Breadcrumb

School of Business New Building

The new School of Business building complex will be a flagship facility, serving as the permanent home for the School. The building will complement the School of Business’ existing space program and fully address enrollment-driven needs in pursuit of their aspiration to become the premier center of management research and education in the Inland Empire.


Project Scope:

The proposed building will provide about 38,500 ASF within approximately to 63,400 GSF, along with exterior circulation and gathering areas. The program includes the following spaces:

  • Classrooms and Educational Spaces
  • Student Support Spaces
  • Academic Offices and Support Spaces
  • Administrative Offices and Support Spaces
  • Shared Building Resources (Lobby, Multipurpose room(s) etc)

School of Business Project Updates

  • 950592 - UCR SBB - Construction Alert #10- Week 01/16/2023

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Genomics

    Footing excavation

    Back Hoe, mini-ex, dump truck

    Noise due to equipment

    Genomics

    Rebar Install

    N/A

    N/A

    Genomics

    Underground Electrical

    N/A

    N/A

     

    Week of January 23, 2023

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Genomics

    Underground Electrical

    N/A

    N/A

    Genomics

    Form and pour foundations

    pump

    Noise due to equipment

    SBB (Lot 8)

    Locate and Cap Existing Utilities

    N/A

    N/A

    SBB (Lot 8)

    Campus Drive Lane Closure

    N/A

    Single Lane Traffic

    SBB (Lot 8)

    Site Utilities

    Back hoe, excavator, trucks

    Noise due to equipment

    SBB (Lot 8)

    Electrical Trenching

    N/A

    Noise due to equipment (College Place)

     

     

     

     

    SBB (Lot 8)

    College Place Closure

    N/A

    College Place Closure

     

    Week of January 30, 2023

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8)

    Locate and Cap Existing Utilities

    N/A

    N/A

    SBB (Lot 8)

    Campus Drive Lane Closure

    N/A

    Single Lane Traffic

    SBB (Lot 8)

    Site Utilities

    Back hoe, excavator, trucks

    Noise due to equipment

    SBB (Lot 8)

    Electrical Trenching

    N/A

    Noise due to equipment (College Place)

    SBB (Lot 8)

    College Place Closure

    N/A

    College Place Closure

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Indefinitely

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

     

  • 950592 - UCR SBB - Construction Alert #9

    Week of January 9, 2023

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Lot 43

    Trailer Interior/Exterior Build-out

    Small hand tools

    Noise due to hand tools

    Bio-Control

    Relocate Existing Lines (Water, Telecom, and electrical)

    N/A

    N/A

    Genomics

    Excavate and Weather Protect Footings

    Back Hoe, mini-ex, dump truck

    Noise due to equipment

     

    Week of January 16, 2023

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Genomics

    Footing excavation

    Back Hoe, mini-ex, dump truck

    Noise due to equipment

    Genomics

    Rebar Install

    N/A

    N/A

    Genomics

    Form and pour foundations

    pump

    Noise due to equipment

    Genomics

    Underground Electrical

    N/A

    N/A

     

    Week of January 23, 2023

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    SBB (Lot 8)

    Locate and Cap Existing Utilities

    N/A

    N/A

    SBB (Lot 8)

    Campus Drive Lane Closure

    N/A

    Single Lane Traffic

    SBB (Lot 8)

    Site Utilities

    Back hoe, excavator, trucks

    Noise due to equipment

    SBB (Lot 8)

    Electrical Trenching

    N/A

    Noise due to equipment (College Place)

    SBB (Lot 8)

    College Place Closure

    N/A

    College Place Closure

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Indefinitely

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

  • 950592 - UCR SBB - Construction Alert #8 Week 01/2/2023

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Lot 43

    Trailer Interior/Exterior Build-out

    Small hand tools

    Noise due to hand tools

    Genomics

    Grading

    N/A

    N/A

    Bio-Control

    Relocate Existing Lines (Water, Telecom, and electrical)

    N/A

    N/A

     

    Week of January 09, 2023

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Genomics

    Footing excavation

    Back Hoe, mini-ex, dump truck

    Noise due to equipment

    Bio-Control

    Relocate Existing Lines (Water, Telecom, and electrical)

    N/A

    N/A

     

    Week of January 16, 2023

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Genomics

    Rebar Install

    N/A

    N/A

    SBB (Lot 8)

    Site Utilities Excavation

    Mini-Ex and Asphalt Removal

    N/A

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    Lot 8

    Lot 8

    Indefinitely

    Lot 8

    Lot 43

    Lot 43

    Indefinitely

    Lot 43

Project Timeline: 

Anticipated  Start:
Fall, 2022


Anticipated Completion:
Summer, 2024

 

PD&C Contact: 

Project Manager: John Franklin
tel: (951) 203-7920 (951) 827-2421
 

Project Planner: Melissa Garrety
tel: (951) 827-7376

 

Project Working Group: 

Danko Turcic

Jean Helwege

Jennifer Osborne

Kathy Drake

Kennett Lai

Patrick Latimer

Rami Zwick

Sabine Freij

Signup for construction updates on this project