School of Business New Building
The new School of Business building complex will be a flagship facility, serving as the permanent home for the School. The building will complement the School of Business’ existing space program and fully address enrollment-driven needs in pursuit of their aspiration to become the premier center of management research and education in the Inland Empire.
Project Scope:
The proposed building will provide about 38,500 ASF within approximately to 63,400 GSF, along with exterior circulation and gathering areas. The program includes the following spaces:
- Classrooms and Educational Spaces
- Student Support Spaces
- Academic Offices and Support Spaces
- Administrative Offices and Support Spaces
- Shared Building Resources (Lobby, Multipurpose room(s) etc)
School of Business Project Updates
-
950592 UCR SBB - Construction Alert #28
Current Weeks
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
Genomics
MEP Finishes
N/A
N/A
SBB (Lot 8) Earthwork
Grade and Bench
Loader and Excavator
Noise due to equipment
SBB (Lot 8) Earthwork
Soil Nail Wall
Loader, Drill Rig, and Trucks
Noise due to equipment
Week of May 29, 2023
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
Genomics
MEP Finishes
N/A
N/A
SBB (Lot 8) Earthwork
Grade and Bench
Loader and Excavator
Noise due to equipment
SBB (Lot 8) Earthwork
Soil Nail Wall
Loader, Drill Rig, and Trucks
Noise due to equipment
SBB (Lot 8) Concrete
Layout Mat footing 1
N/A
N/A
SBB (Lot 8) Concrete
Excavate Footing for Mat Footing 1
Loader, Excavator, and trucks
Noise due to equipment
Week of June 5, 2023
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
Genomics
Fire Alarm Testing (MEP testing and startup)
N/A
N/A
SBB (Lot 8) Concrete
Layout Mat Footing 2
N/A
N/A
SBB (Lot 8) Concrete
Excavate Footing for Mat Footing 1
Loader, Excavator, and trucks
Noise due to equipment
SBB (Lot 8) Concrete
Excavate Footing for Mat Footing 2
Loader, Excavator, and trucks
Noise due to equipment
SBB (Lot 8) Concrete
Waterproofing Mat Footing 1
N/A
N/A
Current and Upcoming Anticipated Closures
The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete. Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.
Description
Location
Duration & Date
Impacted Buildings/ Facilities
Lot 8
Lot 8
Permanently
Lot 8
Lot 43
Lot 43
Indefinitely
Lot 43
Anderson Park
Anderson Park
Indefinitely
Anderson Park
-
950592 UCR SBB - Construction Alert #27
Current Weeks
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
SBB (Lot 8) Earthwork
Grade and Bench
Loader and Excavator
Noise due to equipment
SBB (Lot 8) Earthwork
Soil Nail Wall
Loader, Drill Rig, and Trucks
Noise due to equipment
Genomics
MEP Finishes
N/A
N/A
Week of May 22, 2023
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
SBB (Lot 8) Earthwork
Grade and Bench
Loader and Excavator
Noise due to equipment
Genomics
MEP Finishes
N/A
N/A
SBB (Lot 8) Earthwork
Soil Nail Wall
Loader, Drill Rig, and Trucks
Noise due to equipment
Week of May 29, 2023
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
SBB (Lot 8) Earthwork
Grade and Bench
Loader and Excavator
Noise due to equipment
SBB (Lot 8) Earthwork
Soil Nail Wall
Loader, Drill Rig, and Trucks
Noise due to equipment
Genomics
Fire Alarm Testing (MEP testing and startup)
N/A
N/A
SBB (Lot 8) Foundations
Layout Mat Foundation 1
N/A
N/A
Current and Upcoming Anticipated Closures
The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete. Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.
Description
Location
Duration & Date
Impacted Buildings/ Facilities
Lot 8
Lot 8
Permanently
Lot 8
Lot 43
Lot 43
Indefinitely
Lot 43
-
950592 UCR SBB - Construction Alert #26
Current Weeks
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
SBB (Lot 8) Earthwork
Grade and Bench
Loader and Excavator
Noise due to equipment
SBB (Lot 8) Earthwork
Soil Nail Wall
Loader, Drill Rig, and Trucks
Noise due to equipment
Genomics
Finish DG Install
N/A
N/A
Week of May 15, 2023
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
SBB (Lot 8) Earthwork
Grade and Bench
Loader and Excavator
Noise due to equipment
Genomics
MEP Finishes
N/A
N/A
SBB (Lot 8) Earthwork
Soil Nail Wall
Loader, Drill Rig, and Trucks
Noise due to equipment
Week of May 22, 2023
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
SBB (Lot 8) Earthwork
Grade and Bench
Loader and Excavator
Noise due to equipment
SBB (Lot 8) Earthwork
Soil Nail Wall
Loader, Drill Rig, and Trucks
Noise due to equipment
Genomics
Fire Alarm Testing (MEP testing and startup)
N/A
N/A
Current and Upcoming Anticipated Closures
The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete. Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.
Description
Location
Duration & Date
Impacted Buildings/ Facilities
Lot 8
Lot 8
Permanently
Lot 8
Lot 43
Lot 43
Indefinitely
Lot 43
-
950592 UCR SBB - Construction Alert #25
Current Weeks
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
SBB (Lot 8) Earthwork
Grade and Bench
Loader and Excavator
Noise due to equipment
SBB (Lot 8) Earthwork
Soil Nail Wall
Loader, Drill Rig, and Trucks
Noise due to equipment
Genomics
Fencing
N/A
N/A
Genomics
Striping & Signage Post Install
N/A
N/A
Week of May 8, 2023
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
SBB (Lot 8) Earthwork
Grade and Bench
Loader and Excavator
Noise due to equipment
Genomics
MEP Finishes
N/A
N/A
SBB (Lot 8) Earthwork
Soil Nail Wall
Loader, Drill Rig, and Trucks
Noise due to equipment
Week of May 15, 2023
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
SBB (Lot 8) Earthwork
Grade and Bench
Loader and Excavator
Noise due to equipment
SBB (Lot 8) Earthwork
Soil Nail Wall
Loader, Drill Rig, and Trucks
Noise due to equipment
Genomics
Fire Alarm Testing (MEP testing and startup)
N/A
N/A
Current and Upcoming Anticipated Closures
The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete. Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.
Description
Location
Duration & Date
Impacted Buildings/ Facilities
Lot 8
Lot 8
Permanently
Lot 8
Lot 43
Lot 43
Indefinitely
Lot 43
-
950592 UCR SBB - Construction Alert #24
Current Weeks
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
SBB (Lot 8) Earthwork
Grade and Bench
Loader and Excavator
Noise due to equipment
Genomics
MEP Finishes
N/A
N/A
SBB (Lot 8) Earthwork
Soil Nail Wall
Loader, Drill Rig, and Trucks
Noise due to equipment
Genomics
Fencing
N/A
N/A
Week of May 1, 2023
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
SBB (Lot 8) Earthwork
Grade and Bench
Loader and Excavator
Noise due to equipment
Genomics
MEP Finishes
N/A
N/A
Genomics
Asphalt
Skid steer/ Mini Excavator
Noise due to equipment
SBB (Lot 8) Earthwork
Soil Nail Wall
Loader, Drill Rig, and Trucks
Noise due to equipment
Week of May 8, 2023
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
SBB (Lot 8) Earthwork
Grade and Bench
Loader and Excavator
Noise due to equipment
SBB (Lot 8) Earthwork
Soil Nail Wall
Loader, Drill Rig, and Trucks
Noise due to equipment
Genomics
Fire Alarm Testing (MEP testing and startup)
N/A
N/A
Current and Upcoming Anticipated Closures
The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete. Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.
Description
Location
Duration & Date
Impacted Buildings/ Facilities
Lot 8
Lot 8
Permanently
Lot 8
Lot 43
Lot 43
Indefinitely
Lot 43
-
950592 UCR SBB - Construction Alert #23
Current Weeks
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
SBB (Lot 8) Earthwork
Grade and Bench
Loader and Excavator
Noise due to equipment
Genomics
MEP Finishes
N/A
N/A
SBB (Lot 8) Earthwork
Soil Nail Wall
Loader, Drill Rig, and Trucks
Noise due to equipment
Genomics
Grading/Pouring Flatwork
Skid steer / Mini Excavator
Noise due to equipment
Week of April 24, 2023
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
SBB (Lot 8) Earthwork
Grade and Bench
Loader and Excavator
Noise due to equipment
Genomics
MEP Finishes
N/A
N/A
Genomics
Asphalt
Skid steer/ Mini Excavator
Noise due to equipment
SBB (Lot 8) Earthwork
Soil Nail Wall
Loader, Drill Rig, and Trucks
Noise due to equipment
Genomics
Fencing
N/A
N/A
Week of May 1, 2023
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
SBB (Lot 8) Earthwork
Grade and Bench
Loader and Excavator
Noise due to equipment
SBB (Lot 8) Earthwork
Soil Nail Wall
Loader, Drill Rig, and Trucks
Noise due to equipment
Genomics
Fire Alarm Testing (MEP testing and startup)
N/A
N/A
Current and Upcoming Anticipated Closures
The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete. Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.
Description
Location
Duration & Date
Impacted Buildings/ Facilities
Lot 8
Lot 8
Permanently
Lot 8
Lot 43
Lot 43
Indefinitely
Lot 43
-
950592 UCR SBB - Construction Alert #22
Current Weeks
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
SBB (Lot 8) Earthwork
Grade and Bench
Loader and Excavator
Noise due to equipment
Genomics
MEP Rough-in
N/A
N/A
Genomics
Site Wall
Skid steer / Mini Excavator
Noise due to equipment
SBB (Lot 8) Earthwork
Soil Nail Wall
Loader, Drill Rig, and Trucks
Noise due to equipment
Genomics
Grading for Flatwork
Skid steer / Mini Excavator
Noise due to equipment
Week of April 17, 2023
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
SBB (Lot 8) Earthwork
Grade and Bench
Loader and Excavator
Noise due to equipment
Genomics
MEP Finishes
N/A
N/A
Genomics
Asphalt
Skid steer/ Mini Excavator
Noise due to equipment
SBB (Lot 8) Earthwork
Soil Nail Wall
Loader, Drill Rig, and Trucks
Noise due to equipment
Week of April 24, 2023
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
SBB (Lot 8) Earthwork
Grade and Bench
Loader and Excavator
Noise due to equipment
Genomics
MEP Finishes
N/A
N/A
SBB (Lot 8) Earthwork
Soil Nail Wall
Loader, Drill Rig, and Trucks
Noise due to equipment
Genomics
Fencing
N/A
N/A
Current and Upcoming Anticipated Closures
The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete. Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.
Description
Location
Duration & Date
Impacted Buildings/ Facilities
Lot 8
Lot 8
Permanently
Lot 8
Lot 43
Lot 43
Indefinitely
Lot 43
-
950592 UCR SBB - Construction Alert #21
Current Weeks
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
SBB (Lot 8) Earthwork
Soil Nail Wall Mob
Loader, Drill Rig, and Trucks
Noise due to equipment
Genomics
Install Metal Building (PEMB)
N/A
N/A
SBB (Lot 8) Earthwork
Clear & Grub for SBB and Export Dirt
Loader and Excavator
Noise due to equipment
Genomics
Site Wall
Skid Steer/Mini Excavator
Noise due to equipment
Genomics
MEP Rough-in
N/A
N/A
Week of April 10, 2023
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
SBB (Lot 8) Earthwork
Clear & Grub for SBB and Misc. Export
Loader and Excavator
Noise due to equipment
Genomics
MEP Rough-in
N/A
N/A
Genomics
Site Wall
Skid steer / Mini Excavator
Noise due to equipment
SBB (Lot 8) Earthwork
Soil Nail Wall
Loader, Drill Rig, and Trucks
Noise due to equipment
Week of April 17, 2023
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
SBB (Lot 8)
Site Utilities
Backhoe, excavator, trucks
Noise due to equipment
SBB (Lot 8) Earthwork
Grade and Bench
Loader and Excavator
Noise due to equipment
Genomics
MEP Finishes
N/A
N/A
Genomics
Site Wall
Skid steer/ Mini Excavator
Noise due to equipment
SBB (Lot 8) Earthwork
Soil Nail Wall
Loader, Drill Rig, and Trucks
Noise due to equipment
Current and Upcoming Anticipated Closures
The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete. Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.
Description
Location
Duration & Date
Impacted Buildings/ Facilities
Lot 8
Lot 8
Permanently
Lot 8
Lot 43
Lot 43
Indefinitely
Lot 43
-
950592 UCR SBB - Construction Alert #20
Current Weeks
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
SBB (Lot 8) Earthwork
Soil Nail Wall
Loader, Drill Rig, and Trucks
Noise due to equipment
Genomics
Install Metal Building (PEMB)
N/A
N/A
SBB (Lot 8) Earthwork
Clear & Grub for SBB
Loader and Excavator
Noise due to equipment
Genomics
Site Wall
Skid Steer
Noise due to equipment
Week of April 3, 2023
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
SBB (Lot 8)
Site Utilities
Backhoe, excavator, trucks
Noise due to equipment
SBB (Lot 8) Earthwork
Clear & Grub for SBB
Loader and Excavator
Noise due to equipment
Genomics
MEP Rough-in
N/A
N/A
Genomics
Site Wall
Skid steer
Noise due to equipment
SBB (Lot 8) Earthwork
Soil Nail Wall
Loader, Drill Rig, and Trucks
Noise due to equipment
Week of April 10, 2023
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
SBB (Lot 8)
Site Utilities
Backhoe, excavator, trucks
Noise due to equipment
SBB (Lot 8) Earthwork
Grade and Bench
Loader and Excavator
Noise due to equipment
Genomics
MEP Finishes
N/A
N/A
Genomics
Site Wall
Skid steer
Noise due to equipment
SBB (Lot 8) Earthwork
Soil Nail Wall
Loader, Drill Rig, and Trucks
Noise due to equipment
Current and Upcoming Anticipated Closures
The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete. Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.
Description
Location
Duration & Date
Impacted Buildings/ Facilities
Lot 8
Lot 8
Permanently
Lot 8
Lot 43
Lot 43
Indefinitely
Lot 43
-
950592 UCR SBB - Construction Alert #19
Current Weeks
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
SBB (Lot 8)
Locate and Cap Existing Utilities
N/A
N/A
Genomics
Install Metal Building (PEMB)
N/A
N/A
SBB (Site)
Street Paving
Trucks and Rollers
Noise due to equipment
SBB (Lot 8) Earthwork
Clear & Grub for SBB
Loader and Excavator
Noise due to equipment
Week of March 27, 2023
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
SBB (Lot 8) Earthwork
Soil Nail Wall
Loader, Drill Rig, and Trucks
Noise due to equipment
Genomics
Install Metal Building (PEMB)
N/A
N/A
SBB (Lot 8) Earthwork
Clear & Grub for SBB
Loader and Excavator
Noise due to equipment
Genomics
Site Wall
Skid Steer
Noise due to equipment
Week of April 3, 2023
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
SBB (Lot 8)
Site Utilities
Backhoe, excavator, trucks
Noise due to equipment
SBB (Lot 8) Earthwork
Clear & Grub for SBB
Loader and Excavator
Noise due to equipment
Genomics
MEP Rough-in
N/A
N/A
Genomics
Site Wall
Skid steer
Noise due to equipment
SBB (Lot 8) Earthwork
Soil Nail Wall
Loader, Drill Rig, and Trucks
Noise due to equipment
Current and Upcoming Anticipated Closures
The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete. Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.
Description
Location
Duration & Date
Impacted Buildings/ Facilities
Lot 8
Lot 8
Permanently
Lot 8
Lot 43
Lot 43
Indefinitely
Lot 43
-
950592 UCR SBB - Construction Alert #18 - Week 03/13/2023
Current Weeks
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
SBB (Lot 8)
Locate and Cap Existing Utilities
N/A
N/A
SBB (Lot 8)
Site Utilities
Backhoe, excavator, trucks
Noise due to equipment
Genomics
Install Metal Building (PEMB)
N/A
N/A
SBB (site electrical)
Concrete backfill of medium voltage trench
Concrete pump and trucks
Noise due to equipment
SBB (Lot 8)
Electrical Shutdown
N/A
N/A
Week of March 20, 2023
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
SBB (Lot 8)
Locate and Cap Existing Utilities
N/A
N/A
SBB (Lot 8)
Site Utilities
Backhoe, excavator, trucks
Noise due to equipment
Genomics
Install Metal Building (PEMB)
N/A
N/A
SBB (Lot 8) Earthwork
Clear & Grub for Soil Nail Wall
Loader and Excavator
Noise due to equipment
Genomics
Site Wall
Skid Steer
Noise due to equipment
Week of March 27, 2023
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
SBB (Lot 8)
Site Utilities
Backhoe, excavator, trucks
Noise due to equipment
Genomics
Install Metal Building (PEMB)
N/A
N/A
SBB (Lot 8) Earthwork
Clear & Grub for Soil Nail Wall
Loader and Excavator
Noise due to equipment
Genomics
MEP Rough-in
N/A
N/A
Genomics
Site Wall
Skid steer
Noise due to equipment
Current and Upcoming Anticipated Closures
The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete. Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.
Description
Location
Duration & Date
Impacted Buildings/ Facilities
Lot 8
Lot 8
Permanently
Lot 8
Lot 43
Lot 43
Indefinitely
Lot 43
-
UCR SBB - Construction Alert #17 - Week 03/06/2023
Current Weeks
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
SBB (Lot 8)
Locate and Cap Existing Utilities
N/A
N/A
SBB (Lot 8)
Site Utilities
Backhoe, excavator, trucks
Noise due to equipment
SBB (site electrical)
Pulling Medium Voltage cable
N/A
N/A
SBB (site electrical)
Setting new power pole
N/A
N/A
Genomics
Install Metal Building (PEMB)
N/A
N/A
SBB (site electrical)
Concrete backfill of medium voltage trench
Concrete pump and trucks
Noise due to equipment
SBB (Lot 8)
Domestic Water Shutdown
N/A
N/A
Week of March 13, 2023
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
SBB (Lot 8)
Locate and Cap Existing Utilities
N/A
N/A
SBB (Lot 8)
Site Utilities
Backhoe, excavator, trucks
Noise due to equipment
Genomics
Install Metal Building (PEMB)
N/A
N/A
SBB (Lot 8)
Electrical Shutdown
N/A
N/A
Week of March 20, 2023
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
SBB (Lot 8)
Locate and Cap Existing Utilities
N/A
N/A
SBB (Lot 8)
Site Utilities
Backhoe, excavator, trucks
Noise due to equipment
Genomics
Install Metal Building (PEMB)
N/A
N/A
SBB (Lot 8) Earthwork
Clear & Grub for Soil Nail Wall
Loader and Excavator
Noise due to equipment
Genomics
MEP Rough-in
N/A
N/A
Current and Upcoming Anticipated Closures
The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete. Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.
Description
Location
Duration & Date
Impacted Buildings/ Facilities
Lot 8
Lot 8
Permanently
Lot 8
Lot 43
Lot 43
Indefinitely
Lot 43
-
950592 - UCR SBB - Construction Alert #16 - Week 02/27/2023
Current Weeks
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
SBB (Lot 8)
Locate and Cap Existing Utilities
N/A
N/A
SBB (Lot 8)
Site Utilities
Backhoe, excavator, trucks
Noise due to equipment
Genomics
Metal Building Arrives (PEMB)
N/A
N/A
SBB (site electrical)
Pulling Medium Voltage cable
N/A
N/A
SBB (site electrical)
Installing conduit
N/A
N/A
Genomics
Form and reinforce SOG
N/A
N/A
Genomics
Concrete Pour
Concrete Pump
Noise due to equipment
Week of March 6, 2023
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
SBB (Lot 8)
Locate and Cap Existing Utilities
N/A
N/A
SBB (Lot 8)
Site Utilities
Backhoe, excavator, trucks
Noise due to equipment
SBB (site electrical)
Pulling Medium Voltage cable
N/A
N/A
SBB (site electrical)
Setting new power pole
N/A
N/A
Genomics
Install Metal Building (PEMB)
N/A
N/A
SBB (Lot 8)
Domestic Water Shutdown
N/A
N/A
Week of March 13, 2023
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
SBB (Lot 8)
Locate and Cap Existing Utilities
N/A
N/A
SBB (Lot 8)
Site Utilities
Backhoe, excavator, trucks
Noise due to equipment
Genomics
Install Metal Building (PEMB)
N/A
N/A
SBB (site electrical)
Pulling Medium Voltage cable
N/A
N/A
SBB (Lot 8) Earthwork
Clear & Grub for Soil Nail Wall
Loader and Excavator
Noise due to equipment
Current and Upcoming Anticipated Closures
The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete. Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.
Description
Location
Duration & Date
Impacted Buildings/ Facilities
Lot 8
Lot 8
Permanently
Lot 8
Lot 43
Lot 43
Indefinitely
Lot 43
-
950592 - UCR SBB - Construction Alert #15 - Week 02/20/2023
Current Weeks
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
SBB (Lot 8)
Locate and Cap Existing Utilities
N/A
N/A
SBB (Lot 8)
Site Utilities
Backhoe, excavator, trucks
Noise due to equipment
Genomics
Metal Building Arrives (PEMB)
N/A
N/A
SBB (site electrical)
Pulling Medium Voltage cable
N/A
N/A
Genomics
Back fill
Bobcat or skid-steer
Noise due to equipment
SBB (site electrical)
Installing conduit
N/A
N/A
Genomics
Form and reinforce SOG
N/A
N/A
Week of February 27, 2023
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
SBB (Lot 8)
Locate and Cap Existing Utilities
N/A
N/A
SBB (Lot 8)
Site Utilities
Backhoe, excavator, trucks
Noise due to equipment
SBB (site electrical)
Pulling Medium Voltage cable
N/A
N/A
SBB (site electrical)
Setting new power pole
N/A
N/A
SBB Earthwork
Clear & Grub for Soil Nail Wall
Loader and Excavator
Noise due to equipment
Genomics
Concrete Pour
Concrete Pump
Noise due to equipment
Week of March 6, 2023
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
SBB (Lot 8)
Locate and Cap Existing Utilities
N/A
N/A
SBB (Lot 8)
Site Utilities
Backhoe, excavator, trucks
Noise due to equipment
Genomics
Install Metal Building (PEMB)
N/A
N/A
SBB (site electrical)
Pulling Medium Voltage cable
N/A
N/A
SBB Earthwork
Clear & Grub for Soil Nail Wall
Loader and Excavator
Noise due to equipment
Current and Upcoming Anticipated Closures
The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete. Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.
Description
Location
Duration & Date
Impacted Buildings/ Facilities
Lot 8
Lot 8
Permanently
Lot 8
Lot 43
Lot 43
Indefinitely
Lot 43
-
950592 - UCR SBB - Construction Alert #14- Week 02/13/2023
Current Weeks
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
SBB (Lot 8)
Locate and Cap Existing Utilities
N/A
N/A
SBB (Lot 8)
Domestic Water Shutdown Feb. 15th
N/A
Shutdown water to the greenhouses
SBB (Lot 8)
Campus Drive Lane Closure
N/A
Single Lane Traffic
SBB (Lot 8)
Site Utilities
Backhoe, excavator, trucks
Noise due to equipment
SBB (Lot 8)
Electrical Trenching
N/A
Noise due to equipment (College Place)
Genomics
Under-slab plumbing and electrical
N/A
N/A
SBB (Lot 8)
College Place Closure
N/A
College Place Closure
Genomics
Anchor Bolt Installation
N/A
N/A
Genomics
Concrete Pour
Concrete Pump
Noise due to equipment
Genomics
Back fill
Bobcat or skid-steer
Noise due to equipment
SBB (site electrical)
Installing conduit
N/A
N/A
Genomics
Form and reinforce SOG
N/A
N/A
Week of February 20, 2023
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
SBB (Lot 8)
Locate and Cap Existing Utilities
N/A
N/A
SBB (Lot 8)
Site Utilities
Backhoe, excavator, trucks
Noise due to equipment
Genomics
Install Metal Building (PEMB)
N/A
N/A
SBB (site electrical)
Pulling Medium Voltage cable
N/A
N/A
SBB (site electrical)
Setting new power pole
N/A
N/A
Genomics
Back fill
Bobcat or skid-steer
Noise due to equipment
Week of February 27, 2023
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
SBB (Lot 8)
Locate and Cap Existing Utilities
N/A
N/A
SBB (Lot 8)
Site Utilities
Backhoe, excavator, trucks
Noise due to equipment
Genomics
Install Metal Building (PEMB)
N/A
N/A
SBB (site electrical)
Pulling Medium Voltage cable
N/A
N/A
SBB (site electrical)
Setting new power pole
N/A
N/A
SBB Earthwork
Clear & Grub for Soil Nail Wall
Loader and Excavator
Noise due to equipment
Current and Upcoming Anticipated Closures
The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete. Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.
Description
Location
Duration & Date
Impacted Buildings/ Facilities
Lot 8
Lot 8
Permanently
Lot 8
Lot 43
Lot 43
Indefinitely
Lot 43
-
950592 - UCR SBB - Construction Alert #13- Week 02/06/2023
Current Weeks
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
SBB (Lot 8)
Locate and Cap Existing Utilities
N/A
N/A
SBB (Lot 8)
Campus Drive Lane Closure
N/A
Single Lane Traffic
SBB (Lot 8)
Site Utilities
Back hoe, excavator, trucks
Noise due to equipment
SBB (Lot 8)
Electrical Trenching
N/A
Noise due to equipment (College Place)
SBB (Lot 8)
College Place Closure
N/A
College Place Closure
SBB (Lot 8)
Gas Shutdown Feb. 10th
N/A
Shutdown gas to the greenhouses
Genomics
Waterproofing
N/A
N/A
Existing Sheds
Demo Existing Sheds
Excavator
Noise due to equipment
Week of February 13, 2023
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
SBB (Lot 8)
Locate and Cap Existing Utilities
N/A
N/A
SBB (Lot 8)
Domestic Water Shutdown Feb. 15th
N/A
Shutdown water to the greenhouses
SBB (Lot 8)
Campus Drive Lane Closure
N/A
Single Lane Traffic
SBB (Lot 8)
Site Utilities
Back hoe, excavator, trucks
Noise due to equipment
SBB (Lot 8)
Electrical Trenching
N/A
Noise due to equipment (College Place)
Genomics
Underslab plumbing and electrical
N/A
N/A
SBB (Lot 8)
College Place Closure
N/A
College Place Closure
Genomics
Anchor Bolt Installation
N/A
N/A
Genomics
Concrete Pour
Concrete Pump
Noise due to equipment
Genomics
Back fill
Bobcat or skid-steer
Noise due to equipment
SBB (site electrical)
Installing conduit
N/A
N/A
Genomics
Form and reinforce SOG
N/A
N/A
Week of February 20, 2023
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
SBB (Lot 8)
Locate and Cap Existing Utilities
N/A
N/A
SBB (Lot 8)
Site Utilities
Back hoe, excavator, trucks
Noise due to equipment
Genomics
Install Metal Building
N/A
N/A
SBB (site electrical)
Pulling Medium Voltage cable
N/A
N/A
SBB (site electrical)
Setting new power pole
N/A
N/A
Genomics
Back fill
Bobcat or skid-steer
Noise due to equipment
Current and Upcoming Anticipated Closures
The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete. Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.
Description
Location
Duration & Date
Impacted Buildings/ Facilities
Lot 8
Lot 8
Permanently
Lot 8
Lot 43
Lot 43
Indefinitely
Lot 43
-
950592 - UCR SBB - Construction Alert #12- Week 01/30/2023
Current Weeks
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
Genomics
Underground Electrical
N/A
N/A
Genomics
CMU Stem wall
N/A
N/A
SBB (Lot 8)
Locate and Cap Existing Utilities
N/A
N/A
SBB (Lot 8)
Campus Drive Lane Closure
N/A
Single Lane Traffic
SBB (Lot 8)
Site Utilities
Back hoe, excavator, trucks
Noise due to equipment
SBB (Lot 8)
Electrical Trenching
N/A
Noise due to equipment (College Place)
SBB (Lot 8)
College Place Closure
N/A
College Place Closure
Existing Sheds
Demo Existing Sheds
Excavator
Noise due to equipment
Week of February 06, 2023
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
SBB (Lot 8)
Locate and Cap Existing Utilities
N/A
N/A
SBB (Lot 8)
Campus Drive Lane Closure
N/A
Single Lane Traffic
SBB (Lot 8)
Site Utilities
Back hoe, excavator, trucks
Noise due to equipment
SBB (Lot 8)
Electrical Trenching
N/A
Noise due to equipment (College Place)
SBB (Lot 8)
College Place Closure
N/A
College Place Closure
SBB (Lot 8)
Gas Shutdown Feb. 10th
N/A
Shutdown gas to the greenhouses
Existing Sheds
Demo Existing Sheds
Excavator
Noise due to equipment
Week of February 13, 2023
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
SBB (Lot 8)
Locate and Cap Existing Utilities
N/A
N/A
SBB (Lot 8)
Domestic Water Shutdown Feb. 15th
N/A
Shutdown water to the greenhouses
SBB (Lot 8)
Campus Drive Lane Closure
N/A
Single Lane Traffic
SBB (Lot 8)
Site Utilities
Back hoe, excavator, trucks
Noise due to equipment
SBB (Lot 8)
Electrical Trenching
N/A
Noise due to equipment (College Place)
SBB (Lot 8)
College Place Closure
N/A
College Place Closure
Genomics
Anchor Bolt Installation
N/A
N/A
Genomics
Concrete Pour
Concrete Pump
Noise due to equipment
Genomics
Back fill
Bobcat or skid-steer
Noise due to equipment
Genomics
Form and reinforce SOG
N/A
N/A
Current and Upcoming Anticipated Closures
The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete. Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.
Description
Location
Duration & Date
Impacted Buildings/ Facilities
Lot 8
Lot 8
Permanently
Lot 8
Lot 43
Lot 43
Indefinitely
Lot 43
Campus Drive
Single Lane Closure
Until 02/09/23
Buildings along Campus Drive
-
950592 - UCR SBB - Construction Alert #11- Week 01/23/2023
Current Weeks
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
Genomics
Underground Electrical
N/A
N/A
Genomics
Form and pour foundations
pump
Noise due to equipment
SBB (Lot 8)
Locate and Cap Existing Utilities
N/A
N/A
SBB (Lot 8)
Campus Drive Lane Closure
N/A
Single Lane Traffic
SBB (Lot 8)
Site Utilities
Back hoe, excavator, trucks
Noise due to equipment
SBB (Lot 8)
Electrical Trenching
N/A
Noise due to equipment (College Place)
SBB (Lot 8)
College Place Closure
N/A
College Place Closure
Week of January 30, 2023
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
Genomics
Underground Electrical
N/A
N/A
Genomics
CMU Stem wall
N/A
N/A
SBB (Lot 8)
Locate and Cap Existing Utilities
N/A
N/A
SBB (Lot 8)
Campus Drive Lane Closure
N/A
Single Lane Traffic
SBB (Lot 8)
Site Utilities
Back hoe, excavator, trucks
Noise due to equipment
SBB (Lot 8)
Electrical Trenching
N/A
Noise due to equipment (College Place)
SBB (Lot 8)
College Place Closure
N/A
College Place Closure
Week of February 6, 2023
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
SBB (Lot 8)
Locate and Cap Existing Utilities
N/A
N/A
SBB (Lot 8)
Campus Drive Lane Closure
N/A
Single Lane Traffic
SBB (Lot 8)
Site Utilities
Back hoe, excavator, trucks
Noise due to equipment
SBB (Lot 8)
Electrical Trenching
N/A
Noise due to equipment (College Place)
SBB (Lot 8)
College Place Closure
N/A
College Place Closure
Current and Upcoming Anticipated Closures
The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete. Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.
Description
Location
Duration & Date
Impacted Buildings/ Facilities
Lot 8
Lot 8
Permanently
Lot 8
Lot 43
Lot 43
Indefinitely
Lot 43
-
950592 - UCR SBB - Construction Alert #10- Week 01/16/2023
Current Weeks
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
Genomics
Footing excavation
Back Hoe, mini-ex, dump truck
Noise due to equipment
Genomics
Rebar Install
N/A
N/A
Genomics
Underground Electrical
N/A
N/A
Week of January 23, 2023
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
Genomics
Underground Electrical
N/A
N/A
Genomics
Form and pour foundations
pump
Noise due to equipment
SBB (Lot 8)
Locate and Cap Existing Utilities
N/A
N/A
SBB (Lot 8)
Campus Drive Lane Closure
N/A
Single Lane Traffic
SBB (Lot 8)
Site Utilities
Back hoe, excavator, trucks
Noise due to equipment
SBB (Lot 8)
Electrical Trenching
N/A
Noise due to equipment (College Place)
SBB (Lot 8)
College Place Closure
N/A
College Place Closure
Week of January 30, 2023
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
SBB (Lot 8)
Locate and Cap Existing Utilities
N/A
N/A
SBB (Lot 8)
Campus Drive Lane Closure
N/A
Single Lane Traffic
SBB (Lot 8)
Site Utilities
Back hoe, excavator, trucks
Noise due to equipment
SBB (Lot 8)
Electrical Trenching
N/A
Noise due to equipment (College Place)
SBB (Lot 8)
College Place Closure
N/A
College Place Closure
Current and Upcoming Anticipated Closures
The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete. Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.
Description
Location
Duration & Date
Impacted Buildings/ Facilities
Lot 8
Lot 8
Indefinitely
Lot 8
Lot 43
Lot 43
Indefinitely
Lot 43
-
950592 - UCR SBB - Construction Alert #9
Week of January 9, 2023
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
Lot 43
Trailer Interior/Exterior Build-out
Small hand tools
Noise due to hand tools
Bio-Control
Relocate Existing Lines (Water, Telecom, and electrical)
N/A
N/A
Genomics
Excavate and Weather Protect Footings
Back Hoe, mini-ex, dump truck
Noise due to equipment
Week of January 16, 2023
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
Genomics
Footing excavation
Back Hoe, mini-ex, dump truck
Noise due to equipment
Genomics
Rebar Install
N/A
N/A
Genomics
Form and pour foundations
pump
Noise due to equipment
Genomics
Underground Electrical
N/A
N/A
Week of January 23, 2023
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
SBB (Lot 8)
Locate and Cap Existing Utilities
N/A
N/A
SBB (Lot 8)
Campus Drive Lane Closure
N/A
Single Lane Traffic
SBB (Lot 8)
Site Utilities
Back hoe, excavator, trucks
Noise due to equipment
SBB (Lot 8)
Electrical Trenching
N/A
Noise due to equipment (College Place)
SBB (Lot 8)
College Place Closure
N/A
College Place Closure
Current and Upcoming Anticipated Closures
The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete. Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.
Description
Location
Duration & Date
Impacted Buildings/ Facilities
Lot 8
Lot 8
Indefinitely
Lot 8
Lot 43
Lot 43
Indefinitely
Lot 43
-
950592 - UCR SBB - Construction Alert #8 Week 01/2/2023
Current Weeks
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
Lot 43
Trailer Interior/Exterior Build-out
Small hand tools
Noise due to hand tools
Genomics
Grading
N/A
N/A
Bio-Control
Relocate Existing Lines (Water, Telecom, and electrical)
N/A
N/A
Week of January 09, 2023
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
Genomics
Footing excavation
Back Hoe, mini-ex, dump truck
Noise due to equipment
Bio-Control
Relocate Existing Lines (Water, Telecom, and electrical)
N/A
N/A
Week of January 16, 2023
Construction Activities
Location
Activity
Equipment Used
Anticipated Disturbance
Genomics
Rebar Install
N/A
N/A
SBB (Lot 8)
Site Utilities Excavation
Mini-Ex and Asphalt Removal
N/A
Current and Upcoming Anticipated Closures
The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete. Please contact John Franklin with any specific questions or concerns at john.franklin@ucr.edu.
Description
Location
Duration & Date
Impacted Buildings/ Facilities
Lot 8
Lot 8
Indefinitely
Lot 8
Lot 43
Lot 43
Indefinitely
Lot 43
Project Timeline:
Anticipated Start:
Fall, 2022
Anticipated Completion:
Summer, 2024
PD&C Contact:
Project Manager: John Franklin
tel: (951) 203-7920 (951) 827-2421
Project Planner: Melissa Garrety
tel: (951) 827-7376
Project Working Group:
Danko Turcic
Jean Helwege
Jennifer Osborne
Kathy Drake
Kennett Lai
Patrick Latimer
Rami Zwick
Sabine Freij
Signup for construction updates on this project