School of Business New Building
The new School of Business building complex will be a flagship facility, serving as the permanent home for the School. The building will complement the School of Business’ existing space program and fully address enrollment-driven needs in pursuit of their aspiration to become the premier center of management research and education in the Inland Empire.
Project Scope:
The proposed building will provide about 38,500 ASF within approximately to 63,400 GSF, along with exterior circulation and gathering areas. The program includes the following spaces:
- Classrooms and Educational Spaces
- Student Support Spaces
- Academic Offices and Support Spaces
- Administrative Offices and Support Spaces
- Shared Building Resources (Lobby, Multipurpose room(s) etc)
School of Business Project Updates
-
950592 - UCR SBB - Construction Alert #10- Week 01/16/2023
Current Weeks
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
Genomics
Footing excavation
Back Hoe, mini-ex, dump truck
Noise due to equipment
Genomics
Rebar Install
N/A
N/A
Genomics
Underground Electrical
N/A
N/A
Week of January 23, 2023
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
Genomics
Underground Electrical
N/A
N/A
Genomics
Form and pour foundations
pump
Noise due to equipment
SBB (Lot 8)
Locate and Cap Existing Utilities
N/A
N/A
SBB (Lot 8)
Campus Drive Lane Closure
N/A
Single Lane Traffic
SBB (Lot 8)
Site Utilities
Back hoe, excavator, trucks
Noise due to equipment
SBB (Lot 8)
Electrical Trenching
N/A
Noise due to equipment (College Place)
SBB (Lot 8)
College Place Closure
N/A
College Place Closure
Week of January 30, 2023
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
SBB (Lot 8)
Locate and Cap Existing Utilities
N/A
N/A
SBB (Lot 8)
Campus Drive Lane Closure
N/A
Single Lane Traffic
SBB (Lot 8)
Site Utilities
Back hoe, excavator, trucks
Noise due to equipment
SBB (Lot 8)
Electrical Trenching
N/A
Noise due to equipment (College Place)
SBB (Lot 8)
College Place Closure
N/A
College Place Closure
Current and Upcoming Anticipated Closures
The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete. Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.
Description
Location
Duration & Date
Impacted Buildings/ Facilities
Lot 8
Lot 8
Indefinitely
Lot 8
Lot 43
Lot 43
Indefinitely
Lot 43
-
950592 - UCR SBB - Construction Alert #9
Week of January 9, 2023
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
Lot 43
Trailer Interior/Exterior Build-out
Small hand tools
Noise due to hand tools
Bio-Control
Relocate Existing Lines (Water, Telecom, and electrical)
N/A
N/A
Genomics
Excavate and Weather Protect Footings
Back Hoe, mini-ex, dump truck
Noise due to equipment
Week of January 16, 2023
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
Genomics
Footing excavation
Back Hoe, mini-ex, dump truck
Noise due to equipment
Genomics
Rebar Install
N/A
N/A
Genomics
Form and pour foundations
pump
Noise due to equipment
Genomics
Underground Electrical
N/A
N/A
Week of January 23, 2023
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
SBB (Lot 8)
Locate and Cap Existing Utilities
N/A
N/A
SBB (Lot 8)
Campus Drive Lane Closure
N/A
Single Lane Traffic
SBB (Lot 8)
Site Utilities
Back hoe, excavator, trucks
Noise due to equipment
SBB (Lot 8)
Electrical Trenching
N/A
Noise due to equipment (College Place)
SBB (Lot 8)
College Place Closure
N/A
College Place Closure
Current and Upcoming Anticipated Closures
The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete. Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.
Description
Location
Duration & Date
Impacted Buildings/ Facilities
Lot 8
Lot 8
Indefinitely
Lot 8
Lot 43
Lot 43
Indefinitely
Lot 43
-
950592 - UCR SBB - Construction Alert #8 Week 01/2/2023
Current Weeks
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
Lot 43
Trailer Interior/Exterior Build-out
Small hand tools
Noise due to hand tools
Genomics
Grading
N/A
N/A
Bio-Control
Relocate Existing Lines (Water, Telecom, and electrical)
N/A
N/A
Week of January 09, 2023
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
Genomics
Footing excavation
Back Hoe, mini-ex, dump truck
Noise due to equipment
Bio-Control
Relocate Existing Lines (Water, Telecom, and electrical)
N/A
N/A
Week of January 16, 2023
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
Genomics
Rebar Install
N/A
N/A
SBB (Lot 8)
Site Utilities Excavation
Mini-Ex and Asphalt Removal
N/A
Current and Upcoming Anticipated Closures
The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete. Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.
Description
Location
Duration & Date
Impacted Buildings/ Facilities
Lot 8
Lot 8
Indefinitely
Lot 8
Lot 43
Lot 43
Indefinitely
Lot 43
Project Timeline:
Anticipated Start:
Fall, 2022
Anticipated Completion:
Summer, 2024
PD&C Contact:
Project Manager: John Franklin
tel: (951) 203-7920 (951) 827-2421
Project Planner: Melissa Garrety
tel: (951) 827-7376
Project Working Group:
Danko Turcic
Jean Helwege
Jennifer Osborne
Kathy Drake
Kennett Lai
Patrick Latimer
Rami Zwick
Sabine Freij
Signup for construction updates on this project