Student Health and Counseling Center

 

Student Health and Counseling Center

Create an identifiable and easily accessible facility that welcomes members of our diverse campus community and conveys a commitment to quality care, innovation in technical, medical and clinical services, student support and well being. This facility aligns with the missions and values of the UCR campus, the Division of Student Affairs, Student Health Services, Counseling and Psychological Services, Student Affairs Case Management, and The Well that support student retention and success through optimization of emotional and physical health, through direct service, promotion, prevention, education, student engagement, and provision of resources and referrals.


Project Scope:

  • The new SHCC will further improve health, counseling and wellness services currently provided at the Campus
  • It will offer integrated and holistic care in a welcoming and student-centered environment, with increased medical and mental health providers on staff
  • The design of the SHCC should address the students’ experience
  • In addition to providing medical and mental health services, the new facility is envisioned as a destination within the UCR Campus
  • While the current Student Health Center is relatively insular, the new SHCC should be more visible and become an integral part of the UCR Campus
  • Different programs within the SHCC will share common resources and they will be administered accordingly
  • The SHCC building space should provide opportunities for collaboration, be flexible and have room for growth
  • To best serve the significant number of commuter students. t the SHCC should be a comfortable and welcoming space that accommodates these students while waiting for appointments

Student Health & Counseling Center Construction Updates
  • 950578- STUDENT HEALTH & COUNSELING CENTER CONSTRUCTION ADVISORY #43

    Current Weeks

    Construction Activities

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Project Site

    Restroom tile installation

     

    various hand tools,

    Low level of pedestrian noise including occasional hammering, and backup alarms.

     

    Project Site

    Low Voltage Installation

     

    various hand tools,

    Low level of pedestrian noise including occasional hammering, and backup alarms.

     

    Project Site

    Drywall, Tape, Mud and Paint

     

    various hand tools,

    Low level of pedestrian noise including occasional hammering, and backup alarms.

     

    Project Site

    Exterior Landscaping

     

    Excavator, various hand tools

    Moderate level of pedestrian noise including occasional hammering, and backup alarms.

     

    Contractor Parking Area

    Continued parking for contractor and sub-contractors; storage of equipment

     

    Contractor vehicles

    Low level of vehicle and pedestrian noise.

     

    Contractor Offices

    Continued office use

    Office Equipment and Furniture

    Low level of pedestrian noise

     

    Week of May 1

    Construction Activities

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Project Site

    Continuation of restroom tile installation

     

    various hand tools,

    Low level of pedestrian noise including occasional hammering, and backup alarms.

     

    Project Site

    Continuation of Low Voltage Installation

     

    various hand tools,

    Low level of pedestrian noise including occasional hammering, and backup alarms.

     

    Project Site

    Exterior Landscaping

     

    Excavator, various hand tools

    Moderate level of pedestrian noise including occasional hammering, and backup alarms.

     

    Project Site

    Parking Lot Demolition

     

    Excavator, Sawcutter, Jackhammer

    Moderate level of noise including running engines, and backup alarms with high levels of short sustained noise from jackhammering and sawcutting.

     

    Contractor Parking Area

    Continued parking for contractor and sub-contractors; storage of equipment

     

    Contractor vehicles

    Low level of vehicle and pedestrian noise.

     

    Contractor Offices

    Continued office use

    Office Equipment and Furniture

    Low level of pedestrian noise

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact Dexter Galang with any specific questions or concerns at dexter.galang@ucr.edu.

     

    Description

    Location

    Duration & Date

    Description and Impacted Buildings/ Facilities

    North Sidewalk

    Sidewalk at Linden from Dundee- Glasgow access road to Parking Lot 21 driveway

    Until Mid-June

    The north sidewalk will be closed and construction fence line relocated to allow for equipment to access the north landscape area.  Traffic speed limits will be lower and cones will divide the street for safety proposes.

  • 950578- STUDENT HEALTH & COUNSELING CENTER CONSTRUCTION ADVISORY #42

    Current Weeks

    Construction Activities

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Project Site

    Restroom tile installation

     

    various hand tools,

    Low level of pedestrian noise including occasional hammering, and backup alarms.

     

    Project Site

    Low Voltage Installation

     

    various hand tools,

    Low level of pedestrian noise including occasional hammering, and backup alarms.

     

    Project Site

    Drywall, Tape, Mud and Paint

     

    various hand tools,

    Low level of pedestrian noise including occasional hammering, and backup alarms.

     

    Project Site

    Exterior Landscaping

     

    Excavator, various hand tools

    Moderate level of pedestrian noise including occasional hammering, and backup alarms.

     

    Contractor Parking Area

    Continued parking for contractor and sub-contractors; storage of equipment

     

    Contractor vehicles

    Low level of vehicle and pedestrian noise.

     

    Contractor Offices

    Continued office use

    Office Equipment and Furniture

    Low level of pedestrian noise

     

    Week of April 24

    Construction Activities

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Project Site

    Continuation of restroom tile installation

     

    various hand tools,

    Low level of pedestrian noise including occasional hammering, and backup alarms.

     

    Project Site

    Continuation of Low Voltage Installation

     

    various hand tools,

    Low level of pedestrian noise including occasional hammering, and backup alarms.

     

    Project Site

    Exterior Landscaping

     

    Excavator, various hand tools

    Moderate level of pedestrian noise including occasional hammering, and backup alarms.

     

    Contractor Parking Area

    Continued parking for contractor and sub-contractors; storage of equipment

     

    Contractor vehicles

    Low level of vehicle and pedestrian noise.

     

    Contractor Offices

    Continued office use

    Office Equipment and Furniture

    Low level of pedestrian noise

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact Dexter Galang with any specific questions or concerns at dexter.galang@ucr.edu.

     

    Description

    Location

    Duration & Date

    Description and Impacted Buildings/ Facilities

    North Sidewalk

    Sidewalk at Linden from Dundee- Glasgow access road to Parking Lot 21 driveway

    Until Mid-June

    The north sidewalk will be closed and construction fence line relocated to allow for equipment to access the north landscape area.  Traffic speed limits will be lower and cones will divide the street for safety proposes.

  • 950578- STUDENT HEALTH & COUNSELING CENTER CONSTRUCTION ADVISORY #41

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Project Site

    Continuation of Exterior wall foam insulation and stucco installation

     

    Rough terrain lift, delivery trucks, various hand and power tools

    Moderate level of engine and pedestrian noise including occasional High level of noise from hammering and backup alarms.

     

    Project Site

    Continuation of Exterior wall caulking and weatherproofing

     

    Rough terrain lift, delivery trucks, various hand and power tools

    Moderate level of engine and pedestrian noise including occasional High level of noise from hammering and backup alarms.

     

    Project Site

    Exterior Landscaping Installation

     

    Excavator, various hand tools

    Moderate level of pedestrian noise including occasional hammering, and backup alarms.

     

    Contractor Parking Area

    Continued parking for contractor and sub-contractors; storage of equipment

     

    Contractor vehicles

    Low level of vehicle and pedestrian noise.

     

    Contractor Offices

    Continued office use

    Office Equipment and Furniture

    Low level of pedestrian noise

     

     

     

    Week of April 10, 2023

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Project Site

    Continuation of Exterior wall foam insulation and stucco installation

     

    Rough terrain lift, delivery trucks, various hand and power tools

    Moderate level of engine and pedestrian noise including occasional High level of noise from hammering and backup alarms.

     

    Project Site

    Continuation of Exterior wall caulking and weatherproofing

     

    Rough terrain lift, delivery trucks, various hand and power tools

    Moderate level of engine and pedestrian noise including occasional High level of noise from hammering and backup alarms.

     

    Project Site

    Continuation of Exterior Landscaping Installation

     

    Excavator, various hand tools

    Moderate level of pedestrian noise including occasional hammering, and backup alarms.

     

    Contractor Parking Area

    Continued parking for contractor and sub-contractors; storage of equipment

     

    Contractor vehicles

    Low level of vehicle and pedestrian noise.

     

    Contractor Offices

    Continued office use

    Office Equipment and Furniture

    Low level of pedestrian noise

     

     

    Current and Upcoming Anticipated Shutdowns/ Closures

    The following shutdowns/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact Dexter Galang with any specific questions or concerns at dexter.galang@ucr.edu.

     

    Description

    Location

    Duration & Date

    Description and Impacted Buildings/ Facilities

    North Sidewalk

    Sidewalk at Linden from Dundee- Glasgow access road to Parking Lot 21 driveway

    2 months

    The north sidewalk will be closed and construction fence line relocated to allow for equipment to access the north landscape area.  Traffic speed limits will be lower and cones will divide the street for safety proposes.

  • 950578- STUDENT HEALTH & COUNSELING CENTER CONSTRUCTION ADVISORY #40

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Project Site

    Continuation of Exterior wall EIFS installation

     

    Rough terrain lift, delivery trucks, various hand and power tools

    Moderate level of engine and pedestrian noise including occasional High level of noise from hammering and backup alarms.

     

    Project Site

    Continuation of Exterior wall caulking and weatherproofing

     

    Rough terrain lift, delivery trucks, various hand and power tools

    Moderate level of engine and pedestrian noise including occasional High level of noise from hammering and backup alarms.

     

    Project Site

    Continuation of interior wall drywall, tape, mud and paint

     

    Various hand tools, scissor lift

    Moderate level of pedestrian noise including occasional hammering, electric sawing and backup alarms.

     

    Project Site

    Continuation of interior MEP installation

     

    Various hand tools, scissor lift

    Moderate level of pedestrian noise including occasional hammering, and backup alarms.

    Project Site

    Continuation of Exterior Glass Installation

     

    Various hand tools, scissor lift

    Moderate level of pedestrian noise including occasional hammering, and backup alarms.

     

    Contractor Parking Area

    Continued parking for contractor and sub-contractors; storage of equipment

     

    Contractor vehicles

    Low level of vehicle and pedestrian noise.

     

    Contractor Offices

    Continued office use

    Office Equipment and Furniture

    Low level of pedestrian noise

     

     

     

    Week of March 20, 2022

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Project Site

    Continuation of Exterior wall EIFS installation

     

    Rough terrain lift, delivery trucks, various hand and power tools

    Moderate level of engine and pedestrian noise including occasional High level of noise from hammering and backup alarms.

     

    Project Site

    Continuation of installation of trellis steel

    Rough terrain lift, delivery trucks, various hand and power tools

    Moderate level of engine and pedestrian noise including occasional High level of noise from hammering and backup alarms.

     

    Project Site

    Continuation of Exterior wall caulking and weatherproofing

     

    Rough terrain lift, delivery trucks, various hand and power tools

    Moderate level of engine and pedestrian noise including occasional High level of noise from hammering and backup alarms.

     

    Project Site

    Continuation of interior wall drywall, tape, mud and paint

     

    Various hand tools, scissor lift

    Moderate level of pedestrian noise including occasional hammering, electric sawing and backup alarms.

     

    Project Site

    Continuation of interior MEP installation

     

    Various hand tools, scissor lift

    Moderate level of pedestrian noise including occasional hammering, and backup alarms.

    Project Site

    Continuation of Exterior Glass Installation

     

    Various hand tools, scissor lift

    Moderate level of pedestrian noise including occasional hammering, and backup alarms.

     

    Contractor Parking Area

    Continued parking for contractor and sub-contractors; storage of equipment

     

    Contractor vehicles

    Low level of vehicle and pedestrian noise.

     

    Contractor Offices

    Continued office use

    Office Equipment and Furniture

    Low level of pedestrian noise

     

     

    Current and Upcoming Anticipated Shutdowns/ Closures

    The following shutdowns/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact Dexter Galang with any specific questions or concerns at dexter.galang@ucr.edu.

     

    Description

    Location

    Duration & Date

    Description and Impacted Buildings/ Facilities

    None at this time

     

     

     

  • 950578- STUDENT HEALTH & COUNSELING CENTER CONSTRUCTION ADVISORY #39

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Project Site

    Continuation of Exterior wall foam insulation and stucco installation

     

    Rough terrain lift, delivery trucks, various hand and power tools

    Moderate level of engine and pedestrian noise including occasional High level of noise from hammering and backup alarms.

     

    Project Site

    Continuation of Exterior wall caulking and weatherproofing

     

    Rough terrain lift, delivery trucks, various hand and power tools

    Moderate level of engine and pedestrian noise including occasional High level of noise from hammering and backup alarms.

     

    Project Site

    Continuation of interior wall drywall, tape, mud and paint

     

    Various hand tools, scissor lift

    Moderate level of pedestrian noise including occasional hammering, electric sawing and backup alarms.

     

    Project Site

    Continuation of interior MEP installation

     

    Various hand tools, scissor lift

    Moderate level of pedestrian noise including occasional hammering, and backup alarms.

    Project Site

    Continuation of Exterior Glass Installation

     

    Various hand tools, scissor lift

    Moderate level of pedestrian noise including occasional hammering, and backup alarms.

     

    Contractor Parking Area

    Continued parking for contractor and sub-contractors; storage of equipment

     

    Contractor vehicles

    Low level of vehicle and pedestrian noise.

     

    Contractor Offices

    Continued office use

    Office Equipment and Furniture

    Low level of pedestrian noise

     

     

     

    Week of February 27, 2022

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Project Site

    Continuation of Exterior wall foam insulation and stucco installation

     

    Rough terrain lift, delivery trucks, various hand and power tools

    Moderate level of engine and pedestrian noise including occasional High level of noise from hammering and backup alarms.

     

    Project Site

    Continuation of Exterior wall caulking and weatherproofing

     

    Rough terrain lift, delivery trucks, various hand and power tools

    Moderate level of engine and pedestrian noise including occasional High level of noise from hammering and backup alarms.

     

    Project Site

    Continuation of interior wall drywall, tape, mud and paint

     

    Various hand tools, scissor lift

    Moderate level of pedestrian noise including occasional hammering, electric sawing and backup alarms.

     

    Project Site

    Continuation of interior MEP installation

     

    Various hand tools, scissor lift

    Moderate level of pedestrian noise including occasional hammering, and backup alarms.

    Project Site

    Continuation of Exterior Glass Installation

     

    Various hand tools, scissor lift

    Moderate level of pedestrian noise including occasional hammering, and backup alarms.

     

    Contractor Parking Area

    Continued parking for contractor and sub-contractors; storage of equipment

     

    Contractor vehicles

    Low level of vehicle and pedestrian noise.

     

    Contractor Offices

    Continued office use

    Office Equipment and Furniture

    Low level of pedestrian noise

     

     

    Current and Upcoming Anticipated Shutdowns/ Closures

    The following shutdowns/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact Dexter Galang with any specific questions or concerns at dexter.galang@ucr.edu.

     

    Description

    Location

    Duration & Date

    Description and Impacted Buildings/ Facilities

    Non at this time

     

     

     

  • 950578- STUDENT HEALTH & COUNSELING CENTER CONSTRUCTION ADVISORY #38

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Project Site

    Continuation of Exterior wall foam insulation and stucco installation

     

    Rough terrain lift, delivery trucks, various hand and power tools

    Moderate level of engine and pedestrian noise including occasional High level of noise from hammering and backup alarms.

     

    Project Site

    Continuation of Exterior wall caulking and weatherproofing

     

    Rough terrain lift, delivery trucks, various hand and power tools

    Moderate level of engine and pedestrian noise including occasional High level of noise from hammering and backup alarms.

     

    Project Site

    Continuation of interior wall drywall, tape, mud and paint

     

    Various hand tools, scissor lift

    Moderate level of pedestrian noise including occasional hammering, electric sawing and backup alarms.

     

    Project Site

    Continuation of interior MEP installation

     

    Various hand tools, scissor lift

    Moderate level of pedestrian noise including occasional hammering, and backup alarms.

    Project Site

    Continuation of Exterior Glass Installation

     

    Various hand tools, scissor lift

    Moderate level of pedestrian noise including occasional hammering, and backup alarms.

     

    Contractor Parking Area

    Continued parking for contractor and sub-contractors; storage of equipment

     

    Contractor vehicles

    Low level of vehicle and pedestrian noise.

     

    Contractor Offices

    Continued office use

    Office Equipment and Furniture

    Low level of pedestrian noise

     

     

     

    Week of February 13, 2022

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Project Site

    Continuation of Exterior wall foam insulation and stucco installation

     

    Rough terrain lift, delivery trucks, various hand and power tools

    Moderate level of engine and pedestrian noise including occasional High level of noise from hammering and backup alarms.

     

    Project Site

    Continuation of Exterior wall caulking and weatherproofing

     

    Rough terrain lift, delivery trucks, various hand and power tools

    Moderate level of engine and pedestrian noise including occasional High level of noise from hammering and backup alarms.

     

    Project Site

    Continuation of interior wall drywall, tape, mud and paint

     

    Various hand tools, scissor lift

    Moderate level of pedestrian noise including occasional hammering, electric sawing and backup alarms.

     

    Project Site

    Continuation of interior MEP installation

     

    Various hand tools, scissor lift

    Moderate level of pedestrian noise including occasional hammering, and backup alarms.

    Project Site

    Continuation of Exterior Glass Installation

     

    Various hand tools, scissor lift

    Moderate level of pedestrian noise including occasional hammering, and backup alarms.

     

    Contractor Parking Area

    Continued parking for contractor and sub-contractors; storage of equipment

     

    Contractor vehicles

    Low level of vehicle and pedestrian noise.

     

    Contractor Offices

    Continued office use

    Office Equipment and Furniture

    Low level of pedestrian noise

     

     

    Current and Upcoming Anticipated Shutdowns/ Closures

    The following shutdowns/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact Dexter Galang with any specific questions or concerns at dexter.galang@ucr.edu.

     

    Description

    Location

    Duration & Date

    Description and Impacted Buildings/ Facilities

    Electrical Shutdown

    Linden Street and Dundee Glasgow intersection

    Saturday, February 18

    Connection to Campus permanent power.

    Will require a 4 hour weekend power shutdown.  The effected buildings include those in the Corp Yard area (Facilities, Mail, Fleet Buildings).  Fire watch will be in place.

    Access at the intersection of Linden and Dundee Access Road may be limited at times however, flag people will be on site to guide traffic.

  • 950578- STUDENT HEALTH & COUNSELING CENTER CONSTRUCTION ADVISORY #37

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Project Site

    Continuation of exterior wall framing

     

    Rough terrain lift, delivery trucks, scaffolding, various hand and power tools

    Moderate level of engine and pedestrian noise including occasional High level of noise from hammering and backup alarms.

     

    Project Site

    Continuation of Storefront Installation

     

    Rough terrain lift, delivery trucks, scaffolding, various hand and power tools

    Moderate level of pedestrian noise including occasional High level of noise from hammering.

     

    Project Site

    Continuation of interior wall framing

     

    Various hand tools, scissor lift

    Moderate level of pedestrian noise including occasional hammering, electric sawing and backup alarms.

     

    Project Site

    Continuation of interior MEP installation

     

    Various hand tools, scissor lift

    Moderate level of pedestrian noise including occasional hammering, and backup alarms.

    Project Site

    Continuation of Drywall installation

     

    Various hand tools, scissor lift, rolling scaffolds

    Moderate level of pedestrian noise including occasional hammering, and backup alarms.

     

    Project Site

    Continuation of Interior Painting

     

    Various hand tools, scissor lift, rolling scaffolds

    Moderate level of pedestrian noise including occasional backup alarms.

     

    Contractor Parking Area

    Continued parking for contractor and sub-contractors; storage of equipment

     

    Contractor vehicles

    Low level of vehicle and pedestrian noise.

     

    Contractor Offices

    Continued office use

    Office Equipment and Furniture

    Low level of pedestrian noise

     

     

     

    Week of January 23, 2022

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Project Site

    Continuation of exterior wall framing

     

    Rough terrain lift, delivery trucks, scaffolding, various hand and power tools

    Moderate level of engine and pedestrian noise including occasional High level of noise from hammering and backup alarms.

     

    Project Site

    Continuation of Storefront Installation

     

    Rough terrain lift, delivery trucks, scaffolding, various hand and power tools

    Moderate level of pedestrian noise including occasional High level of noise from hammering.

     

    Project Site

    Continuation of interior wall framing

     

    Various hand tools, scissor lift

    Moderate level of pedestrian noise including occasional hammering, electric sawing and backup alarms.

     

    Project Site

    Continuation of interior MEP installation

     

    Various hand tools, scissor lift

    Moderate level of pedestrian noise including occasional hammering, and backup alarms.

    Project Site

    Continuation of Drywall installation

     

    Various hand tools, scissor lift, rolling scaffolds

    Moderate level of pedestrian noise including occasional hammering, and backup alarms.

     

    Project Site

    Continuation of Interior Painting

     

    Various hand tools, scissor lift, rolling scaffolds

    Moderate level of pedestrian noise including occasional backup alarms.

     

    Contractor Parking Area

    Continued parking for contractor and sub-contractors; storage of equipment

     

    Contractor vehicles

    Low level of vehicle and pedestrian noise.

     

    Contractor Offices

    Continued office use

    Office Equipment and Furniture

    Low level of pedestrian noise

     

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact Dexter Galang with any specific questions or concerns at dexter.galang@ucr.edu.

     

    Description

    Location

    Duration & Date

    Description and Impacted Buildings/ Facilities

    Electrical Shutdown

    Linden Street and Dundee Glasgow intersection

    Sunday, January 29

    Connection to Campus permanent power.  This activity will require a 8 hour weekend power shutdown that will affect the Corp Yard Area and a 4 hour power outage to TAPS and EH&S.

    Access along this road may be limited at times however, flag people will be on site to guide traffic.

     

  • 950578- STUDENT HEALTH & COUNSELING CENTER CONSTRUCTION ADVISORY #36

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Project Site

    Continuation of exterior wall framing

     

    Rough terrain lift, delivery trucks, scaffolding, various hand and power tools

    Moderate level of engine and pedestrian noise including occasional High level of noise from hammering and backup alarms.

     

    Project Site

    Storefront Installation

     

    Rough terrain lift, delivery trucks, scaffolding, various hand and power tools

    Moderate level of pedestrian noise including occasional High level of noise from hammering.

     

    Project Site

    Continuation of interior wall framing

     

    Various hand tools, scissor lift

    Moderate level of pedestrian noise including occasional hammering, electric sawing and backup alarms.

     

    Project Site

    Continuation of interior MEP installation

     

    Various hand tools, scissor lift

    Moderate level of pedestrian noise including occasional hammering, and backup alarms.

    Project Site

    Continuation of Drywall installation

     

    Various hand tools, scissor lift, rolling scaffolds

    Moderate level of pedestrian noise including occasional hammering, and backup alarms.

     

    Project Site

    Painting

     

    Various hand tools, scissor lift, rolling scaffolds

    Moderate level of pedestrian noise including occasional backup alarms.

     

    Contractor Parking Area

    Continued parking for contractor and sub-contractors; storage of equipment

     

    Contractor vehicles

    Low level of vehicle and pedestrian noise.

     

    Contractor Offices

    Continued office use

    Office Equipment and Furniture

    Low level of pedestrian noise

     

     

     

    Week of January 11, 2022

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Project Site

    Continuation of exterior wall framing

     

    Rough terrain lift, delivery trucks, scaffolding, various hand and power tools

    Moderate level of engine and pedestrian noise including occasional High level of noise from hammering and backup alarms.

     

    Project Site

    Storefront Installation

     

    Rough terrain lift, delivery trucks, scaffolding, various hand and power tools

    Moderate level of pedestrian noise including occasional High level of noise from hammering.

     

    Project Site

    Continuation of interior wall framing

     

    Various hand tools, scissor lift

    Moderate level of pedestrian noise including occasional hammering, electric sawing and backup alarms.

     

    Project Site

    Continuation of interior MEP installation

     

    Various hand tools, scissor lift

    Moderate level of pedestrian noise including occasional hammering, and backup alarms.

    Project Site

    Continuation of Drywall installation

     

    Various hand tools, scissor lift, rolling scaffolds

    Moderate level of pedestrian noise including occasional hammering, and backup alarms.

     

    Project Site

    Painting

     

    Various hand tools, scissor lift, rolling scaffolds

    Moderate level of pedestrian noise including occasional backup alarms.

     

    Contractor Parking Area

    Continued parking for contractor and sub-contractors; storage of equipment

     

    Contractor vehicles

    Low level of vehicle and pedestrian noise.

     

    Contractor Offices

    Continued office use

    Office Equipment and Furniture

    Low level of pedestrian noise

     

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact Dexter Galang with any specific questions or concerns at dexter.galang@ucr.edu.

     

    Description

    Location

    Duration & Date

    Description and Impacted Buildings/ Facilities

    Electrical Shutdown

    Linden Street and Dundee Glasgow intersection

    Sunday, January 29

    Connection to Campus permanent power.  This activity will require a 8 hour weekend power shutdown that will affect the Corp Yard Area and a 4 hour power outage to TAPS and EH&S.

    Access along this road may be limited at times however, flag people will be on site to guide traffic.

     

  • 950578- STUDENT HEALTH & COUNSELING CENTER CONSTRUCTION ADVISORY #35

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Project Site

    Continuation of exterior wall framing

     

    Rough terrain lift, delivery trucks, scaffolding, various hand and power tools

    Moderate level of engine and pedestrian noise including occasional High level of noise from hammering and backup alarms.

     

    Project Site

    Storefront Installation

     

    Rough terrain lift, delivery trucks, scaffolding, various hand and power tools

    Moderate level of pedestrian noise including occasional High level of noise from hammering.

     

    Project Site

    Continuation of roofing installation

     

    Rough terrain lift, delivery trucks, various hand and power tools

    Moderate level of pedestrian noise including occasional High level of noise from hammering, sawing and backup alarms.

     

    Project Site

    Continuation of interior wall framing

     

    Various hand tools, scissor lift

    Moderate level of pedestrian noise including occasional hammering, electric sawing and backup alarms.

     

    Project Site

    Continuation of interior MEP installation

     

    Various hand tools, scissor lift

    Moderate level of pedestrian noise including occasional hammering, and backup alarms.

    Project Site

    Continuation of Drywall installation

     

    Various hand tools, scissor lift, rolling scaffolds

    Moderate level of pedestrian noise including occasional hammering, and backup alarms.

     

    Contractor Parking Area

    Continued parking for contractor and sub-contractors; storage of equipment

     

    Contractor vehicles

    Low level of vehicle and pedestrian noise.

     

    Contractor Offices

    Continued office use

    Office Equipment and Furniture

    Low level of pedestrian noise

     

     

     

    Week of December 26, 2022

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Project Site

    Continuation of exterior wall framing

     

    Rough terrain lift, delivery trucks, scaffolding, various hand and power tools

    Moderate level of engine and pedestrian noise including occasional High level of noise from hammering and backup alarms.

     

    Project Site

    Continuation of Storefront Installation

     

    Rough terrain lift, delivery trucks, scaffolding, various hand and power tools

     

    Moderate level of pedestrian noise including occasional High level of noise from hammering.

     

    Project Site

    Continuation of roofing installation

     

    Rough terrain lift, delivery trucks, various hand and power tools

    Moderate level of pedestrian noise including occasional High level of noise from hammering, sawing and backup alarms.

     

    Project Site

    Continuation of interior wall framing

     

    Various hand tools, scissor lift

    Moderate level of pedestrian noise including occasional hammering, electric sawing and backup alarms.

     

    Project Site

    Continuation of interior MEP installation

     

    Various hand tools, scissor lift

    Moderate level of pedestrian noise including occasional hammering, and backup alarms.

    Project Site

    Continuation of Drywall installation

     

    Various hand tools, scissor lift, rolling scaffolds

     

    Moderate level of pedestrian noise including occasional hammering, and backup alarms.

     

    Contractor Parking Area

    Continued parking for contractor and sub-contractors; storage of equipment

     

    Contractor vehicles

    Low level of vehicle and pedestrian noise.

     

    Contractor Offices

    Continued office use

    Office Equipment and Furniture

    Low level of pedestrian noise

     

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact Dexter Galang with any specific questions or concerns at dexter.galang@ucr.edu.

     

    Description

    Location

    Duration & Date

    Description and Impacted Buildings/ Facilities

    Electrical Shutdown

    Linden Street and Dundee Glasgow intersection

    Saturday, January 28

    Connection to Campus permanent power.  Will require a 4 to 8 hour weekend power shutdown.  The effected buildings include those in the Corp Yard area (Facilities, Mail, Fleet Buildings)

    Access along this road may be limited at times however, flag people will be on site to guide traffic.

     

  • 950578- STUDENT HEALTH & COUNSELING CENTER CONSTRUCTION ADVISORY #34

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Project Site

    Exterior wall framing

     

    Rough terrain lift, delivery trucks, various hand and power tools

    Moderate level of engine and pedestrian noise including occasional High level of noise from hammering and backup alarms.

     

    Project Site

    Roofing installation

     

    Rough terrain lift, delivery trucks, various hand and power tools

    Moderate level of pedestrian noise including occasional High level of noise from hammering, sawing and backup alarms.

     

    Project Site

    Continuation of interior wall framing

     

    Various hand tools, scissor lift

    Moderate level of pedestrian noise including occasional hammering, electric sawing and backup alarms.

     

    Project Site

    Continuation of interior MEP installation

     

    Various hand tools, scissor lift

    Moderate level of pedestrian noise including occasional hammering, and backup alarms.

    Project Site

    Drywall installation

     

    Various hand tools, scissor lift

    Moderate level of pedestrian noise including occasional hammering, and backup alarms.

     

    Contractor Parking Area

    Continued parking for contractor and sub-contractors; storage of equipment

     

    Contractor vehicles

    Low level of vehicle and pedestrian noise.

     

    Contractor Offices

    Continued office use

    Office Equipment and Furniture

    Low level of pedestrian noise

     

     

     

    Week of December 12, 2022

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Project Site

    Continuation of Exterior wall framing

     

    Rough terrain lift, delivery trucks, various hand and power tools

    Moderate level of engine and pedestrian noise including occasional High level of noise from hammering and backup alarms.

     

    Project Site

    Continuation of Roofing installation

     

    Rough terrain lift, delivery trucks, various hand and power tools

    Moderate level of pedestrian noise including occasional High level of noise from hammering, sawing and backup alarms.

     

    Project Site

    Continuation of interior wall framing

     

    Various hand tools, scissor lift

    Moderate level of pedestrian noise including occasional hammering, electric sawing and backup alarms.

     

    Project Site

    Continuation of interior MEP installation

     

    Various hand tools, scissor lift

    Moderate level of pedestrian noise including occasional hammering, and backup alarms.

    Project Site

    Continuation of Drywall installation

     

    Various hand tools, scissor lift

    Moderate level of pedestrian noise including occasional hammering, and backup alarms.

     

    Contractor Parking Area

    Continued parking for contractor and sub-contractors; storage of equipment

     

    Contractor vehicles

    Low level of vehicle and pedestrian noise.

     

    Contractor Offices

    Continued office use

    Office Equipment and Furniture

    Low level of pedestrian noise

     

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact Dexter Galang with any specific questions or concerns at dexter.galang@ucr.edu.

     

    Description

    Location

    Duration & Date

    Description and Impacted Buildings/ Facilities

    Electrical Shutdown

    Linden Street and Dundee Glasgow intersection

    Saturday, January 28

    Connection to Campus permanent power.  Will require a 4 to 8 hour weekend power shutdown.  The effected buildings include those in the Corp Yard area (Facilities, Mail, Fleet Buildings)

    Access along this road may be limited at times however, flag people will be on site to guide traffic.

     

  • 950578- STUDENT HEALTH & COUNSELING CENTER CONSTRUCTION ADVISORY #33

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Project Site

    North perimeter wall installation

     

    Crane Truck, delivery trucks, various hand and power tools

    The crane will be located at the Linden Entrance to Facilities Services and Fleet Services.  Temporary access to and from the Facilities and Fleet Yards will be from the west gate in Lot 23 and the entry off of Watkins Drive.  The Crane will be offloading wall panels from trucks that will be occupying one lane of Linden Street.  Flag people will be onsite to control traffic.

    Moderate level of engine and pedestrian noise including occasional High level of noise from hammering and backup alarms.

     

    Project Site

    Continuation of Metal Stud Wall Framing

     

    Various hand and power tools, aerial device

    Moderate level of pedestrian noise including occasional High level of noise from hammering, sawing and backup alarms.

     

    Project Site

    Continuation of HVAC equipment installation

     

    Various hand tools, aerial device

    Moderate level of pedestrian noise including occasional hammering and backup alarms.

     

    Project Site

    Miscellaneous Concrete Work

     

    Various hand tools, jack hammer

    Moderate level of pedestrian noise with occasion high levels of noise from jackhammering.

     

    Project Site

    Continuation of in-wall utility installation

     

    Various hand tools, aerial device

    Moderate level of pedestrian noise including occasional hammering and backup alarms.

     

    Contractor Parking Area

    Continued parking for contractor and sub-contractors; storage of equipment

     

    Contractor vehicles

    Low level of vehicle and pedestrian noise.

     

    Contractor Offices

    Continued office use

    Office Equipment and Furniture

    Low level of pedestrian noise

     

     

     

    Week of November 14, 2022

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Project Site

    West perimeter wall installation

     

    Crane Truck, delivery trucks, various hand and power tools

    The crane will be located within the construction fence line and will be offloading wall panels from trucks that will be occupying one lane of the Dundee- Glasgow Access Road.  Flag people will be onsite to control traffic.

    Moderate level of engine and pedestrian noise including occasional High level of noise from hammering and backup alarms.

     

    Project Site

    Continuation of Metal Stud Wall Framing

     

    Various hand and power tools, aerial device

    Moderate level of pedestrian noise including occasional hammering, sawing and backup alarms.

     

    Project Site

    Miscellaneous Concrete Work

     

    Various hand tools, jack hammer

    Moderate level of pedestrian noise with occasion high levels of noise from jackhammering.

     

     

    Project Site

    Continuation of HVAC equipment installation

     

    Various hand tools, aerial device

    Moderate level of pedestrian noise including occasional hammering and backup alarms.

     

    Project Site

    Continuation of in wall utility installation

     

    Various hand tools, aerial device

    Moderate level of pedestrian noise including occasional hammering and backup alarms.

     

    Contractor Parking Area

    Continued parking for contractor and sub-contractors; storage of equipment

     

    Contractor vehicles

    Low level of vehicle and pedestrian noise.

     

    Contractor Offices

    Continued office use

    Office Equipment and Furniture

    Low level of pedestrian noise

     

    Current and Upcoming Anticipated Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact Dexter Galang with any specific questions or concerns at dexter.galang@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    North Exterior Wall Panel Crane

    Pick

    Linden Entrance to Facilities Services and Fleet Services (see Map A below)

    November 9-

    November 10

    The crane will be located at Linden Entrance to Facilities Services and Fleet Services.  Temporary access to and from the Corp Yard will be from the entrance off of Watkins Avenue.  The Crane will be offloading wall panels from trucks that will be occupying one lane of Linden Street.  Flag people will be onsite to control traffic.

     

    West Exterior Wall Panel Crane

    Pick

    Dundee- Glasgow Access Road (see Map B below)

    November 14-17

    The crane will be located within the construction fence line and will be offloading wall panels from trucks that will be occupying one lane of the Dundee- Glasgow Access Road.  Flag people will be onsite to control traffic.

     

  • 950578- STUDENT HEALTH & COUNSELING CENTER CONSTRUCTION ADVISORY #32

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Project Site

    North perimeter wall installation

     

    Crane Truck, delivery trucks, various hand and power tools

    The crane will be located at the Linden Entrance to Facilities Services and Fleet Services.  Temporary access to and from the Facilities and Fleet Yards will be from the west gate in Lot 23 and the entry off of Watkins Drive.  The Crane will be offloading wall panels from trucks that will be occupying one lane of Linden Street.  Flag people will be onsite to control traffic.

    Moderate level of engine and pedestrian noise including occasional High level of noise from hammering and backup alarms.

     

    Project Site

    Continuation of Metal Stud Wall Framing

     

    Various hand and power tools, aerial device

    Moderate level of pedestrian noise including occasional High level of noise from hammering, sawing and backup alarms.

     

    Project Site

    Continuation of HVAC equipment installation

     

    Various hand tools, aerial device

    Moderate level of pedestrian noise including occasional hammering and backup alarms.

     

    Project Site

    Continuation of in-wall utility installation

     

    Various hand tools, aerial device

    Moderate level of pedestrian noise including occasional hammering and backup alarms.

     

    Contractor Parking Area

    Continued parking for contractor and sub-contractors; storage of equipment

     

    Contractor vehicles

    Low level of vehicle and pedestrian noise.

     

    Contractor Offices

    Continued office use

    Office Equipment and Furniture

    Low level of pedestrian noise

     

     

     

    Week of November 7, 2022

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Project Site

    West perimeter wall installation

     

    Crane Truck, delivery trucks, various hand and power tools

    The crane will be located within the construction fence line and will be offloading wall panels from trucks that will be occupying one lane of the Dundee- Glasgow Access Road.  Flag people will be onsite to control traffic.

    Moderate level of engine and pedestrian noise including occasional High level of noise from hammering and backup alarms.

     

    Project Site

    Continuation of Metal Stud Wall Framing

     

    Various hand and power tools, aerial device

    Moderate level of pedestrian noise including occasional hammering, sawing and backup alarms.

     

    Project Site

    Continuation of HVAC equipment installation

     

    Various hand tools, aerial device

    Moderate level of pedestrian noise including occasional hammering and backup alarms.

     

    Project Site

    Continuation of in wall utility installation

     

    Various hand tools, aerial device

    Moderate level of pedestrian noise including occasional hammering and backup alarms.

     

    Contractor Parking Area

    Continued parking for contractor and sub-contractors; storage of equipment

     

    Contractor vehicles

    Low level of vehicle and pedestrian noise.

     

    Contractor Offices

    Continued office use

    Office Equipment and Furniture

    Low level of pedestrian noise

     

    Current and Upcoming Anticipated Shutdowns/ Closures

    The following shutdown(s)/ closures are anticipated as indicated below. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact Dexter Galang with any specific questions or concerns at dexter.galang@ucr.edu.

     

    Description

    Location

    Duration & Date

    Impacted Buildings/ Facilities

    North Exterior Wall Panel Crane

    Pick

    Linden Entrance to Facilities Services and Fleet Services (see Map A below)

    November 3-

    November 9

    The crane will be located at Linden Entrance to Facilities Services and Fleet Services.  Temporary access to and from the Corp Yard will be from the entrance off of Watkins Avenue.  The Crane will be offloading wall panels from trucks that will be occupying one lane of Linden Street.  Flag people will be onsite to control traffic.

     

    West Exterior Wall Panel Crane

    Pick

    Dundee- Glasgow Access Road (see Map B below)

    November 7- 11

    The crane will be located within the construction fence line and will be offloading wall panels from trucks that will be occupying one lane of the Dundee- Glasgow Access Road.  Flag people will be onsite to control traffic.

     

  • 950578- STUDENT HEALTH & COUNSELING CENTER CONSTRUCTION ADVISORY #31

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Project Site

    Continuation of Metal Stud Wall Framing

     

    Various hand and power tools, aerial device

    Moderate level of pedestrian noise including occasional High level of noise from hammering, sawing and backup alarms.

     

    Project Site

    Continuation of HVAC equipment installation

     

    Various hand tools, aerial device

    Moderate level of pedestrian noise including occasional hammering and backup alarms.

     

    Project Site

    Continuation of in wall utility installation

     

    Various hand tools, aerial device

    Moderate level of pedestrian noise including occasional hammering and backup alarms.

     

    Contractor Parking Area

    Continued parking for contractor and sub-contractors; storage of equipment

     

    Contractor vehicles

    Low level of vehicle and pedestrian noise.

     

    Contractor Offices

    Continued office use

    Office Equipment and Furniture

    Low level of pedestrian noise

     

     

     

    Week of October 24, 2022

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Project Site

    Continuation of Metal Stud Wall Framing

     

    Various hand and power tools, aerial device

    Moderate level of pedestrian noise including occasional hammering, sawing and backup alarms.

     

    Project Site

    Continuation of HVAC equipment installation

     

    Various hand tools, aerial device

    Moderate level of pedestrian noise including occasional hammering and backup alarms.

     

    Project Site

    Continuation of in wall utility installation

     

    Various hand tools, aerial device

    Moderate level of pedestrian noise including occasional hammering and backup alarms.

     

    Contractor Parking Area

    Continued parking for contractor and sub-contractors; storage of equipment

     

    Contractor vehicles

    Low level of vehicle and pedestrian noise.

     

    Contractor Offices

    Continued office use

    Office Equipment and Furniture

    Low level of pedestrian noise

     

    Upcoming Anticipated Shutdowns/ Closures

    The following shutdown(s)/ closures are anticipated in the weeks to come.  Specific locations of equipment and dates are approximations and may change due to UCR review comments and unforeseen schedule delays. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact Dexter Galang with any specific questions or concerns at dexter.galang@ucr.edu.

     

    Description

    Location

    Proposed

    Duration & Date

    Potential Impacted Buildings/ Facilities

    North Exterior Wall Panel Crane

    Pick

    Linden Entrance to Facilities Services and Fleet Services (see Map A below)

    October 31-

    November 4

    The crane will be located at Linden Entrance to Facilities Services and Fleet Services.  Temporary access to and from the Facilities and Fleet Yards will be from the west gate in Lot 23.  The Crane will be offloading wall panels from trucks that will be occupying one lane of Linden Street.  Flag people will be onsite to control traffic.

     

    West Exterior Wall Panel Crane

    Pick

    Dundee- Glasgow Access Road (see Map B below)

    November 7- 11

    The crane will be located within the construction fence line and will be offloading wall panels from trucks that will be occupying one lane of the Dundee- Glasgow Access Road.  Flag people will be onsite to control traffic.

     

  • 950578- STUDENT HEALTH & COUNSELING CENTER CONSTRUCTION ADVISORY #30

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Project Site

    Continuation of Metal Stud Wall Framing

     

    Various hand and power tools, aerial device

    Moderate level of pedestrian noise including occasional hammering, sawing and backup alarms.

     

    Project Site

    HVAC equipment installation

     

    Various hand tools, aerial device

    Moderate level of pedestrian noise including occasional hammering and backup alarms.

     

    Project Site

    Continuation of site drainage installation & storm drain tie in.

     

    Mini excavator, various hand tools

     

    Moderate level of vehicle and pedestrian noise .

    Contractor Parking Area

    Continued parking for contractor and sub-contractors; storage of equipment

     

    Contractor vehicles

    Low level of vehicle and pedestrian noise.

     

    Contractor Offices

    Continued office use

    Office Equipment and Furniture

    Low level of pedestrian noise

     

     

     

    Week of October 17, 2022

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Project Site

    Continuation of Metal Stud Wall Framing

     

    Various hand and power tools, aerial device

    Moderate level of pedestrian noise including occasional hammering, sawing and backup alarms.

     

    Project Site

    Continuation of HVAC equipment installation

     

    Various hand tools, aerial device

    Moderate level of pedestrian noise including occasional hammering and backup alarms.

     

    Project Site

    Continuation of site drainage installation & storm drain tie in.

     

    Mini excavator, various hand tools

     

    Moderate level of vehicle and pedestrian noise .

    Contractor Parking Area

    Continued parking for contractor and sub-contractors; storage of equipment

     

    Contractor vehicles

    Low level of vehicle and pedestrian noise.

     

    Contractor Offices

    Continued office use

    Office Equipment and Furniture

    Low level of pedestrian noise

     

    Upcoming Anticipated Shutdowns/ Closures

    The following shutdown(s)/ closures are anticipated in the weeks to come.  Specific locations of equipment and dates are approximations and may change due to UCR review comments and unforeseen schedule delays. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact Dexter Galang with any specific questions or concerns at dexter.galang@ucr.edu.

     

    Description

    Location

    Proposed

    Duration & Date

    Potential Impacted Buildings/ Facilities

    North Exterior Wall Panel Crane

    Pick

    Linden Entrance to Facilities Services and Fleet Services (see Map A below)

    October 31-

    November 4

    The crane will be located at Linden Entrance to Facilities Services and Fleet Services.  Temporary access to and from the Facilities and Fleet Yards will be from the west gate in Lot 23.  The Crane will be offloading wall panels from trucks that will be occupying one lane of Linden Street.  Flag people will be onsite to control traffic.

     

    West Exterior Wall Panel Crane

    Pick

    Dundee- Glasgow Access Road (see Map B below)

    November 7- 11

    The crane will be located within the construction fence line and will be offloading wall panels from trucks that will be occupying one lane of the Dundee- Glasgow Access Road.  Flag people will be onsite to control traffic.

     

  • 950578- STUDENT HEALTH & COUNSELING CENTER CONSTRUCTION ADVISORY #29

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Project Site

    Level 1 Concrete Curing

     

    Curing blankets and various hand tools

    Low level of vehicle engine and pedestrian noise.

     

    Project Site

    HVAC hanger installation

     

    Various hand tools

    Moderate level of pedestrian noise including occasional hammering.

     

    Project Site

    Site drainage installation & storm drain tie in.

     

    Mini excavator, various hand tools

     

    Moderate level of vehicle and pedestrian noise .

    Project Site

    Wall framing

     

    Various hand tools

     

    Moderate level of pedestrian noise.

     

    Contractor Parking Area

    Continued parking for contractor and sub-contractors; storage of equipment

     

    Contractor vehicles

    Low level of vehicle and pedestrian noise.

     

    Contractor Offices

    Continued office use

    Office Equipment and Furniture

    Low level of pedestrian noise

     

     

     

    Week of October 3, 2022

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Project Site

    Continuation of HVAC hanger installation

     

    Various hand tools

    Moderate level of pedestrian noise including occasional hammering.

     

    Project Site

    Continuation of site drainage installation & storm drain tie in.

     

    Mini excavator, various hand tools

     

    Moderate level of vehicle and pedestrian noise .

    Project Site

    Continuation of wall framing

     

    Various hand tools

     

    Moderate level of pedestrian noise.

     

    Contractor Parking Area

    Continued parking for contractor and sub-contractors; storage of equipment

     

    Contractor vehicles

    Low level of vehicle and pedestrian noise.

     

    Contractor Offices

    Continued office use

    Office Equipment and Furniture

    Low level of pedestrian noise

     

    Upcoming Anticipated Shutdowns/ Closures

    The following shutdown(s)/ closures are anticipated in the weeks to come.  Specific locations of equipment and dates are approximations and may change due to UCR review comments and unforeseen schedule delays. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact Dexter Galang with any specific questions or concerns at dexter.galang@ucr.edu.

     

    Description

    Location

    Proposed

    Duration & Date

    Potential Impacted Buildings/ Facilities

    North Exterior Wall Panel Crane

    Pick

    Linden Entrance to Facilities Services and Fleet Services (see Map A below)

    October 17-21

    The crane will be located at Linden Entrance to Facilities Services and Fleet Services.  Temporary access to and from the Facilities and Fleet Yards will be from the west gate in Lot 23.  The Crane will be offloading wall panels from trucks that will be occupying one lane of Linden Street.  Flag people will be onsite to control traffic.

     

    West Exterior Wall Panel Crane

    Pick

    Dundee- Glasgow Access Road (see Map B below)

    October 24-28

    The crane will be located within the construction fence line and will be offloading wall panels from trucks that will be occupying one lane of the Dundee- Glasgow Access Road.  Flag people will be onsite to control traffic.

     

  • 950578- STUDENT HEALTH & COUNSELING CENTER CONSTRUCTION ADVISORY #28

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Project Site

    Gravel, sand base and vapor barrier for slab on grade

     

    Delivery trucks, mini excavator, various hand tools

    Moderate level of vehicle engine and pedestrian noise.

     

    Project Site

    Additional Sewer and Storm Drain tie in

     

    Mini excavator, various hand tools

    Moderate level of vehicle engine and pedestrian noise.

     

    Project Site

    Concrete Pour at northwest corner

     

    Concrete delivery trucks, pumper truck, mini excavator, various hand tools

     

    5:00 am start.  Contractor will mitigate early hours noise and light. Moderate level of vehicle engine and pedestrian noise.

     

    Contractor Parking Area

    Continued parking for contractor and sub-contractors; storage of equipment

     

    Contractor vehicles

    Low level of vehicle and pedestrian noise.

     

    Contractor Offices

    Continued office use

    Office Equipment and Furniture

    Low level of pedestrian noise

     

     

     

    Week of September 26, 2022

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Project Site

    First Floor Slab on Grade Concrete Pour

     

    Pumper Truck, Concrete Delivery Trucks, various hand tools.

    5:00 am start.  Contractor will mitigate early hours noise and light. Moderate level of vehicle engine and pedestrian noise.

     

    Contractor Parking Area

    Continued parking for contractor and sub-contractors; storage of equipment

     

    Contractor vehicles

    Low level of vehicle and pedestrian noise.

     

    Contractor Offices

    Continued office use

    Office Equipment and Furniture

    Low level of pedestrian noise

     

    Upcoming Anticipated Shutdowns/ Closures

    The following shutdown(s)/ closures are anticipated in the weeks to come.  Specific dates are approximations and may change due to unforeseen schedule delays. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact Dexter Galang with any specific questions or concerns at dexter.galang@ucr.edu.

     

    Description

    Location

    Proposed

    Duration & Date

    Potential Impacted Buildings/ Facilities

    North Exterior Wall Panel Crane

    Pick

    Linden Entrance to Facilities Services and Fleet Services (see Map A below)

    October 17-21

    The crane will be located at Linden Entrance to Facilities Services and Fleet Services.  Temporary access to and from the Facilities and Fleet Yards will be from the west gate in Lot 23.  The Crane will be offloading wall panels from trucks that will be occupying one lane of Linden Street.  Flag people will be onsite to control traffic.

     

    West Exterior Wall Panel Crane

    Pick

    Dundee- Glasgow Access Road (see Map B below)

    October 24-28

    The crane will be located within the construction fence line and will be offloading wall panels from trucks that will be occupying one lane of the Dundee- Glasgow Access Road.  Flag people will be onsite to control traffic.

     

  • 950578- STUDENT HEALTH & COUNSELING CENTER CONSTRUCTION ADVISORY #27

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Project Site

    Shallow ground utility layout

     

    Mini Excavator, various hand tools

    Moderate level of vehicle engine and pedestrian noise.

     

    Project Site

    Gravel and sand base for slab on grade

     

    Delivery trucks, mini excavator, various hand tools

    Moderate level of vehicle engine and pedestrian noise.

     

    Project Site

    Additional Sewer and Storm Drain tie in

     

    Mini excavator, various hand tools

    Moderate level of vehicle engine and pedestrian noise.

     

    Contractor Parking Area

    Continued parking for contractor and sub-contractors; storage of equipment

     

    Contractor vehicles

    Low level of vehicle and pedestrian noise.

     

    Contractor Offices

    Continued office use

    Office Equipment and Furniture

    Low level of pedestrian noise

     

    No work outside of fence line is anticipated at this time during student move-in weekend on September 17 & 18.

     

     

    Week of September 19, 2022

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Project Site

    Vapor Barrier Installation for slab on grade

     

    Delivery trucks, fork lift, various hand tools

    Moderate level of vehicle engine and pedestrian noise.

     

    Contractor Parking Area

    Continued parking for contractor and sub-contractors; storage of equipment

     

    Contractor vehicles

    Low level of vehicle and pedestrian noise.

     

    Contractor Offices

    Continued office use

    Office Equipment and Furniture

    Low level of pedestrian noise

     

    Upcoming Anticipated Shutdowns/ Closures

    The following shutdown(s)/ closures are anticipated in the weeks to come.  Specific dates are approximations and may change due to unforeseen schedule delays. Updates to this schedule will be released weekly in the Project Construction Advisories until the work is complete.  Please contact Dexter Galang with any specific questions or concerns at dexter.galang@ucr.edu.

     

    Description

    Location

    Proposed

    Duration & Date

    Potential Impacted Buildings/ Facilities

    North Exterior Wall Panel Crane

    Pick

    Linden Entrance to Facilities Services and Fleet Services (see Map A below)

    October 17-21

    The crane will be located at Linden Entrance to Facilities Services and Fleet Services.  Temporary access to and from the Facilities and Fleet Yards will be from the west gate in Lot 23.  The Crane will be offloading wall panels from trucks that will be occupying one lane of Linden Street.  Flag people will be onsite to control traffic.

     

    West Exterior Wall Panel Crane

    Pick

    Dundee- Glasgow Access Road (see Map B below)

    October 24-28

    The crane will be located within the construction fence line and will be offloading wall panels from trucks that will be occupying one lane of the Dundee- Glasgow Access Road.  Flag people will be onsite to control traffic.

     

  • 950578- STUDENT HEALTH & COUNSELING CENTER CONSTRUCTION ADVISORY #26

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Project Site

    Underground Electrical and Plumbing

     

    Mini Excavator, various hand tools

    Moderate level of vehicle engine and pedestrian noise.

     

    Project Site

    First Level Slab on Grade Concrete Pour

     

    Concrete Mixer Truck, Concrete Pumper, various hand tools

    Moderate level of vehicle engine and pedestrian noise.

     

    Project Site

    Utility Yard Footing concrete pour

    Concrete Mixer Truck, Concrete Pumper, various hand tools

    Moderate level of vehicle engine and pedestrian noise.

     

    Contractor Parking Area

    Continued parking for contractor and sub-contractors; storage of equipment

     

    Contractor vehicles

    Low level of vehicle and pedestrian noise.

     

    Contractor Offices

    Continued office use

    Office Equipment and Furniture

    Low level of pedestrian noise

     

     

     

    Week of September 5, 2022

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Project Site

    Second Level Slab Concrete Pour

     

    Concrete Mixer Truck, Concrete Pumper, various hand tools

     

    Moderate level of vehicle engine and pedestrian noise.

     

    Contractor Parking Area

    Continued parking for contractor and sub-contractors; storage of equipment

     

    Contractor vehicles

    Low level of vehicle and pedestrian noise.

     

    Contractor Offices

    Continued office use

    Office Equipment and Furniture

    Low level of pedestrian noise

     

    No work is anticipated at this time during student move-in weekend on September 17 & 18.

     

    Upcoming Anticipated Utility Shutdowns

    The following utility shutdown(s) are anticipated in the weeks to come.  Specific dates are approximations and logistical details are pending approval. Please contact Dexter Galang with any specific questions or concerns at dexter.galang@ucr.edu.

     

    Description

    Location

    Proposed

    Duration & Date

    Potential Impacted Buildings/ Facilities

    None anticipated at this time

    -

    -

    -

  • 950578- STUDENT HEALTH & COUNSELING CENTER CONSTRUCTION ADVISORY #25

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Project Site

    Continuation of Structural steel erection- plumbing squaring, bolting and welding

    Truck crane, Various hand tools

    Moderate level of, vehicle engine noise, occasional hammering and pedestrian noise.

     

    Project Site

    Utility Yard CMU Wall Construction

     

    Mini Excavator, various hand tools

    Moderate level of vehicle engine and pedestrian noise.

     

    Project Site

    Various concrete

     

    Concrete truck and Pumper, various hand tools

    Moderate level of vehicle engine and pedestrian noise.

     

    Landscape Area between Dundee and Glasgow and Dundee Glasgow Access Road

     

    Landscape Restoration

     

    Various hand tools

    Periodic limited access on road with traffic controlled by flag people.

    Contractor Parking Area

    Continued parking for contractor and sub-contractors; storage of equipment

     

    Contractor vehicles

    Low level of vehicle and pedestrian noise.

     

    Contractor Offices

    Continued office use

    Office Equipment and Furniture

    Low level of pedestrian noise

     

     

    Week of 8-29-2022

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Landscape Area between Dundee and Glasgow and Dundee Glasgow Access Road

    Continuation of Landscape Restoration

    Mini Excavator, various hand tools

    Periodic limited access on road with traffic controlled by flag people.

    Project Site

    Utility Yard Footing concrete pour

    Mini Excavator, various hand tools

    Moderate level of vehicle engine and pedestrian noise.

     

    Contractor Parking Area

    Continued parking for contractor and sub-contractors; storage of equipment

     

    Contractor vehicles

    Low level of vehicle and pedestrian noise.

     

    Contractor Offices

    Continued office use

    Office Equipment and Furniture

    Low level of pedestrian noise

     

    Upcoming Anticipated Utility Shutdowns

    The following utility shutdown(s) are anticipated in the weeks to come.  Specific dates are approximations and logistical details are pending approval. Please contact Dexter Galang with any specific questions or concerns at dexter.galang@ucr.edu.

     

    Description

    Location

    Proposed

    Duration & Date

    Potential Impacted Buildings/ Facilities

    None anticipated at this time

    -

    -

    -

     

  • 950578- STUDENT HEALTH & COUNSELING CENTER CONSTRUCTION ADVISORY #24

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Project Site

    Continuation of Structural steel deliveries

    Delivery semi-trucks, Rough terrain fork lift, Various hand tools

    Moderate level of backup alarms, vehicle engine and pedestrian noise. Increased traffic along Linden.

     

    Project Site

    Continuation of Structural steel erection

    Truck crane, Various hand tools

    Moderate level of, vehicle engine noise, occasional hammering and pedestrian noise.

     

    Project Site

    Utility Yard Footing- setting rebar

     

    Mini Excavator, various hand tools

    Moderate level of vehicle engine and pedestrian noise.

     

    Contractor Parking Area

    Continued parking for contractor and sub-contractors; storage of equipment

     

    Contractor vehicles

    Low level of vehicle and pedestrian noise.

     

    Contractor Offices

    Continued office use

    Office Equipment and Furniture

    Low level of pedestrian noise

     

     

    Week of 8-15-2022

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Project Site

    Continuation of Structural steel deliveries

    Delivery semi-trucks, Rough terrain fork lift, Various hand tools

    Moderate level of backup alarms, vehicle engine and pedestrian noise. Increased traffic along Linden.

     

    Project Site

    Continuation of Structural steel erection

    Truck crane, Various hand tools

    Moderate level of, vehicle engine noise, occasional hammering and pedestrian noise.

     

    Landscape Area between Dundee and Glasgow and Dundee Glasgow Access Road

     

    Landscape Restoration

     

    Mini Excavator, various hand tools

    Periodic limited access on road with traffic controlled by flag people.

    Project Site

    Utility Yard Footing concrete pour

     

    Mini Excavator, various hand tools

    Moderate level of vehicle engine and pedestrian noise.

     

    Project Site

    Utility Yard concrete block wall construction

     

    Fork lift, various hand tools

    Moderate level of vehicle engine and pedestrian noise.

     

    Contractor Parking Area

    Continued parking for contractor and sub-contractors; storage of equipment

     

    Contractor vehicles

    Low level of vehicle and pedestrian noise.

     

    Contractor Offices

    Continued office use

    Office Equipment and Furniture

    Low level of pedestrian noise

    Upcoming Anticipated Utility Shutdowns

    The following utility shutdown(s) are anticipated in the weeks to come.  Specific dates are approximations and logistical details are pending approval. Please contact Dexter Galang with any specific questions or concerns at dexter.galang@ucr.edu.

     

    Description

    Location

    Proposed

    Duration & Date

    Potential Impacted Buildings/ Facilities

    None anticipated at this time

    -

    -

    -

     

  • 950578- STUDENT HEALTH & COUNSELING CENTER CONSTRUCTION ADVISORY #23

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Project Site

    Continuation of Structural steel deliveries

    Delivery semi-trucks, Rough terrain fork lift, Various hand tools

    Moderate level of backup alarms, vehicle engine and pedestrian noise. Increased traffic along Linden.

     

    Project Site

    Continuation of Structural steel erection

    Truck crane, Various hand tools

    Moderate level of, vehicle engine noise, occasional hammering and pedestrian noise.

     

    Landscape Area between Dundee and Glasgow and Dundee Glasgow Access Road

     

    Sewer Connection

     

    Mini Excavator, various hand tools

    Periodic limited access on road with traffic controlled by flag people. Temporary walkways will be installed using metal plates.

    Project Site

    Utility Yard Footing excavation

     

    Mini Excavator, various hand tools

    Moderate level of vehicle engine and pedestrian noise.

     

    Contractor Parking Area

    Continued parking for contractor and sub-contractors; storage of equipment

    Contractor vehicles

    Low level of vehicle and pedestrian noise.

     

    Contractor Offices

    Continued office use

    Office Equipment and Furniture

    Low level of pedestrian noise

     

     

     

    Week of 8-1-2022

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Project Site

    Continuation of Structural steel deliveries

    Delivery semi-trucks, Rough terrain fork lift, Various hand tools

    Moderate level of backup alarms, vehicle engine and pedestrian noise. Increased traffic along Linden.

     

    Project Site

    Continuation of Structural steel erection

    Truck crane, Various hand tools

    Moderate level of, vehicle engine noise, occasional hammering and pedestrian noise.

     

    Landscape Area between Dundee and Glasgow and Dundee Glasgow Access Road

     

    Sewer Connection

     

    Mini Excavator, various hand tools

    Periodic limited access on road with traffic controlled by flag people. Temporary walkways will be installed using metal plates.

    Project Site

    Utility Yard Footing excavation

     

    Mini Excavator, various hand tools

    Moderate level of vehicle engine and pedestrian noise.

     

    Contractor Parking Area

    Continued parking for contractor and sub-contractors; storage of equipment

     

    Contractor vehicles

    Low level of vehicle and pedestrian noise.

     

    Contractor Offices

    Continued office use

    Office Equipment and Furniture

    Low level of pedestrian noise

     

    Upcoming Anticipated Utility Shutdowns

    The following utility shutdown(s) are anticipated in the weeks to come.  Specific dates are approximations and logistical details are pending approval. Please contact Dexter Galang with any specific questions or concerns at dexter.galang@ucr.edu.

     

    Description

    Location

    Proposed

    Duration & Date

    Potential Impacted Buildings/ Facilities

    None anticipated at this time

    -

    -

    -

  • 950578- STUDENT HEALTH & COUNSELING CENTER CONSTRUCTION ADVISORY #22

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Project Site

    Retaining wall waterproofing

    Various hand tools

    Low level of pedestrian noise.

     

    Project Site

    Structural steel deliveries

    Delivery semi-trucks, Rough terrain fork lift, Various hand tools

    Moderate level of backup alarms, vehicle engine and pedestrian noise. Increased traffic along Linden.

     

    Project Site

    Structural steel erection

    Truck crane, Various hand tools

    Moderate level of, vehicle engine noise, occasional hammering and pedestrian noise.

     

    Project Site

    Telecom conduit installation

    Mini Excavator, various hand tools

    Moderate level of backup alarms, vehicle engine and pedestrian noise.

     

    Landscape Area between Dundee and Glasgow and Dundee Glasgow Access Road

     

    Sewer Connection

     

    Mini Excavator, various hand tools

    Occasion high levels of jackhammering noise with moderate level of vehicle and pedestrian noise.  Periodic limited access on road with traffic controlled by flag people. Temporary walkways will be installed using metal plates.  Sewer connection work will continue until the end of July with no noticeable  interruption to service in surrounding areas.

    Strong odors may be present at this time

     

    Project Site

    Continue underground utility installation

     

    Mini Excavator, various hand tools

    Moderate level of vehicle engine and pedestrian noise.

     

    Contractor Parking Area

    Continued parking for contractor and sub-contractors; storage of equipment

    Contractor vehicles

    Low level of vehicle and pedestrian noise.

     

    Contractor Offices

    Continued office use

    Office Equipment and Furniture

    Low level of pedestrian noise

     

     

     

    Week of 8-1-2022

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Project Site

    Continued Structural steel deliveries

    Delivery semi-trucks, Rough terrain fork lift, Various hand tools

    Moderate level of backup alarms, vehicle engine and pedestrian noise. Increased traffic along Linden.

     

    Project Site

    Continued Structural steel erection

    Truck crane, Various hand tools

    Moderate level of, vehicle engine noise, occasional hammering and pedestrian noise.

     

    Landscape Area between Dundee and Glasgow and Dundee Glasgow Access Road

     

    Sewer Connection

     

    Mini Excavator, various hand tools

    Occasion high levels of jackhammering noise with moderate level of vehicle and pedestrian noise.  Periodic limited access on road with traffic controlled by flag people. Temporary walkways will be installed using metal plates.  Sewer connection work will continue until the end of July with no noticeable  interruption to service in surrounding areas.

    Strong odors may be present at this time

     

    Project Site

    Continue underground utility installation

     

    Mini Excavator, various hand tools

    Moderate level of vehicle engine and pedestrian noise.

     

    Contractor Parking Area

    Continued parking for contractor and sub-contractors; storage of equipment

     

    Contractor vehicles

    Low level of vehicle and pedestrian noise.

     

    Contractor Offices

    Continued office use

    Office Equipment and Furniture

    Low level of pedestrian noise

     

    Upcoming Anticipated Utility Shutdowns

    The following utility shutdown(s) are anticipated in the weeks to come.  Specific dates are approximations and logistical details are pending approval. Please contact Dexter Galang with any specific questions or concerns at dexter.galang@ucr.edu.

     

    Description

    Location

    Proposed

    Duration & Date

    Potential Impacted Buildings/ Facilities

    None anticipated at this time

    -

    -

    -

  • 950578- STUDENT HEALTH & COUNSELING CENTER CONSTRUCTION ADVISORY #21

    Current Weeks

    Construction Activities

     

    Please note that summer work hours will begin at 6:00 am

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Project Site

    Retaining wall waterproofing

    Various hand tools

    Low level of pedestrian noise.

     

    Project Site

    Structural steel deliveries

    Delivery semi-trucks, Rough terrain fork lift, Various hand tools

    Moderate level of backup alarms, vehicle engine and pedestrian noise. Increased traffic along Linden.

     

    Project Site

    Structural steel erection

    Truck crane, Rough terrain fork lift, Various hand tools

    Moderate level of backup alarms, vehicle engine and pedestrian noise.

     

    Project Site

    Telecom conduit installation

    Mini Excavator, various hand tools

    Moderate level of backup alarms, vehicle engine and pedestrian noise.

     

    Landscape Area between Dundee and Glasgow

     

    Sewer Connection

     

    Mini Excavator, various hand tools

    Moderate level of vehicle and pedestrian noise.  Periodic limited access on road with traffic controlled by flag people. Temporary walkways will be installed using metal plates.  Sewer connection work will continue until the end of July with no noticeable  interruption to service in surrounding areas.

     

    Project Site

    Continue underground utility installation

     

    Mini Excavator, various hand tools

    Moderate level of vehicle engine and pedestrian noise.

     

    Contractor Parking Area

    Continued parking for contractor and sub-contractors; storage of equipment

    Contractor vehicles

    Low level of vehicle and pedestrian noise.

     

    Contractor Offices

    Continued office use

    Office Equipment and Furniture

    Low level of pedestrian noise

     

     

     

    Week of 7-25-2022

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Project Site

    Continuation of structural steel deliveries

    Delivery semi-trucks, Rough terrain fork lift, Various hand tools

    Moderate level of backup alarms, vehicle engine and pedestrian noise. Increased traffic along Linden.

     

    Project Site

    Continuation of structural steel erection

    Truck crane, Rough terrain fork lift, Various hand tools

    Moderate level of backup alarms, vehicle engine and pedestrian noise.

     

    Landscape Area between Dundee and Glasgow

     

    Continuation of sewer connection

     

    Mini Excavator, various hand tools

    Moderate level of vehicle and pedestrian noise.  Periodic limited access on road with traffic controlled by flag people. Temporary walkways will be installed using metal plates.  Sewer connection work will continue until the end of July with no noticeable  interruption to service in surrounding areas.

     

    Contractor Parking Area

    Continued parking for contractor and sub-contractors; storage of equipment

    Contractor vehicles

    Low level of vehicle and pedestrian noise.

     

    Contractor Offices

    Continued office use

    Office Equipment and Furniture

    Low level of pedestrian noise

     

    Upcoming Anticipated Utility Shutdowns

    The following utility shutdown(s) are anticipated in the weeks to come.  Specific dates are approximations and logistical details are pending approval. Please contact Dexter Galang with any specific questions or concerns at dexter.galang@ucr.edu.

     

    Description

    Location

    Proposed

    Duration & Date

    Potential Impacted Buildings/ Facilities

    None anticipated at this time

    -

    -

    -

  • 950578- STUDENT HEALTH & COUNSELING CENTER CONSTRUCTION ADVISORY #20

    Current Weeks

    Construction Activities

     

    Please note that summer work hours will begin at 6:00 am

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Project Site

    Concrete wall pour

    Concrete Pumper and Mixer Trucks, Various hand tools

    Moderate level of vehicle engine, backup warning sounds and pedestrian noise.

     

    Landscape Area between Dundee and Glasgow

     

    Sewer Connection

     

    Mini Excavator, various hand tools

    Moderate level of vehicle and pedestrian noise.  Periodic limited access on road with traffic controlled by flag people. Temporary walkways will be installed using metal plates.  Sewer connection work will continue until the end of July with no noticeable  interruption to service in surrounding areas.

     

    Project Site

    Continue underground utility installation

     

    Mini Excavator, various hand tools

    Moderate level of vehicle engine and pedestrian noise.

     

    Contractor Parking Area

    Continued parking for contractor and sub-contractors; storage of equipment

    Contractor vehicles

    Low level of vehicle and pedestrian noise.

     

    Contractor Offices

    Office Use

    Office Equipment and Furniture

    Low level of pedestrian noise

     

     

     

    Week of 7-18-2022

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Project Site

    Steel Erection

    Truck-mounted telescopic Crane, Various Hand Tools

    Moderate level of vehicle engine, backup warning sounds and pedestrian noise.

     

    Landscape Area between Dundee and Glasgow

     

    Sewer Connection

     

    Mini Excavator, various hand tools

    Moderate level of vehicle and pedestrian noise.  Periodic limited access on road with traffic controlled by flag people. Temporary walkways will be installed using metal plates.  Sewer connection work will continue until the end of July with no noticeable  interruption to service in surrounding areas.

     

    Contractor Parking Area

    Continued parking for contractor and sub-contractors; storage of equipment

    Contractor vehicles

    Low level of vehicle and pedestrian noise.

     

    Contractor Offices

    Office Use

    Office Equipment and Furniture

    Low level of pedestrian noise

     

    Upcoming Anticipated Utility Shutdowns

    The following utility shutdown(s) are anticipated in the weeks to come.  Specific dates are approximations and logistical details are pending approval. Please contact Dexter Galang with any specific questions or concerns at dexter.galang@ucr.edu.

     

    Description

    Location

    Proposed

    Duration & Date

    Potential Impacted Buildings/ Facilities

    None anticipated at this time

    -

    -

    -

  • 950578- STUDENT HEALTH & COUNSELING CENTER CONSTRUCTION ADVISORY #19

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Project Site

    Continue installation of concrete wall forms

    Various hand tools, rough terrain fork lift

    Moderate level of vehicle engine, backup warning sounds and pedestrian noise.

     

    Landscape Area between Dundee and Glasgow

     

    Installation of Fencing for sewer connection work

    Various hand tools, Contractor Trucks

    Moderate level of vehicle and pedestrian noise.  Periodic limited access on road with traffic controlled by flag people. Temporary walkways will be installed using metal plates.  Fencing will remain until the end on July.

     

    Landscape Area between Dundee and Glasgow

     

    Sewer Connection

     

    Mini Excavator, various hand tools

    Moderate level of vehicle and pedestrian noise.  Periodic limited access on road with traffic controlled by flag people. Temporary walkways will be installed using metal plates.  Sewer connection work will continue until the end of July with no noticeable  interruption to service in surrounding areas.

     

    East side of Dundee Glasgow Access Road

    Storm Drain Connection

     

    Mini Excavator, various hand tools

    Moderate level of vehicle and pedestrian noise.  Periodic limited access on road with traffic controlled by flag people.

     

    Project Site

    Continue underground utility installation

    Mini Excavator, various hand tools

    Moderate level of vehicle engine and pedestrian noise.

     

    Contractor Parking Area

    Continued parking for contractor and sub-contractors; storage of equipment

    Contractor vehicles

    Low level of vehicle and pedestrian noise.

     

    Contractor Offices

    Office Use

    Office Equipment and Furniture

    Low level of pedestrian noise

     

     

    Week of 7-11-2022

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Project Site

    Concrete wall pour

    Concrete Pumper and Mixer Trucks, Various hand tools

    Moderate level of vehicle engine, backup warning sounds and pedestrian noise.

     

    Landscape Area between Dundee and Glasgow

     

    Sewer Connection

     

    Mini Excavator, various hand tools

    Moderate level of vehicle and pedestrian noise.  Periodic limited access on road with traffic controlled by flag people. Temporary walkways will be installed using metal plates.  Sewer connection work will continue until the end of July with no noticeable  interruption to service in surrounding areas.

     

    Project Site

    Continue underground utility installation

    Mini Excavator, various hand tools

    Moderate level of vehicle engine and pedestrian noise.

     

    Contractor Parking Area

    Continued parking for contractor and sub-contractors; storage of equipment

    Contractor vehicles

    Low level of vehicle and pedestrian noise.

     

    Contractor Offices

    Office Use

    Office Equipment and Furniture

    Low level of pedestrian noise

     

    Upcoming Anticipated Utility Shutdowns

    The following utility shutdown(s) are anticipated in the weeks to come.  Specific dates are approximations and logistical details are pending approval. Please contact Dexter Galang with any specific questions or concerns at dexter.galang@ucr.edu.

     

    Description

    Location

    Proposed

    Duration & Date

    Potential Impacted Buildings/ Facilities

    None anticipated at this time

    -

    -

    -

  • 950578- STUDENT HEALTH & COUNSELING CENTER CONSTRUCTION ADVISORY #18

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Project Site

    Continue shotcrete installation

    Shotcrete Gun, Air Compressor, Concrete Pump, Concrete Mixer Truck, various hand tools

    Increased truck traffic along Linden from concrete truck deliveries.

    Continual hum of pump and air compressor during shotcrete shoots starting at 7:00 AM through the early afternoon.

     

    Project Site

    Continue underground utility installation

    Mini Excavator, various hand tools

    Moderate level of vehicle engine and pedestrian noise.

     

    Contractor Parking Area

    Continued parking for contractor and sub-contractors; storage of equipment

    Contractor vehicles

    Low level of vehicle and pedestrian noise.

     

    Contractor Offices

    Office Use

    Office Equipment and Furniture

    Low level of pedestrian noise

     

     

    Week of 6-27-2022

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Project Site

    Continue shotcrete installation

    Shotcrete Gun, Air Compressor, Concrete Pump, Concrete Mixer Truck, various hand tools

    Increased truck traffic along Linden from concrete truck deliveries.

    Continual hum of pump and air compressor during shotcrete shoots starting at 7:00 AM through the early afternoon.

     

    Project Site

    Remove concrete wall forms

    Mini Excavator, various hand tools

    Moderate level of vehicle engine, backup warning sounds and pedestrian noise.

     

    Project Site

    Continue underground utility installation

    Mini Excavator, various hand tools

    Moderate level of vehicle engine, backup warning sounds and pedestrian noise.

     

    Contractor Parking Area

    Continued parking for contractor and sub-contractors; storage of equipment

    Contractor vehicles

    Low level of vehicle and pedestrian noise.

     

    Contractor Offices

    Office Use

    Office Equipment and Furniture

    Low level of pedestrian noise

     

    Upcoming Anticipated Utility Shutdowns

    The following utility shutdown(s) are anticipated in the weeks to come.  Specific dates are approximations and logistical details are pending approval. Please contact Dexter Galang with any specific questions or concerns at dexter.galang@ucr.edu.

     

    Description

    Location

    Proposed

    Duration & Date

    Potential Impacted Buildings/ Facilities

    None anticipated at this time

    -

    -

    -

     

    Biweekly Neighborhood Meetings are scheduled every other Mondays at 2:00 pm where construction impacts to the adjacent areas are discussed and how those issues can be addressed or mitigated.  If you would like to be added to the list of attendees, or if you would like us to include additional attendees, please respond to this email with the required contact information.

     

  • 950578- STUDENT HEALTH & COUNSELING CENTER CONSTRUCTION ADVISORY #17

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Project Site

    Concrete wall form installation

    Rough Terrain Forklift, & various hand tools

    Moderate level of sustained construction noise primarily comprised of running motors and backup alarms.

    Occasional increased slow traffic due to truck deliveries.

    Sidewalk will be open but alternate paths are encouraged.

     

    Project Site

    Concrete Wall Pour

    Concrete Pump, Concrete Mixer Truck, various hand tools

    Increased truck traffic along Linden from concrete truck deliveries.

     

     

    Project Site

    Underground utility installation

    Mini Excavator, various hand tools

    Moderate level of vehicle engine and pedestrian noise.

     

    Contractor Parking Area

    Continued parking for contractor and sub-contractors; storage of equipment

    Contractor vehicles

    Low level of vehicle and pedestrian noise.

     

    Contractor Offices

    Office Use

    Office Equipment and Furniture

    Low level of pedestrian noise

     

     

    Week of 6-27-2022

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Project Site

    Continue concrete wall form installation

    Rough Terrain Forklift, & various hand tools

    Moderate level of sustained construction noise primarily comprised of running motors and backup alarms.

    Occasional increased slow traffic due to truck deliveries.

    Sidewalk will be open but alternate paths are encouraged.

     

    Project Site

    Continue shotcrete installation

    Shotcrete Gun, Air Compressor, Concrete Pump, Concrete Mixer Truck, various hand tools

    Increased truck traffic along Linden from concrete truck deliveries.

    Continual hum of pump and air compressor during shotcrete shoots starting at 7:00 AM through the early afternoon.

     

    Project Site

    Continue underground utility installation

    Mini Excavator, various hand tools

    Moderate level of vehicle engine and pedestrian noise.

     

    Contractor Parking Area

    Continued parking for contractor and sub-contractors; storage of equipment

    Contractor vehicles

    Low level of vehicle and pedestrian noise.

     

    Contractor Offices

    Office Use

    Office Equipment and Furniture

    Low level of pedestrian noise

     

    Upcoming Anticipated Utility Shutdowns

    The following utility shutdown(s) are anticipated in the weeks to come.  Specific dates are approximations and logistical details are pending approval. Please contact Dexter Galang with any specific questions or concerns at dexter.galang@ucr.edu.

     

    Description

    Location

    Proposed

    Duration & Date

    Potential Impacted Buildings/ Facilities

    None anticipated at this time

    -

    -

    -

  • 950578- STUDENT HEALTH & COUNSELING CENTER CONSTRUCTION ADVISORY #16

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Project Site

    Concrete wall form installation

    Rough Terrain Forklift, & various hand tools

    Moderate level of sustained construction noise primarily comprised of running motors and backup alarms.

    Occasional increased slow traffic due to truck deliveries.

    Sidewalk will be open but alternate paths are encouraged.

     

    Project Site

    Shotcrete installation

    Shotcrete Gun, Air Compressor, Concrete Pump, Concrete Mixer Truck, various hand tools

    Increased truck traffic along Linden from concrete truck deliveries.

    Continual hum of pump and air compressor during shotcrete shoots starting at 7:00 AM through the early afternoon.

     

    Contractor Parking Area

    Continued parking for contractor and sub-contractors; storage of equipment

    Contractor vehicles

    Low level of vehicle and pedestrian noise.

     

    Contractor Offices

    Office Use

    Office Equipment and Furniture

    Low level of pedestrian noise

     

     

    Week of 6-13-2022

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Project Site

    Concrete wall form installation

    Rough Terrain Forklift, & various hand tools

    Moderate level of sustained construction noise primarily comprised of running motors and backup alarms.

    Occasional increased slow traffic due to truck deliveries.

    Sidewalk will be open but alternate paths are encouraged.

     

    Project Site

    Shotcrete installation

    Shotcrete Gun, Air Compressor, Concrete Pump, Concrete Mixer Truck, various hand tools

    Increased truck traffic along Linden from concrete truck deliveries.

    Continual hum of pump and air compressor during shotcrete shoots starting at 7:00 AM through the early afternoon.

     

    Dundee-Glasgow Access Road at Linden

    Utility Shutdown: Domestic water connection

    Contractor Work Trucks

    On June 17 from 7am to 5pm, one lane of Dundee- Glasgow access road will be closed.  During this time, access to and from Linden to Glasgow Dining Hall will be controlled by flag people.

     

    Pentland Hills Residence Halls,

    Building I, J, K and L

     

    Utility Shutdown: Domestic water connection

    Contractor Work Trucks

    Pentland Hills Residence Halls,

    Building I, J, K and L will be without water for 10 hours on June 17 from 7am to 5pm.

    Contractor Parking Area

    Continued parking for contractor and sub-contractors; storage of equipment

    Contractor vehicles

    Low level of vehicle and pedestrian noise.

     

    Contractor Offices

    Office Use

    Office Equipment and Furniture

    Low level of pedestrian noise

     

     

    Upcoming Anticipated Utility Shutdowns

    The following utility shutdown(s) are anticipated in the weeks to come.  Specific dates are approximations and logistical details are pending approval. Please contact Dexter Galang with any specific questions or concerns at dexter.galang@ucr.edu.

     

    Description

    Location

    Proposed

    Duration & Date

    Potential Impacted Buildings/ Facilities

    Sewer connection

    Landscape area between Dundee and Glasgow

    Date: N/A

    This work will not result in a utility shutdown as originally anticipated.  Sewer service will remain operational during construction.

     

     

  • 950578- STUDENT HEALTH & COUNSELING CENTER CONSTRUCTION ADVISORY #15

    950578- STUDENT HEALTH & COUNSELING CENTER CONSTRUCTION ADVISORY #15

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Project Site

    Continued foundation concrete forms and rebar installation

    Rough Terrain Forklift, Excavator, semi-trucks, backhoe, loader, grader, & various hand tools

    Moderate level of sustained construction noise primarily comprised of running motors and backup alarms.

    Occasional increased slow traffic due to truck deliveries.

    Sidewalk will be open but alternate paths are encouraged.

    Project Site

    Continued foundation concrete pouring

    Concrete Pumper Truck, Concrete Mixer Truck, various hand tools

    Increased truck traffic along Linden from concrete truck deliveries.

    Continual hum and clanging during pours from concrete pump and mixing trucks starting at 7:00 AM through the early afternoon.

     

    Contractor Parking Area

    Continued parking for contractor and sub-contractors; storage of equipment

    Contractor vehicles

    Low level of vehicle and pedestrian noise.

     

    Contractor Offices

    Office Use

    Office Equipment and Furniture

    Low level of pedestrian noise

     

     

    Week of 6-6-2022

    Construction Activities

     

    Location

    Activity