School of Business New Building

The new School of Business building complex will be a flagship facility, serving as the permanent home for the School. The building will complement the School of Business’ existing space program and fully address enrollment-driven needs in pursuit of their aspiration to become the premier center of management research and education in the Inland Empire.


Project Scope:

The proposed building will provide about 38,500 ASF within approximately to 63,400 GSF, along with exterior circulation and gathering areas. The program includes the following spaces:

  • Classrooms and Educational Spaces
  • Student Support Spaces
  • Academic Offices and Support Spaces
  • Administrative Offices and Support Spaces
  • Shared Building Resources (Lobby, Multipurpose room(s) etc)

School of Business Project Updates

  • 950592 UCR SBB - Construction Alert #28

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Genomics

    MEP Finishes

    N/A

    N/A

    SBB (Lot 8) Earthwork

    Grade and Bench

    Loader and Excavator

    Noise due to equipment

    SBB (Lot 8) Earthwork

    Soil Nail Wall

    Loader, Drill Rig, and Trucks

    Noise due to equipment

     

    Week of May 29, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Genomics

    MEP Finishes

    N/A

    N/A

    SBB (Lot 8) Earthwork

    Grade and Bench

    Loader and Excavator

    Noise due to equipment

    SBB (Lot 8) Earthwork

    Soil Nail Wall

    Loader, Drill Rig, and Trucks

    Noise due to equipment

    SBB (Lot 8) Concrete

    Layout Mat footing 1

    N/A

    N/A

    SBB (Lot 8) Concrete

    Excavate Footing for Mat Footing 1

    Loader, Excavator, and trucks

    Noise due to equipment

     

    Week of June 5, 2023

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Genomics

    Fire Alarm Testing (MEP testing and startup)

    N/A

    N/A

    SBB (Lot 8) Concrete

    Layout Mat Footing 2

    N/A

    N/A

    SBB (Lot 8) Concrete

    Excavate Footing for Mat Footing 1

    Loader, Excavator, and trucks

    Noise due to equipment

    SBB (Lot 8) Concrete

    Excavate Footing for Mat Footing 2

    Loader, Excavator, and trucks

    Noise due to equipment

    SBB (Lot 8) Concrete

    Waterproofing Mat Footing 1

    N/A

    N/A

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Permanently

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

    Anderson Park

    Anderson Park

    Indefinitely

    Anderson Park

  • 950592 UCR SBB - Construction Alert #27

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Earthwork

    Grade and Bench

    Loader and Excavator

    Noise due to equipment

    SBB (Lot 8) Earthwork

    Soil Nail Wall

    Loader, Drill Rig, and Trucks

    Noise due to equipment

    Genomics

    MEP Finishes

    N/A

    N/A

     

    Week of May 22, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Earthwork

    Grade and Bench

    Loader and Excavator

    Noise due to equipment

    Genomics

    MEP Finishes

    N/A

    N/A

    SBB (Lot 8) Earthwork

    Soil Nail Wall

    Loader, Drill Rig, and Trucks

    Noise due to equipment

     

    Week of May 29, 2023

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Earthwork

    Grade and Bench

    Loader and Excavator

    Noise due to equipment

    SBB (Lot 8) Earthwork

    Soil Nail Wall

    Loader, Drill Rig, and Trucks

    Noise due to equipment

    Genomics

    Fire Alarm Testing (MEP testing and startup)

    N/A

    N/A

    SBB (Lot 8) Foundations

    Layout Mat Foundation 1

    N/A

    N/A

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Permanently

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

  • 950592 UCR SBB - Construction Alert #26

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Earthwork

    Grade and Bench

    Loader and Excavator

    Noise due to equipment

    SBB (Lot 8) Earthwork

    Soil Nail Wall

    Loader, Drill Rig, and Trucks

    Noise due to equipment

    Genomics

    Finish DG Install

    N/A

    N/A

     

    Week of May 15, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Earthwork

    Grade and Bench

    Loader and Excavator

    Noise due to equipment

    Genomics

    MEP Finishes

    N/A

    N/A

    SBB (Lot 8) Earthwork

    Soil Nail Wall

    Loader, Drill Rig, and Trucks

    Noise due to equipment

     

    Week of May 22, 2023

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Earthwork

    Grade and Bench

    Loader and Excavator

    Noise due to equipment

    SBB (Lot 8) Earthwork

    Soil Nail Wall

    Loader, Drill Rig, and Trucks

    Noise due to equipment

    Genomics

    Fire Alarm Testing (MEP testing and startup)

    N/A

    N/A

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Permanently

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

  • 950592 UCR SBB - Construction Alert #25

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Earthwork

    Grade and Bench

    Loader and Excavator

    Noise due to equipment

    SBB (Lot 8) Earthwork

    Soil Nail Wall

    Loader, Drill Rig, and Trucks

    Noise due to equipment

    Genomics

    Fencing

    N/A

    N/A

    Genomics

    Striping & Signage Post Install

    N/A

    N/A

     

    Week of May 8, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Earthwork

    Grade and Bench

    Loader and Excavator

    Noise due to equipment

    Genomics

    MEP Finishes

    N/A

    N/A

    SBB (Lot 8) Earthwork

    Soil Nail Wall

    Loader, Drill Rig, and Trucks

    Noise due to equipment

     

    Week of May 15, 2023

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Earthwork

    Grade and Bench

    Loader and Excavator

    Noise due to equipment

    SBB (Lot 8) Earthwork

    Soil Nail Wall

    Loader, Drill Rig, and Trucks

    Noise due to equipment

    Genomics

    Fire Alarm Testing (MEP testing and startup)

    N/A

    N/A

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Permanently

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

  • 950592 UCR SBB - Construction Alert #24

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Earthwork

    Grade and Bench

    Loader and Excavator

    Noise due to equipment

    Genomics

    MEP Finishes

    N/A

    N/A

    SBB (Lot 8) Earthwork

    Soil Nail Wall

    Loader, Drill Rig, and Trucks

    Noise due to equipment

    Genomics

    Fencing

    N/A

    N/A

     

    Week of May 1, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Earthwork

    Grade and Bench

    Loader and Excavator

    Noise due to equipment

    Genomics

    MEP Finishes

    N/A

    N/A

    Genomics

    Asphalt

    Skid steer/ Mini Excavator

    Noise due to equipment

    SBB (Lot 8) Earthwork

    Soil Nail Wall

    Loader, Drill Rig, and Trucks

    Noise due to equipment

     

    Week of May 8, 2023

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Earthwork

    Grade and Bench

    Loader and Excavator

    Noise due to equipment

    SBB (Lot 8) Earthwork

    Soil Nail Wall

    Loader, Drill Rig, and Trucks

    Noise due to equipment

    Genomics

    Fire Alarm Testing (MEP testing and startup)

    N/A

    N/A

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Permanently

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

  • 950592 UCR SBB - Construction Alert #23

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Earthwork

    Grade and Bench

    Loader and Excavator

    Noise due to equipment

    Genomics

    MEP Finishes

    N/A

    N/A

    SBB (Lot 8) Earthwork

    Soil Nail Wall

    Loader, Drill Rig, and Trucks

    Noise due to equipment

    Genomics

    Grading/Pouring Flatwork

    Skid steer / Mini Excavator

    Noise due to equipment

     

    Week of April 24, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Earthwork

    Grade and Bench

    Loader and Excavator

    Noise due to equipment

    Genomics

    MEP Finishes

    N/A

    N/A

    Genomics

    Asphalt

    Skid steer/ Mini Excavator

    Noise due to equipment

    SBB (Lot 8) Earthwork

    Soil Nail Wall

    Loader, Drill Rig, and Trucks

    Noise due to equipment

    Genomics

    Fencing

    N/A

    N/A

     

    Week of May 1, 2023

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Earthwork

    Grade and Bench

    Loader and Excavator

    Noise due to equipment

    SBB (Lot 8) Earthwork

    Soil Nail Wall

    Loader, Drill Rig, and Trucks

    Noise due to equipment

    Genomics

    Fire Alarm Testing (MEP testing and startup)

    N/A

    N/A

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Permanently

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

  • 950592 UCR SBB - Construction Alert #22

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Earthwork

    Grade and Bench

    Loader and Excavator

    Noise due to equipment

    Genomics

    MEP Rough-in

    N/A

    N/A

    Genomics

    Site Wall

    Skid steer / Mini Excavator

    Noise due to equipment

    SBB (Lot 8) Earthwork

    Soil Nail Wall

    Loader, Drill Rig, and Trucks

    Noise due to equipment

    Genomics

    Grading for Flatwork

    Skid steer / Mini Excavator

    Noise due to equipment

     

    Week of April 17, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Earthwork

    Grade and Bench

    Loader and Excavator

    Noise due to equipment

    Genomics

    MEP Finishes

    N/A

    N/A

    Genomics

    Asphalt

    Skid steer/ Mini Excavator

    Noise due to equipment

    SBB (Lot 8) Earthwork

    Soil Nail Wall

    Loader, Drill Rig, and Trucks

    Noise due to equipment

     

    Week of April 24, 2023

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Earthwork

    Grade and Bench

    Loader and Excavator

    Noise due to equipment

    Genomics

    MEP Finishes

    N/A

    N/A

    SBB (Lot 8) Earthwork

    Soil Nail Wall

    Loader, Drill Rig, and Trucks

    Noise due to equipment

    Genomics

    Fencing

    N/A

    N/A

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Permanently

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

  • 950592 UCR SBB - Construction Alert #21

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Earthwork

    Soil Nail Wall Mob

    Loader, Drill Rig, and Trucks

    Noise due to equipment

    Genomics

    Install Metal Building (PEMB)

    N/A

    N/A

    SBB (Lot 8) Earthwork

    Clear & Grub for SBB and Export Dirt

    Loader and Excavator

    Noise due to equipment

    Genomics

    Site Wall

    Skid Steer/Mini Excavator

    Noise due to equipment

    Genomics

    MEP Rough-in

    N/A

    N/A

     

    Week of April 10, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Earthwork

    Clear & Grub for SBB and Misc. Export

    Loader and Excavator

    Noise due to equipment

    Genomics

    MEP Rough-in

    N/A

    N/A

    Genomics

    Site Wall

    Skid steer / Mini Excavator

    Noise due to equipment

    SBB (Lot 8) Earthwork

    Soil Nail Wall

    Loader, Drill Rig, and Trucks

    Noise due to equipment

     

    Week of April 17, 2023

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8)

    Site Utilities

    Backhoe, excavator, trucks

    Noise due to equipment

    SBB (Lot 8) Earthwork

    Grade and Bench

    Loader and Excavator

    Noise due to equipment

    Genomics

    MEP Finishes

    N/A

    N/A

    Genomics

    Site Wall

    Skid steer/ Mini Excavator

    Noise due to equipment

    SBB (Lot 8) Earthwork

    Soil Nail Wall

    Loader, Drill Rig, and Trucks

    Noise due to equipment

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Permanently

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

  • 950592 UCR SBB - Construction Alert #20

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Earthwork

    Soil Nail Wall

    Loader, Drill Rig, and Trucks

    Noise due to equipment

    Genomics

    Install Metal Building (PEMB)

    N/A

    N/A

    SBB (Lot 8) Earthwork

    Clear & Grub for SBB

    Loader and Excavator

    Noise due to equipment

    Genomics

    Site Wall

    Skid Steer

    Noise due to equipment

     

    Week of April 3, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8)

    Site Utilities

    Backhoe, excavator, trucks

    Noise due to equipment

    SBB (Lot 8) Earthwork

    Clear & Grub for SBB

    Loader and Excavator

    Noise due to equipment

    Genomics

    MEP Rough-in

    N/A

    N/A

    Genomics

    Site Wall

    Skid steer

    Noise due to equipment

    SBB (Lot 8) Earthwork

    Soil Nail Wall

    Loader, Drill Rig, and Trucks

    Noise due to equipment

     

    Week of April 10, 2023

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8)

    Site Utilities

    Backhoe, excavator, trucks

    Noise due to equipment

    SBB (Lot 8) Earthwork

    Grade and Bench

    Loader and Excavator

    Noise due to equipment

    Genomics

    MEP Finishes

    N/A

    N/A

    Genomics

    Site Wall

    Skid steer

    Noise due to equipment

    SBB (Lot 8) Earthwork

    Soil Nail Wall

    Loader, Drill Rig, and Trucks

    Noise due to equipment

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Permanently

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

  • 950592 UCR SBB - Construction Alert #19

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8)

    Locate and Cap Existing Utilities

    N/A

    N/A

    Genomics

    Install Metal Building (PEMB)

    N/A

    N/A

    SBB (Site)

    Street Paving

    Trucks and Rollers

    Noise due to equipment

    SBB (Lot 8) Earthwork

    Clear & Grub for SBB

    Loader and Excavator

    Noise due to equipment

     

    Week of March 27, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8) Earthwork

    Soil Nail Wall

    Loader, Drill Rig, and Trucks

    Noise due to equipment

    Genomics

    Install Metal Building (PEMB)

    N/A

    N/A

    SBB (Lot 8) Earthwork

    Clear & Grub for SBB

    Loader and Excavator

    Noise due to equipment

    Genomics

    Site Wall

    Skid Steer

    Noise due to equipment

     

    Week of April 3, 2023

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8)

    Site Utilities

    Backhoe, excavator, trucks

    Noise due to equipment

    SBB (Lot 8) Earthwork

    Clear & Grub for SBB

    Loader and Excavator

    Noise due to equipment

    Genomics

    MEP Rough-in

    N/A

    N/A

    Genomics

    Site Wall

    Skid steer

    Noise due to equipment

    SBB (Lot 8) Earthwork

    Soil Nail Wall

    Loader, Drill Rig, and Trucks

    Noise due to equipment

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Permanently

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

  • 950592 UCR SBB - Construction Alert #18 - Week 03/13/2023

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8)

    Locate and Cap Existing Utilities

    N/A

    N/A

    SBB (Lot 8)

    Site Utilities

    Backhoe, excavator, trucks

    Noise due to equipment

    Genomics

    Install Metal Building (PEMB)

    N/A

    N/A

    SBB (site electrical)

    Concrete backfill of medium voltage trench

    Concrete pump and trucks

    Noise due to equipment

    SBB (Lot 8)

    Electrical Shutdown

    N/A

    N/A

     

    Week of March 20, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8)

    Locate and Cap Existing Utilities

    N/A

    N/A

    SBB (Lot 8)

    Site Utilities

    Backhoe, excavator, trucks

    Noise due to equipment

    Genomics

    Install Metal Building (PEMB)

    N/A

    N/A

    SBB (Lot 8) Earthwork

    Clear & Grub for Soil Nail Wall

    Loader and Excavator

    Noise due to equipment

    Genomics

    Site Wall

    Skid Steer

    Noise due to equipment

     

    Week of March 27, 2023

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8)

    Site Utilities

    Backhoe, excavator, trucks

    Noise due to equipment

    Genomics

    Install Metal Building (PEMB)

    N/A

    N/A

    SBB (Lot 8) Earthwork

    Clear & Grub for Soil Nail Wall

    Loader and Excavator

    Noise due to equipment

    Genomics

    MEP Rough-in

    N/A

    N/A

    Genomics

    Site Wall

    Skid steer

    Noise due to equipment

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Permanently

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

  • UCR SBB - Construction Alert #17 - Week 03/06/2023

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8)

    Locate and Cap Existing Utilities

    N/A

    N/A

    SBB (Lot 8)

    Site Utilities

    Backhoe, excavator, trucks

    Noise due to equipment

    SBB (site electrical)

    Pulling Medium Voltage cable

    N/A

    N/A

    SBB (site electrical)

    Setting new power pole

    N/A

    N/A

    Genomics

    Install Metal Building (PEMB)

    N/A

    N/A

    SBB (site electrical)

    Concrete backfill of medium voltage trench

    Concrete pump and trucks

    Noise due to equipment

    SBB (Lot 8)

    Domestic Water Shutdown

    N/A

    N/A

     

    Week of March 13, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8)

    Locate and Cap Existing Utilities

    N/A

    N/A

    SBB (Lot 8)

    Site Utilities

    Backhoe, excavator, trucks

    Noise due to equipment

    Genomics

    Install Metal Building (PEMB)

    N/A

    N/A

    SBB (Lot 8)

    Electrical Shutdown

    N/A

    N/A

     

    Week of March 20, 2023

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8)

    Locate and Cap Existing Utilities

    N/A

    N/A

    SBB (Lot 8)

    Site Utilities

    Backhoe, excavator, trucks

    Noise due to equipment

    Genomics

    Install Metal Building (PEMB)

    N/A

    N/A

    SBB (Lot 8) Earthwork

    Clear & Grub for Soil Nail Wall

    Loader and Excavator

    Noise due to equipment

    Genomics

    MEP Rough-in

    N/A

    N/A

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Permanently

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

  • 950592 - UCR SBB - Construction Alert #16 - Week 02/27/2023

    Current Weeks

    Construction Activities

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8)

    Locate and Cap Existing Utilities

    N/A

    N/A

    SBB (Lot 8)

    Site Utilities

    Backhoe, excavator, trucks

    Noise due to equipment

    Genomics

    Metal Building Arrives (PEMB)

    N/A

    N/A

    SBB (site electrical)

    Pulling Medium Voltage cable

    N/A

    N/A

    SBB (site electrical)

    Installing conduit

    N/A

    N/A

    Genomics

    Form and reinforce SOG

    N/A

    N/A

    Genomics

    Concrete Pour

    Concrete Pump

    Noise due to equipment

     

    Week of March 6, 2023

    Construction Activities 

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8)

    Locate and Cap Existing Utilities

    N/A

    N/A

    SBB (Lot 8)

    Site Utilities

    Backhoe, excavator, trucks

    Noise due to equipment

    SBB (site electrical)

    Pulling Medium Voltage cable

    N/A

    N/A

    SBB (site electrical)

    Setting new power pole

    N/A

    N/A

    Genomics

    Install Metal Building (PEMB)

    N/A

    N/A

    SBB (Lot 8)

    Domestic Water Shutdown

    N/A

    N/A

     

    Week of March 13, 2023

    Construction Activities

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8)

    Locate and Cap Existing Utilities

    N/A

    N/A

    SBB (Lot 8)

    Site Utilities

    Backhoe, excavator, trucks

    Noise due to equipment

    Genomics

    Install Metal Building (PEMB)

    N/A

    N/A

    SBB (site electrical)

    Pulling Medium Voltage cable

    N/A

    N/A

    SBB (Lot 8) Earthwork

    Clear & Grub for Soil Nail Wall

    Loader and Excavator

    Noise due to equipment

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Permanently

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

     

  • 950592 - UCR SBB - Construction Alert #15 - Week 02/20/2023

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8)

    Locate and Cap Existing Utilities

    N/A

    N/A

    SBB (Lot 8)

    Site Utilities

    Backhoe, excavator, trucks

    Noise due to equipment

    Genomics

    Metal Building Arrives (PEMB)

    N/A

    N/A

    SBB (site electrical)

    Pulling Medium Voltage cable

    N/A

    N/A

    Genomics

    Back fill

    Bobcat or skid-steer

    Noise due to equipment

    SBB (site electrical)

    Installing conduit

    N/A

    N/A

    Genomics

    Form and reinforce SOG

    N/A

    N/A

     

    Week of February 27, 2023

    Construction Activities 

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8)

    Locate and Cap Existing Utilities

    N/A

    N/A

    SBB (Lot 8)

    Site Utilities

    Backhoe, excavator, trucks

    Noise due to equipment

    SBB (site electrical)

    Pulling Medium Voltage cable

    N/A

    N/A

    SBB (site electrical)

    Setting new power pole

    N/A

    N/A

    SBB Earthwork

    Clear & Grub for Soil Nail Wall

    Loader and Excavator

    Noise due to equipment

    Genomics

    Concrete Pour

    Concrete Pump

    Noise due to equipment

     

    Week of March 6, 2023

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8)

    Locate and Cap Existing Utilities

    N/A

    N/A

    SBB (Lot 8)

    Site Utilities

    Backhoe, excavator, trucks

    Noise due to equipment

    Genomics

    Install Metal Building (PEMB)

    N/A

    N/A

    SBB (site electrical)

    Pulling Medium Voltage cable

    N/A

    N/A

    SBB Earthwork

    Clear & Grub for Soil Nail Wall

    Loader and Excavator

    Noise due to equipment

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Permanently

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

  • 950592 - UCR SBB - Construction Alert #14- Week 02/13/2023

    Current Weeks

    Construction Activities

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8)

    Locate and Cap Existing Utilities

    N/A

    N/A

    SBB (Lot 8)

    Domestic Water Shutdown Feb. 15th

    N/A

    Shutdown water to the greenhouses 

    SBB (Lot 8)

    Campus Drive Lane Closure

    N/A

    Single Lane Traffic

    SBB (Lot 8)

    Site Utilities

    Backhoe, excavator, trucks

    Noise due to equipment

    SBB (Lot 8)

    Electrical Trenching

    N/A

    Noise due to equipment (College Place)

    Genomics

    Under-slab plumbing and electrical

    N/A

    N/A

    SBB (Lot 8)

    College Place Closure

    N/A

    College Place Closure

    Genomics

    Anchor Bolt Installation

    N/A

    N/A

    Genomics

    Concrete Pour

    Concrete Pump

    Noise due to equipment

    Genomics

    Back fill

    Bobcat or skid-steer

    Noise due to equipment

    SBB (site electrical)

    Installing conduit

    N/A

    N/A

    Genomics

    Form and reinforce SOG

    N/A

    N/A

     

    Week of February 20, 2023

    Construction Activities 

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8)

    Locate and Cap Existing Utilities

    N/A

    N/A

    SBB (Lot 8)

    Site Utilities

    Backhoe, excavator, trucks

    Noise due to equipment

    Genomics

    Install Metal Building (PEMB)

    N/A

    N/A

    SBB (site electrical)

    Pulling Medium Voltage cable

    N/A

    N/A

    SBB (site electrical)

    Setting new power pole

    N/A

    N/A

    Genomics

    Back fill

    Bobcat or skid-steer

    Noise due to equipment

     

    Week of February 27, 2023

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8)

    Locate and Cap Existing Utilities

    N/A

    N/A

    SBB (Lot 8)

    Site Utilities

    Backhoe, excavator, trucks

    Noise due to equipment

    Genomics

    Install Metal Building (PEMB)

    N/A

    N/A

    SBB (site electrical)

    Pulling Medium Voltage cable

    N/A

    N/A

    SBB (site electrical)

    Setting new power pole

    N/A

    N/A

    SBB Earthwork

    Clear & Grub for Soil Nail Wall

    Loader and Excavator

    Noise due to equipment

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Permanently

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

  • 950592 - UCR SBB - Construction Alert #13- Week 02/06/2023

    Current Weeks

    Construction Activities

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8)

    Locate and Cap Existing Utilities

    N/A

    N/A

    SBB (Lot 8)

    Campus Drive Lane Closure

    N/A

    Single Lane Traffic

    SBB (Lot 8)

    Site Utilities

    Back hoe, excavator, trucks

    Noise due to equipment

    SBB (Lot 8)

    Electrical Trenching

    N/A

    Noise due to equipment (College Place)

    SBB (Lot 8)

    College Place Closure

    N/A

    College Place Closure

    SBB (Lot 8)

    Gas Shutdown Feb. 10th

    N/A

    Shutdown gas to the greenhouses 

    Genomics

    Waterproofing

    N/A

    N/A

    Existing Sheds

    Demo Existing Sheds

    Excavator

    Noise due to equipment

     

    Week of February 13, 2023

    Construction Activities 

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8)

    Locate and Cap Existing Utilities

    N/A

    N/A

    SBB (Lot 8)

    Domestic Water Shutdown Feb. 15th

    N/A

    Shutdown water to the greenhouses 

    SBB (Lot 8)

    Campus Drive Lane Closure

    N/A

    Single Lane Traffic

    SBB (Lot 8)

    Site Utilities

    Back hoe, excavator, trucks

    Noise due to equipment

    SBB (Lot 8)

    Electrical Trenching

    N/A

    Noise due to equipment (College Place)

    Genomics

    Underslab plumbing and electrical

    N/A

    N/A

    SBB (Lot 8)

    College Place Closure

    N/A

    College Place Closure

    Genomics

    Anchor Bolt Installation

    N/A

    N/A

    Genomics

    Concrete Pour

    Concrete Pump

    Noise due to equipment

    Genomics

    Back fill

    Bobcat or skid-steer

    Noise due to equipment

    SBB (site electrical)

    Installing conduit

    N/A

    N/A

    Genomics

    Form and reinforce SOG

    N/A

    N/A

     

    Week of February 20, 2023

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8)

    Locate and Cap Existing Utilities

    N/A

    N/A

    SBB (Lot 8)

    Site Utilities

    Back hoe, excavator, trucks

    Noise due to equipment

    Genomics

    Install Metal Building

    N/A

    N/A

    SBB (site electrical)

    Pulling Medium Voltage cable

    N/A

    N/A

    SBB (site electrical)

    Setting new power pole

    N/A

    N/A

    Genomics

    Back fill

    Bobcat or skid-steer

    Noise due to equipment

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Permanently

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

  • 950592 - UCR SBB - Construction Alert #12- Week 01/30/2023

    Current Weeks

    Construction Activities

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Genomics

    Underground Electrical

    N/A

    N/A

    Genomics

    CMU Stem wall

    N/A

    N/A

    SBB (Lot 8)

    Locate and Cap Existing Utilities

    N/A

    N/A

    SBB (Lot 8)

    Campus Drive Lane Closure

    N/A

    Single Lane Traffic

    SBB (Lot 8)

    Site Utilities

    Back hoe, excavator, trucks

    Noise due to equipment

    SBB (Lot 8)

    Electrical Trenching

    N/A

    Noise due to equipment (College Place)

    SBB (Lot 8)

    College Place Closure

    N/A

    College Place Closure

    Existing Sheds

    Demo Existing Sheds

    Excavator

    Noise due to equipment

     

    Week of February 06, 2023

    Construction Activities 

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8)

    Locate and Cap Existing Utilities

    N/A

    N/A

    SBB (Lot 8)

    Campus Drive Lane Closure

    N/A

    Single Lane Traffic

    SBB (Lot 8)

    Site Utilities

    Back hoe, excavator, trucks

    Noise due to equipment

    SBB (Lot 8)

    Electrical Trenching

    N/A

    Noise due to equipment (College Place)

    SBB (Lot 8)

    College Place Closure

    N/A

    College Place Closure

    SBB (Lot 8)

    Gas Shutdown Feb. 10th

    N/A

    Shutdown gas to the greenhouses 

    Existing Sheds

    Demo Existing Sheds

    Excavator

    Noise due to equipment

     

     

     

     

     

    Week of February 13, 2023

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8)

    Locate and Cap Existing Utilities

    N/A

    N/A

    SBB (Lot 8)

    Domestic Water Shutdown Feb. 15th

    N/A

    Shutdown water to the greenhouses 

    SBB (Lot 8)

    Campus Drive Lane Closure

    N/A

    Single Lane Traffic

    SBB (Lot 8)

    Site Utilities

    Back hoe, excavator, trucks

    Noise due to equipment

    SBB (Lot 8)

    Electrical Trenching

    N/A

    Noise due to equipment (College Place)

    SBB (Lot 8)

    College Place Closure

    N/A

    College Place Closure

    Genomics

    Anchor Bolt Installation

    N/A

    N/A

    Genomics

    Concrete Pour

    Concrete Pump

    Noise due to equipment

    Genomics

    Back fill

    Bobcat or skid-steer

    Noise due to equipment

    Genomics

    Form and reinforce SOG

    N/A

    N/A

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Permanently

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

    Campus Drive

    Single Lane Closure

    Until 02/09/23

    Buildings along Campus Drive

  • 950592 - UCR SBB - Construction Alert #11- Week 01/23/2023

    Current Weeks

    Construction Activities

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Genomics

    Underground Electrical

    N/A

    N/A

    Genomics

    Form and pour foundations

    pump

    Noise due to equipment

    SBB (Lot 8)

    Locate and Cap Existing Utilities

    N/A

    N/A

    SBB (Lot 8)

    Campus Drive Lane Closure

    N/A

    Single Lane Traffic

    SBB (Lot 8)

    Site Utilities

    Back hoe, excavator, trucks

    Noise due to equipment

    SBB (Lot 8)

    Electrical Trenching

    N/A

    Noise due to equipment (College Place)

    SBB (Lot 8)

    College Place Closure

    N/A

    College Place Closure

     

    Week of January 30, 2023

    Construction Activities 

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Genomics

    Underground Electrical

    N/A

    N/A

    Genomics

    CMU Stem wall

    N/A

    N/A

    SBB (Lot 8)

    Locate and Cap Existing Utilities

    N/A

    N/A

    SBB (Lot 8)

    Campus Drive Lane Closure

    N/A

    Single Lane Traffic

    SBB (Lot 8)

    Site Utilities

    Back hoe, excavator, trucks

    Noise due to equipment

    SBB (Lot 8)

    Electrical Trenching

    N/A

    Noise due to equipment (College Place)

     

     

     

     

    SBB (Lot 8)

    College Place Closure

    N/A

    College Place Closure

     

     

    Week of February 6, 2023

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8)

    Locate and Cap Existing Utilities

    N/A

    N/A

    SBB (Lot 8)

    Campus Drive Lane Closure

    N/A

    Single Lane Traffic

    SBB (Lot 8)

    Site Utilities

    Back hoe, excavator, trucks

    Noise due to equipment

    SBB (Lot 8)

    Electrical Trenching

    N/A

    Noise due to equipment (College Place)

    SBB (Lot 8)

    College Place Closure

    N/A

    College Place Closure

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Permanently

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

  • 950592 - UCR SBB - Construction Alert #10- Week 01/16/2023

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Genomics

    Footing excavation

    Back Hoe, mini-ex, dump truck

    Noise due to equipment

    Genomics

    Rebar Install

    N/A

    N/A

    Genomics

    Underground Electrical

    N/A

    N/A

     

    Week of January 23, 2023

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Genomics

    Underground Electrical

    N/A

    N/A

    Genomics

    Form and pour foundations

    pump

    Noise due to equipment

    SBB (Lot 8)

    Locate and Cap Existing Utilities

    N/A

    N/A

    SBB (Lot 8)

    Campus Drive Lane Closure

    N/A

    Single Lane Traffic

    SBB (Lot 8)

    Site Utilities

    Back hoe, excavator, trucks

    Noise due to equipment

    SBB (Lot 8)

    Electrical Trenching

    N/A

    Noise due to equipment (College Place)

     

     

     

     

    SBB (Lot 8)

    College Place Closure

    N/A

    College Place Closure

     

    Week of January 30, 2023

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8)

    Locate and Cap Existing Utilities

    N/A

    N/A

    SBB (Lot 8)

    Campus Drive Lane Closure

    N/A

    Single Lane Traffic

    SBB (Lot 8)

    Site Utilities

    Back hoe, excavator, trucks

    Noise due to equipment

    SBB (Lot 8)

    Electrical Trenching

    N/A

    Noise due to equipment (College Place)

    SBB (Lot 8)

    College Place Closure

    N/A

    College Place Closure

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Indefinitely

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

     

  • 950592 - UCR SBB - Construction Alert #9

    Week of January 9, 2023

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Lot 43

    Trailer Interior/Exterior Build-out

    Small hand tools

    Noise due to hand tools

    Bio-Control

    Relocate Existing Lines (Water, Telecom, and electrical)

    N/A

    N/A

    Genomics

    Excavate and Weather Protect Footings

    Back Hoe, mini-ex, dump truck

    Noise due to equipment

     

    Week of January 16, 2023

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Genomics

    Footing excavation

    Back Hoe, mini-ex, dump truck

    Noise due to equipment

    Genomics

    Rebar Install

    N/A

    N/A

    Genomics

    Form and pour foundations

    pump

    Noise due to equipment

    Genomics

    Underground Electrical

    N/A

    N/A

     

    Week of January 23, 2023

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8)

    Locate and Cap Existing Utilities

    N/A

    N/A

    SBB (Lot 8)

    Campus Drive Lane Closure

    N/A

    Single Lane Traffic

    SBB (Lot 8)

    Site Utilities

    Back hoe, excavator, trucks

    Noise due to equipment

    SBB (Lot 8)

    Electrical Trenching

    N/A

    Noise due to equipment (College Place)

    SBB (Lot 8)

    College Place Closure

    N/A

    College Place Closure

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Indefinitely

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

  • 950592 - UCR SBB - Construction Alert #8 Week 01/2/2023

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Lot 43

    Trailer Interior/Exterior Build-out

    Small hand tools

    Noise due to hand tools

    Genomics

    Grading

    N/A

    N/A

    Bio-Control

    Relocate Existing Lines (Water, Telecom, and electrical)

    N/A

    N/A

     

    Week of January 09, 2023

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Genomics

    Footing excavation

    Back Hoe, mini-ex, dump truck

    Noise due to equipment

    Bio-Control

    Relocate Existing Lines (Water, Telecom, and electrical)

    N/A

    N/A

     

    Week of January 16, 2023

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Genomics

    Rebar Install

    N/A

    N/A

    SBB (Lot 8)

    Site Utilities Excavation

    Mini-Ex and Asphalt Removal

    N/A

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Indefinitely

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

Project Timeline: 

Anticipated  Start:
Fall, 2022


Anticipated Completion:
Summer, 2024

 

PD&C Contact: 

Project Manager: John Franklin
tel: (951) 203-7920 (951) 827-2421
 

Project Planner: Melissa Garrety
tel: (951) 827-7376

 

Project Working Group: 

Danko Turcic

Jean Helwege

Jennifer Osborne

Kathy Drake

Kennett Lai

Patrick Latimer

Rami Zwick

Sabine Freij

Signup for construction updates on this project

CLICK HERE