM to 4:00PM on the Student Success Center site and adjacent areas on Saturday, July 25th:
Level 2
- Strip deck forms (equipment: crane, forklift, scissor lifts, drills, hammers).
Level 3
- Deck forms installation (equipment: crane, forklift, scissor lifts, hammers, drills, skill saws);
Please be advised that the following activities will be occurring from 5:00AM to 4:00PM on the Student Success Center site and adjacent areas during the week of July 27th through August 1st:
General
- Material deliveries (equipment: trucks and trailers, forklift).
Level 1
- Strip deck forms (equipment: crane, forklift, scissor lifts, drills, hammers).
Level 2
- Form stripping (equipment: crane, forklift, scissor lifts, drills, hammers).
Level 3
- Concrete placement – West Deck (equipment: concrete trucks, pump truck, crane);
- Deck forms installation (equipment: crane, forklift, hammers, drills, skill saws);
- Deck, columns and shear walls – rebar installation (equipment: crane, forklift, hammers);
- Columns and shear walls – forms installation (equipment: trucks, crane, forklift, drills, skill saws, hammers);
- Inserts, deck sleeves and embeds (equipment: lasers, drills, saws, hammers);
- In slab rough ins (equipment: drills, hammers).
In addition, please be advised that we will be starting on some of the site work outside of the current fence line boundary. The upcoming site work is projected to start end of July and projected to last through September. We are currently working with the Swinerton team on the proposed fence plan. I am attaching a draft of this document so that you are aware of the impact and will share if there are any updates. Below are some of the expected activities that will be part of the work related to Alternate 1 & 2 as well as some of the future fire lane work at the south entry and the west.
- Temporary Fence
- Landscape and Hardscape Demo
- Grading
- Structural Steel
- Concrete Sidewalks
- Concrete Seat Walls
- Lighting
- Landscaping
Items listed in red: Please note that this activity may potentially disrupt the occupants in adjacent buildings;
Continuous noises on site: Construction equipment (back-up alarms), delivery trucks (back-up alarms), forklifts, generators, jackhammers, boom lifts, scissor lifts, saws, screw guns, and hammers.
The Student Success Center Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
Construction Alert #38
950512 SSC Construction Alert #38
Please be advised that the following activities will be occurring from 5:00AM to 4:00PM on the Student Success Center site and adjacent areas on Saturday, August 1st:
Level 3
- Columns and shear walls – forms installation (equipment: crane, forklift, scissor lifts, hammers, drills, skill saws);
- Columns and shear walls – rebar installation (equipment: crane, forklift, hammers).
Please be advised that the following activities will be occurring from 5:00AM to 4:00PM on the Student Success Center site and adjacent areas during the week of August 3rd through August 8th:
General
- Material deliveries (equipment: trucks and trailers, forklift).
Site
- Storm drain install – Eastern portion of the site (equipment: truck, backhoe, cut off saw).
Level 1
- Form stripping (equipment: crane, forklift, scissor lifts, drills, hammers).
Level 2
- Form stripping (equipment: crane, forklift, scissor lifts, drills, hammers).
Level 3
- Concrete placement – East deck, columns and shear walls (equipment: concrete trucks, pump truck, crane);
- Columns and shear walls – rebar installation (equipment: crane, forklift, hammers);
- Columns and shear walls – forms installation (equipment: trucks, crane, forklift, drills, skill saws, hammers).
In addition, please be advised that we will be starting on some of the site work outside of the current fence line boundary. The upcoming site work is projected to start beginning of August and projected to last through September. I am attaching the proposed fence plan so that you are aware of the impact and will share any updates as they become available. Below are some of the expected activities that will be part of the work related to Alternate 1 & 2 as well as some of the future fire lane work at the south entry and the west.
- Temporary Fence
- Landscape and Hardscape Demo
- Grading
- Structural Steel
- Concrete Sidewalks
- Concrete Seat Walls
- Lighting
- Landscaping
Items listed in red: Please note that this activity may potentially disrupt the occupants in adjacent buildings;
Continuous noises on site: Construction equipment (back-up alarms), delivery trucks (back-up alarms), forklifts, generators, jackhammers, boom lifts, scissor lifts, saws, screw guns, and hammers.
The Student Success Center Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
Construction Alert #39
950512 SSC Construction Alert #39
Please be advised that the following activities will be occurring from 5:00AM to 4:00PM on the Student Success Center site and adjacent areas on Saturday, August 8th:
Level 1&2
- Form removal (equipment: crane, forklift, scissor lifts, drills, hammers).
Please be advised that the following activities will be occurring from 5:00AM to 4:00PM on the Student Success Center site and adjacent areas during the week of August 10th through August 15th:
General
- Material deliveries (equipment: trucks and trailers, forklift).
Level 1
- Reshore removal (equipment: forklift, scissor lifts, drills, hammers);
- Framing layout (equipment: roto hammers, chop saws).
Level 2
- Form removal (equipment: crane, forklift, scissor lifts, drills, hammers, skill saws).
Level 3
- Concrete placement – columns and shear walls (equipment: concrete trucks, pump truck, crane);
- Columns and shear walls – rebar installation (equipment: crane, forklift, hammers);
- Columns and shear walls – forms installation (equipment: trucks, crane, forklift, drills, skill saws, hammers).
Roof
- Deck forms installation (equipment: crane, forklift, scissor lifts, drills, hammers, skill saws).
In addition, please be advised that we will be starting on some of the site work outside of the current fence line boundary. I am attaching the proposed fence plan so that you are aware of the impact and will share any updates as they become available. Below are some of the expected activities that will be part of the work related to Alternate 1 & 2 as well as some of the future fire lane work at the south entry and the west.
- Temporary Fence
- Landscape and Hardscape Demo
- Grading
- Structural Steel
- Concrete Sidewalks
- Concrete Seat Walls
- Lighting
- Landscaping
Items listed inred: Please note that this activity may potentially disrupt the occupants in adjacent buildings;
Continuous noises on site: Construction equipment (back-up alarms), delivery trucks (back-up alarms), forklifts, generators, jackhammers, boom lifts, scissor lifts, saws, screw guns, and hammers
The Student Success Center Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
Construction Alert #40
950512 SSC Construction Alert #40
Please be advised that the following activities will be occurring from 5:00AM to 4:00PM on the Student Success Center site and adjacent areas on Saturday, August 15th:
Level 1
- Reshore removal (equipment: forklift, scissor lifts, drills, hammers).
Level 3
- Shear walls – forms installation (equipment: trucks, crane, forklift, drills, skill saws, hammers).
Roof
- Deck forms installation (equipment: crane, forklift, scissor lifts, drills, hammers, skill saws).
Please be advised that the following activities will be occurring from 5:00AM to 4:00PM on the Student Success Center site and adjacent areas during the week of August 17th through August 22nd:
General
- Material deliveries (equipment: trucks and trailers, forklift);
- Formwork removal from site (equipment: trucks, forklift, skill saws).
Site
- Water distribution (equipment: truck, backhoe).
Level 1
- Reshore removal (equipment: forklift, scissor lifts, drills, hammers);
- Interior framing (equipment: scissor lifts, powder actuated tools, drills, roto hammers, chop saws);
- Rough overhead MEPFS (equipment: scissor lifts, drills, hammers);
- Curbs and housekeeping pads (equipment: concrete trucks, skill saws, drills, hammers).
Level 2
- Form removal (equipment: crane, forklift, scissor lifts, drills, hammers, skill saws).
Level 3
- Concrete placement – columns and shear walls (equipment: concrete trucks, pump truck, crane);
- Form removal (equipment: crane, forklift, scissor lifts, drills, hammers, skill saws).
Roof
- Deck forms installation (equipment: crane, forklift, scissor lifts, drills, hammers, skill saws).
In addition, please be advised that we will be starting shortly on some of the site work outside of the current fence line boundary. I am attaching the proposed fence plan so that you are aware of the impact and will share any updates as they become available. Below are some of the expected activities that will be part of the work related to Alternate 1 & 2 as well as some of the future fire lane work at the south entry and the west.
- Temporary Fence
- Landscape and Hardscape Demo
- Grading
- Structural Steel
- Concrete Sidewalks
- Concrete Seat Walls
- Lighting
- Landscaping
Items listed in red: Please note that this activity may potentially disrupt the occupants in adjacent buildings;
Continuous noises on site: Construction equipment (back-up alarms), delivery trucks (back-up alarms), forklifts, generators, jackhammers, boom lifts, scissor lifts, saws, screw guns, and hammers.
The Student Success Center Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
Construction Alert #41
950512 SSC Construction Alert #41
Please be advised that the following activities will be occurring from 5:00AM to 4:00PM on the Student Success Center site and adjacent areas during the week of August 24th through August 29th:
General
- Material deliveries (equipment: trucks and trailers, forklift);
- Formwork removal from site (equipment: trucks, forklift, skill saws).
Site
- Water distribution (equipment: concrete trucks, backhoe, vibratory equipment).
Level 1
- Interior framing (equipment: scissor lifts, powder actuated tools, drills, roto hammers, chop saws);
- Rough-in MEPFS (equipment: scissor lifts, drills, band saws, hammers).
Level 2
- Form removal (equipment: crane, forklift, scissor lifts, drills, hammers, skill saws).
Roof
- Deck forms installation (equipment: crane, forklift, scissor lifts, drills, hammers, skill saws);
- Deck rebar installation (equipment: crane, forklift, hammers);
- Inserts and deck sleeves (equipment: lasers, drills, saws, hammers).
In addition, please be advised that we will be starting shortly on some of the site work outside of the current fence line boundary. I am attaching the proposed fence plan so that you are aware of the impact and will share any updates as they become available. Below are some of the expected activities that will be part of the work related to Alternate 1 & 2 as well as some of the future fire lane work at the south entry and the west.
- Temporary Fence
- Landscape and Hardscape Demo
- Grading
- Structural Steel
- Concrete Sidewalks
- Concrete Seat Walls
- Lighting
- Landscaping
Items listed in red: Please note that this activity may potentially disrupt the occupants in adjacent buildings;
Continuous noises on site: Construction equipment (back-up alarms), delivery trucks (back-up alarms), forklifts, generators, jackhammers, boom lifts, scissor lifts, saws, screw guns, and hammers.
The Student Success Center Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
-
Construction Alert #42
950512 SSC Construction Alert #42
Please be advised that the following activities will be occurring from 5:00AM to 4:00PM on the Student Success Center site and adjacent areas on Saturday, August 29th:
Roof
- Rebar installation (equipment: crane, forklift, hammers).
Please be advised that the following activities will be occurring from 5:00AM to 4:00PM on the Student Success Center site and adjacent areas during the week of August 31st through September 5th:
General
- Material deliveries (equipment: trucks and trailers, forklift);
- Site demobilization – concrete (equipment: trucks, dumpster exchanges, forklift, skill saws, hammers).
Site
- Water distribution (equipment: concrete trucks, backhoe, vibratory equipment).
Level 1
- Interior framing (equipment: scissor lifts, powder actuated tools, drills, roto hammers, chop saws);
- Rough-in MEPFS (equipment: scissor lifts, drills, band saws, hammers).
Level 2
- Form removal (equipment: crane, forklift, scissor lifts, drills, hammers, skill saws).
Roof
- Form installation – slab and edge (equipment: crane, forklift, scissor lifts, drills, hammers, skill saws);
- Rebar installation – slab and beams (equipment: crane, forklift, hammers);
- In slab rough-in (equipment: lasers, drills, saws, hammers);
- Concrete placement (equipment: concrete trucks, pump truck, crane).
In addition, please be advised that we will be starting shortly on some of the site work outside of the current fence line boundary. I am attaching the proposed fence plan so that you are aware of the impact and will share any updates as they become available. Below are some of the expected activities that will be part of the work related to Alternate 1 & 2 as well as some of the future fire lane work at the south entry and the west.
- Temporary Fence
- Landscape and Hardscape Demo