Breadcrumb
Student Health and Counseling Center

 

Student Health and Counseling Center

Create an identifiable and easily accessible facility that welcomes members of our diverse campus community and conveys a commitment to quality care, innovation in technical, medical and clinical services, student support and well being. This facility aligns with the missions and values of the UCR campus, the Division of Student Affairs, Student Health Services, Counseling and Psychological Services, Student Affairs Case Management, and The Well that support student retention and success through optimization of emotional and physical health, through direct service, promotion, prevention, education, student engagement, and provision of resources and referrals.


Project Scope:

  • The new SHCC will further improve health, counseling and wellness services currently provided at the Campus
  • It will offer integrated and holistic care in a welcoming and student-centered environment, with increased medical and mental health providers on staff
  • The design of the SHCC should address the students’ experience
  • In addition to providing medical and mental health services, the new facility is envisioned as a destination within the UCR Campus
  • While the current Student Health Center is relatively insular, the new SHCC should be more visible and become an integral part of the UCR Campus
  • Different programs within the SHCC will share common resources and they will be administered accordingly
  • The SHCC building space should provide opportunities for collaboration, be flexible and have room for growth
  • To best serve the significant number of commuter students. t the SHCC should be a comfortable and welcoming space that accommodates these students while waiting for appointments

Student Health & Counseling Center Construction Updates
  • 950578- STUDENT HEALTH & COUNSELING CENTER CONSTRUCTION ADVISORY #17

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Project Site

    Concrete wall form installation

    Rough Terrain Forklift, & various hand tools

    Moderate level of sustained construction noise primarily comprised of running motors and backup alarms.

    Occasional increased slow traffic due to truck deliveries.

    Sidewalk will be open but alternate paths are encouraged.

     

    Project Site

    Concrete Wall Pour

    Concrete Pump, Concrete Mixer Truck, various hand tools

    Increased truck traffic along Linden from concrete truck deliveries.

     

     

    Project Site

    Underground utility installation

    Mini Excavator, various hand tools

    Moderate level of vehicle engine and pedestrian noise.

     

    Contractor Parking Area

    Continued parking for contractor and sub-contractors; storage of equipment

    Contractor vehicles

    Low level of vehicle and pedestrian noise.

     

    Contractor Offices

    Office Use

    Office Equipment and Furniture

    Low level of pedestrian noise

     

     

    Week of 6-27-2022

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Project Site

    Continue concrete wall form installation

    Rough Terrain Forklift, & various hand tools

    Moderate level of sustained construction noise primarily comprised of running motors and backup alarms.

    Occasional increased slow traffic due to truck deliveries.

    Sidewalk will be open but alternate paths are encouraged.

     

    Project Site

    Continue shotcrete installation

    Shotcrete Gun, Air Compressor, Concrete Pump, Concrete Mixer Truck, various hand tools

    Increased truck traffic along Linden from concrete truck deliveries.

    Continual hum of pump and air compressor during shotcrete shoots starting at 7:00 AM through the early afternoon.

     

    Project Site

    Continue underground utility installation

    Mini Excavator, various hand tools

    Moderate level of vehicle engine and pedestrian noise.

     

    Contractor Parking Area

    Continued parking for contractor and sub-contractors; storage of equipment

    Contractor vehicles

    Low level of vehicle and pedestrian noise.

     

    Contractor Offices

    Office Use

    Office Equipment and Furniture

    Low level of pedestrian noise

     

    Upcoming Anticipated Utility Shutdowns

    The following utility shutdown(s) are anticipated in the weeks to come.  Specific dates are approximations and logistical details are pending approval. Please contact Dexter Galang with any specific questions or concerns at dexter.galang@ucr.edu.

     

    Description

    Location

    Proposed

    Duration & Date

    Potential Impacted Buildings/ Facilities

    None anticipated at this time

    -

    -

    -

  • 950578- STUDENT HEALTH & COUNSELING CENTER CONSTRUCTION ADVISORY #16

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Project Site

    Concrete wall form installation

    Rough Terrain Forklift, & various hand tools

    Moderate level of sustained construction noise primarily comprised of running motors and backup alarms.

    Occasional increased slow traffic due to truck deliveries.

    Sidewalk will be open but alternate paths are encouraged.

     

    Project Site

    Shotcrete installation

    Shotcrete Gun, Air Compressor, Concrete Pump, Concrete Mixer Truck, various hand tools

    Increased truck traffic along Linden from concrete truck deliveries.

    Continual hum of pump and air compressor during shotcrete shoots starting at 7:00 AM through the early afternoon.

     

    Contractor Parking Area

    Continued parking for contractor and sub-contractors; storage of equipment

    Contractor vehicles

    Low level of vehicle and pedestrian noise.

     

    Contractor Offices

    Office Use

    Office Equipment and Furniture

    Low level of pedestrian noise

     

     

    Week of 6-13-2022

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Project Site

    Concrete wall form installation

    Rough Terrain Forklift, & various hand tools

    Moderate level of sustained construction noise primarily comprised of running motors and backup alarms.

    Occasional increased slow traffic due to truck deliveries.

    Sidewalk will be open but alternate paths are encouraged.

     

    Project Site

    Shotcrete installation

    Shotcrete Gun, Air Compressor, Concrete Pump, Concrete Mixer Truck, various hand tools

    Increased truck traffic along Linden from concrete truck deliveries.

    Continual hum of pump and air compressor during shotcrete shoots starting at 7:00 AM through the early afternoon.

     

    Dundee-Glasgow Access Road at Linden

    Utility Shutdown: Domestic water connection

    Contractor Work Trucks

    On June 17 from 7am to 5pm, one lane of Dundee- Glasgow access road will be closed.  During this time, access to and from Linden to Glasgow Dining Hall will be controlled by flag people.

     

    Pentland Hills Residence Halls,

    Building I, J, K and L

     

    Utility Shutdown: Domestic water connection

    Contractor Work Trucks

    Pentland Hills Residence Halls,

    Building I, J, K and L will be without water for 10 hours on June 17 from 7am to 5pm.

    Contractor Parking Area

    Continued parking for contractor and sub-contractors; storage of equipment

    Contractor vehicles

    Low level of vehicle and pedestrian noise.

     

    Contractor Offices

    Office Use

    Office Equipment and Furniture

    Low level of pedestrian noise

     

     

    Upcoming Anticipated Utility Shutdowns

    The following utility shutdown(s) are anticipated in the weeks to come.  Specific dates are approximations and logistical details are pending approval. Please contact Dexter Galang with any specific questions or concerns at dexter.galang@ucr.edu.

     

    Description

    Location

    Proposed

    Duration & Date

    Potential Impacted Buildings/ Facilities

    Sewer connection

    Landscape area between Dundee and Glasgow

    Date: N/A

    This work will not result in a utility shutdown as originally anticipated.  Sewer service will remain operational during construction.

     

     

  • 950578- STUDENT HEALTH & COUNSELING CENTER CONSTRUCTION ADVISORY #15

    950578- STUDENT HEALTH & COUNSELING CENTER CONSTRUCTION ADVISORY #15

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Project Site

    Continued foundation concrete forms and rebar installation

    Rough Terrain Forklift, Excavator, semi-trucks, backhoe, loader, grader, & various hand tools

    Moderate level of sustained construction noise primarily comprised of running motors and backup alarms.

    Occasional increased slow traffic due to truck deliveries.

    Sidewalk will be open but alternate paths are encouraged.

    Project Site

    Continued foundation concrete pouring

    Concrete Pumper Truck, Concrete Mixer Truck, various hand tools

    Increased truck traffic along Linden from concrete truck deliveries.

    Continual hum and clanging during pours from concrete pump and mixing trucks starting at 7:00 AM through the early afternoon.

     

    Contractor Parking Area

    Continued parking for contractor and sub-contractors; storage of equipment

    Contractor vehicles

    Low level of vehicle and pedestrian noise.

     

    Contractor Offices

    Office Use

    Office Equipment and Furniture

    Low level of pedestrian noise

     

     

    Week of 6-6-2022

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Project Site

    Continued foundation concrete forms and rebar installation

    Rough Terrain Forklift, Excavator, semi-trucks, backhoe, loader, grader, & various hand tools

    Moderate level of sustained construction noise primarily comprised of running motors and backup alarms.

    Occasional increased slow traffic due to truck deliveries.

    Sidewalk will be open but alternate paths are encouraged.

     

    Project Site

    Continued foundation concrete pouring

    Concrete Pumper Truck, Concrete Mixer Truck, various hand tools

    Increased truck traffic along Linden from concrete truck deliveries.

    Continual hum and clanging during pours from concrete pump and mixing trucks starting at 7:00 AM through the early afternoon.

     

    Contractor Parking Area

    Continued parking for contractor and sub-contractors; storage of equipment

    Contractor vehicles

    Low level of vehicle and pedestrian noise.

     

    Contractor Offices

    Office Use

    Office Equipment and Furniture

    Low level of pedestrian noise

     

    Upcoming Anticipated Utility Shutdowns

    The following utility shutdown(s) are anticipated in the weeks to come.  Specific dates are approximations and logistical details are pending approval. Please contact Dexter Galang with any specific questions or concerns at dexter.galang@ucr.edu.

     

    Description

    Location

    Proposed

    Duration & Date

    Potential Impacted Buildings/ Facilities

    Domestic water connection

    Pentland Hills Residence Halls,

    Building I, J, K and L

    Duration: 8 hours

    Dates: Friday, June 17

    Pentland Hills Residence Halls,

    Building I, J, K and L will likely be without water for 8 hours;

    Domestic water connection

    Dundee access road at Linden

    Dates:

    Monday, June 13 to

    Friday, June 17

    Periodically, one lane of Dundee- Glasgow access road will be closed.  During that time, access to and from Linden to Glasgow Dining Hall will be controlled by flag people.

     

    Sewer connection

    Landscape area between Dundee and Glasgow

    Duration: TBD

    Date: TDB

    Details of this utility shutdown are in progress.  Please reach out to Dexter Galang at dexter.galang@ucr.edu with any concerns or questions.

     

  • 950578- STUDENT HEALTH & COUNSELING CENTER CONSTRUCTION ADVISORY #14

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Project Site

    Continued foundation concrete forms and rebar installation

    Excavator, semi-trucks, backhoe, loader, grader, & various hand tools

    Moderate level of sustained construction noise primarily comprised of running motors and backup alarms.

    Occasional increased slow traffic due to truck deliveries.

    Sidewalk will be open but alternate paths are encouraged.

    Project Site

    Continued foundation concrete pouring

    Concrete pumper truck, Concrete Mixer Truck, various hand tools

    Increased truck traffic along Linden from concrete truck deliveries.

    Continual hum and clanging during pours from concrete pump and mixing trucks starting at 7:00 AM through the early afternoon.

     

    Contractor Parking Area

    Continued parking for contractor and sub-contractors; storage of equipment

    Contractor vehicles

    Low level of vehicle and pedestrian noise.

     

    Contractor Offices

    Office Use

    Office Equipment and Furniture

    Low level of pedestrian noise

     

     

    Week of 5-30-2022

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Project Site

    Continued foundation concrete forms and rebar installation

    Excavator, semi-trucks, backhoe, loader, grader, & various hand tools

    Moderate level of sustained construction noise primarily comprised of running motors and backup alarms.

    Occasional increased slow traffic due to truck deliveries.

    Sidewalk will be open but alternate paths are encouraged.

     

    Project Site

    Continued foundation concrete pouring

    Concrete pumper truck, Concrete Mixer Truck, various hand tools

    Increased truck traffic along Linden from concrete truck deliveries.

    Continual hum and clanging during pours from concrete pump and mixing trucks starting at 7:00 AM through the early afternoon.

     

    Contractor Parking Area

    Continued parking for contractor and sub-contractors; storage of equipment

    Contractor vehicles

    Low level of vehicle and pedestrian noise.

     

    Contractor Offices

    Office Use

    Office Equipment and Furniture

    Low level of pedestrian noise

     

    Upcoming Anticipated Utility Shutdowns

    The following utility shutdown(s) are anticipated in the weeks to come.  Specific dates are approximations and logistical details are pending approval. Please contact Dexter Galang with any specific questions or concerns at dexter.galang@ucr.edu.

     

    Description

    Location

    Proposed

    Duration & Date

    Potential Impacted Buildings/ Facilities

    Domestic water connection

    Dundee access road at Linden and Pentland Hills Residence Halls,

    Building I, J, K and L

    Duration: 8 hours

    Date: Friday, June 17

    Pentland Hills Residence Halls,

    Building I, J, K and L will likely be without water for 8 hours;

    One lane of Dundee- Glasgow access road will be closed.  Traffic will be controlled by flag people.

     

    Sewer connection

    Landscape area between Dundee and Glasgow

    Duration: TBD

    Date: TDB

    Details of this utility shutdown are in progress.  It will also be discussed at the next Biweekly Neighborhood Meeting next Monday, May 30.  Please reach out to Dexter Galang at dexter.galang@ucr.edu with any concerns, questions or if you would like to attend that meeting.

     

  • 950578- STUDENT HEALTH & COUNSELING CENTER CONSTRUCTION ADVISORY #13

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Project Site

    Continued foundation excavation and rebar installation

    Excavator, semi-trucks, backhoe, loader, grader, & various hand tools

    Moderate level of sustained construction noise primarily comprised of running motors and backup alarms.

    Occasional increased slow traffic due to truck deliveries.

    Sidewalk will be open but alternate paths are encouraged.

     

    Contractor Parking Area

    Continued parking for contractor and sub-contractors; storage of equipment

     

    Contractor vehicles

    Low level of vehicle and pedestrian noise.

     

     

    Contractor Offices

    Office Use

    Office Equipment and Furniture

     

    Low level of pedestrian noise

     

     

    Week of 5-23-2022

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Project Site

    Continued foundation excavation and rebar installation

    Excavator, semi-trucks, backhoe, loader, grader, & various hand tools

    Moderate level of sustained construction noise primarily comprised of running motors and backup alarms.

    Occasional increased slow traffic due to truck deliveries.

    Sidewalk will be open but alternate paths are encouraged.

    Project Site

    Foundation Concrete Pouring

    Concrete pumper truck, Concrete Mixer Truck, various hand tools

    Increased truck traffic along Linden from concrete truck deliveries.

    Continual hum and clanging during pours from concrete pump and mixing trucks starting at 7:00 AM through the early afternoon.

     

    Dundee-Glasgow Access Road

    Utility Investigation/ potholing

    Vacuum excavator

    One lane of Dundee- Glasgow access road will be closed.  Traffic will be controlled by flag people.

    Contractor Parking Area

    Continued parking for contractor and sub-contractors; storage of equipment

    Contractor vehicles

    Low level of vehicle and pedestrian noise.

     

    Contractor Offices

    Office Use

    Office Equipment and Furniture

    Low level of pedestrian noise

     

    Live Earthcam link available soon!

     

    Upcoming Anticipated Utility Shutdowns

    The following utility shutdown is anticipated in the weeks to come.  Specific dates are approximations and logistical details are pending approval. Please contact Dexter Galang with any specific questions or concerns at dexter.galang@ucr.edu.

     

    Description

    Location

    Proposed

    Duration & Date

    Potential Impacted Buildings/ Facilities

    Domestic water connection

    Dundee access road at Linden and Pentland Hills Residence Halls,

    Building I, J, K and L

    Duration: 8 hours

    Date: Friday, June 17

    Pentland Hills Residence Halls,

    Building I, J, K and L will likely be without water for 8 hours;

    Temporary water option is currently being explored.

    One lane of Dundee- Glasgow access road will be closed.  Traffic will be controlled by flag people.

     

  • 950578- STUDENT HEALTH & COUNSELING CENTER CONSTRUCTION ADVISORY #12

    Please be advised that the following activities will be occurring during the weeks/ dates noted below at the Student Health & Counseling Center (SHCC) project site and surrounding areas during construction work hours (7am to 5pm).  The activities will occur within the areas identified and the contractor will access the Project Site as shown in the map below.

    The Student Health & Counseling Center Building Team recognizes that construction activities will pose inconveniences and disruption to the surrounding neighborhood. We thank you for your continued patience during the construction of this much needed project.

     

     

     

     

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Project Site

    Continued foundation excavation and rebar installation

    Excavator, semi-trucks, backhoe, loader, grader, & various hand tools

    Moderate level of sustained construction noise primarily comprised of running motors and backup alarms.

    Occasional increased slow traffic due to truck deliveries.

    Sidewalk will be open but alternate paths are encouraged.

     

    Contractor Parking Area

    Continued parking for contractor and sub-contractors; storage of equipment

     

    Contractor vehicles

    Low level of vehicle and pedestrian noise.

     

     

    Contractor Offices

    Office Use

    Office Equipment and Furniture

     

    Low level of pedestrian noise

     

     

    Week of 5-16-2022

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Project Site

    Continued foundation excavation and rebar installation

    Excavator, semi-trucks, backhoe, loader, grader, & various hand tools

    Moderate level of sustained construction noise primarily comprised of running motors and backup alarms.

    Occasional increased slow traffic due to truck deliveries.

    Sidewalk will be open but alternate paths are encouraged.

    Dundee Access Road

    Utility Investigation/ potholing

    Vacuum excavator

    Limited access of Dundee Access Road

    Contractor Parking Area

    Continued parking for contractor and sub-contractors; storage of equipment

    Contractor vehicles

    Low level of vehicle and pedestrian noise.

     

    Contractor Offices

    Office Use

    Office Equipment and Furniture

    Low level of pedestrian noise

     

    Live Earthcam link available soon!

     

    Upcoming Anticipated Utility Shutdowns

    The following utility shutdown is anticipated in the weeks to come.  Specific dates are approximations and logistical details are pending approval. Please contact Dexter Galang with any specific questions or concerns at dexter.galang@ucr.edu.

     

    Location

    Proposed

    Duration & Date

    Description

    Potential Impacted Buildings/ Facilities

    Dundee access road at Linden

    Duration: 8 hours

    Date: TBD, will occur on a day between June 12 through June 18

    Domestic water connection

    Pentland Hills Residence Halls,

    Building I, J, K and L will likely be without water for 8 hours;

    Limited access through the Dundee Access Road

     

  • 950578- STUDENT HEALTH & COUNSELING CENTER CONSTRUCTION ADVISORY #11

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Project Site

    Earthwork & Grading

    Excavator, semi-trucks, backhoe, loader, grader, & various hand tools

    Moderate level of sustained construction noise primarily comprised of running motors and backup alarms.

     

    Sidewalk will be open but alternate paths are encouraged.

     

    Contractor Parking Area

    Continued parking for contractor and sub-contractors; storage of equipment

     

    Contractor vehicles

    Low level of vehicle and pedestrian noise.

     

     

    Contractor Offices

    Office Use

    Office Equipment and Furniture

     

    Low level of pedestrian noise

     

     

    Week of 5-2-2022

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Project Site

    Foundation Excavation

    Excavator, semi-trucks, backhoe, loader, grader, & various hand tools

    Moderate level of sustained construction noise primarily comprised of running motors and backup alarms.

     

    Sidewalk will be open but alternate paths are encouraged.

     

    Linden Street at TAPS Parking Lot

    Temporary Power Installation

    Contractor Vehicles, various hand tools

    Low level of vehicle and pedestrian noise.  Brief traffic disturbances.

     

     

    Contractor Parking Area

    Continued parking for contractor and sub-contractors; storage of equipment

     

    Contractor vehicles

    Low level of vehicle and pedestrian noise.

     

     

    Contractor Offices

    Office Use

    Office Equipment and Furniture

     

    Low level of pedestrian noise

     

    Live Earthcam link available soon!

  • 950578- STUDENT HEALTH & COUNSELING CENTER CONSTRUCTION ADVISORY #10

    Current Weeks

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Project Site

    Earthwork & Grading

    Excavator, semi-trucks, backhoe, loader, grader, & various hand tools

    Moderate level of sustained construction noise primarily comprised of running motors and backup alarms.

     

    Sidewalk will be open but alternate paths are encouraged.

     

    Linden Street, Pentland Way, and South drive lane of remaining Parking Lot 21

    (see plan below)

     

    Earthwork, Grading & Soil Import

    Semi-trucks and Trailers

    Increased traffic during soil import operations anticipated on Friday, 4-15 from 8am to 4pm.

    Street closures not anticipated.

    Staging outside of the jobsite also not anticipated at this point.

    See diagram below for truck route in and out of the project site.

     

    Contractor Parking Area

    Continued parking for contractor and sub-contractors; storage of equipment

     

    Contractor vehicles

    Low level of vehicle and pedestrian noise.

     

     

    Contractor Offices

    Office Use

    Office Equipment and Furniture

     

    Low level of pedestrian noise

     

     

    Week of 4-18-2022

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Project Site

    Earthwork & Grading

    Excavator, semi-trucks, backhoe, loader, grader, & various hand tools

    Moderate level of sustained construction noise primarily comprised of running motors and backup alarms.

     

    Sidewalk will be open but alternate paths are encouraged.

     

    Linden Street, Pentland Way, and South drive lane of remaining Parking Lot 21

    (see plan below)

     

    Earthwork, Grading & Soil Import

    Semi-trucks and Trailers

    Continued increased traffic during soil import operations anticipated beginning Monday, 4-18 to Friday 4-22 from the hours of 8am to 4pm.

    Street closures not anticipated.

    Staging outside of the jobsite also not anticipated.

    Contractor Parking Area

    Continued parking for contractor and sub-contractors; storage of equipment

     

    Contractor vehicles

    Low level of vehicle and pedestrian noise.

     

     

    Contractor Offices

    Office Use

    Office Equipment and Furniture

     

    Low level of pedestrian noise

  • 950578- STUDENT HEALTH & COUNSELING CENTER CONSTRUCTION ADVISORY #9

    Current Weeks

    Construction Activities

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Project Site

    Continue underground utility relocation work within planting area along sidewalk of Linden

    Excavator, backhoe, trencher, & various hand tools

    Moderate level of sustained construction noise primarily comprised of running motors. Sidewalk will be open but alternate paths are encouraged.

     

    Contractor Parking Area

    Continued parking for contractor and sub-contractors; storage of equipment

    Contractor vehicles

    Low level of vehicle and pedestrian noise.

     

     

    Contractor Offices

    Office Use

    Office Equipment and Furniture

    Low level of pedestrian noise

     

     

     

     

    TAPS and EH&S Building

    Weekend Power Switchovers

    Trailered Generator, various hand tools

    1 hour power outage beginning Saturday, April 8 at approximately 7:00-8:00am and Sunday, April 9 at approximately 3:00-4:00pm

     

    TAPS Building

    Data/ Communications Cable Installation

    Various hand tools, contractor vehicles

    Data/ Communications shutdown beginning Saturday, April 8 at approximately 8:00 am to Sunday, April 9 at approximately 4:00pm.

    Fire watch will be in place for the duration of the data/com shutdown.

     

    Dundee Access Road

    Data/ Communications Cable Installation

    Cable Spools, various hand tools, contractor vehicles

    Full road closure beginning approximately Saturday, April 8 at 8 am to 5 pm and Sunday, April 9, 8am to 4pm.

    Access will be available for deliveries to and from Glasgow Dining Hall during that time.

    The road will be open to traffic after construction work hours.

     

    TAPS/ EH&S Backlot

    Weekend operation of backup power generator and removal of backup power generator

    Truck and Trailered Generator, various hand tools

    Moderate level of sustained running motor beginning approximately April 8 at 8am to April 9 at 1pm.  Disconnection of generator and haul away will occur on April 9 at approximately 2:00pm.

     

     

    Week of 4-11-2022

    Construction Activities

     

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Project Site

    Earthwork & Grading

    Excavator, semi-trucks, backhoe, loader, grader, & various hand tools

    Moderate level of sustained construction noise primarily comprised of running motors and backup alarms.

     

    Sidewalk will be open but alternate paths are encouraged.

     

     

     

     

     

     

     

    Linden Street, Pentland Way, and South drive lane of remaining Parking Lot 21

    (see plan below)

     

    Earthwork, Grading & Soil Import

    Semi-trucks and Trailers

    Increased traffic during soil import operations anticipated on Friday, 4-15 from 8am to 4pm.

    Street closures not anticipated.

    Staging outside of the jobsite also not anticipated at this point.

     

    Contractor Parking Area

    Continued parking for contractor and sub-contractors; storage of equipment

     

    Contractor vehicles

    Low level of vehicle and pedestrian noise.

     

     

     

    Contractor Offices

    Office Use

    Office Equipment and Furniture

     

    Low level of pedestrian noise

                     

     

     

  • 950578- STUDENT HEALTH & COUNSELING CENTER CONSTRUCTION ADVISORY #8

    Current Weeks

    Construction Activities

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Project Site

    Continue underground utility relocation work within planting area along sidewalk of Linden

    Excavator, backhoe, trencher, & various hand tools

    Moderate level of sustained construction noise primarily comprised of running motors. Sidewalk will be open but alternate paths are encouraged.

     

    Contractor Parking Area

    Continued parking for contractor and sub-contractors; storage of equipment

    Contractor vehicles

    Low level of vehicle and pedestrian noise.

     

     

    Contractor Offices

    Office Use

    Office Equipment and Furniture

    Low level of pedestrian noise

     

    TAPS/ EH&S Backlot

    Installation and weekend operation of backup power generator

    Truck and Trailered Generator, various hand tools

    Friday, April 1 afternoon installation beginning approximately 3pm.

    Moderate level of sustained running motor beginning April 2 at approximately 8am to April 3 at approximately 1pm.

     

    TAPS and EH&S Building

    Weekend Power Switchovers

    Trailered Generator, various hand tools

    1 hour power outage beginning Saturday, April 2 at approximately 8:00-9:00am and Sunday, April 3 at approximately 12:00-1:00pm

     

    Dundee Access Road at Linden

    Weekend Dundee Access Road Vault investigation

    Jack hammer, Backhoe/excavator with breaker, Contractor work vehicles.

     

    Partial road closure beginning Saturday, April 2 at approximately 8 am to 5 pm Sunday, April 3, approximately 8am to 1pm. There will be a high level of sustained construction noise primarily comprised of chipping and banging

     

    Week of 4-4-2022

    Construction Activities

    Location

    Activity

    Equipment Used

    Anticipated Disturbance

    Project Site

    Continue underground utility relocation work within planting area along sidewalk of Linden

    Excavator, backhoe, trencher, & various hand tools

    Moderate level of sustained construction noise primarily comprised of running motors. Sidewalk will be open but alternate paths are encouraged.

     

    Contractor Parking Area

    Continued parking for contractor and sub-contractors; storage of equipment

    Contractor vehicles

    Low level of vehicle and pedestrian noise.

     

     

    Contractor Offices

    Office Use

    Office Equipment and Furniture

    Low level of pedestrian noise

     

     

     

     

    TAPS and EH&S Building

    Weekend Power Switchovers

    Trailered Generator, various hand tools

    1 hour power outage beginning Saturday, April 8 at approximately 8:00-9:00am and Sunday, April 9 at approximately 12:00-1:00pm

     

    TAPS Building

    Data/ Communications Cable Installation

    Various hand tools, contractor vehicles

    Data/ Communications shutdown beginning Saturday, April 8 at approximately 8:00 am to Sunday, April 9 at approximately 1:00pm.  Fire watch will be in place for the duration of the data/com shutdown.

     

    Dundee Access Road

    Data/ Communications Cable Installation

    Cable Spools, various hand tools, contractor vehicles

    Full road closure beginning approximately Saturday, April 8 at 8 am to 5 pm Sunday, April 9, 8am to 1pm. Access will be available for deliveries to and from Glasgow Dining Hall during that time.

     

    TAPS/ EH&S Backlot

    Weekend operation of backup power generator and removal of backup power generator

    Truck and Trailered Generator, various hand tools

    Moderate level of sustained running motor beginning approximately April 8 at 8am to April 9 at 1pm.  Disconnection of generator and haul away will occur on April 9 at approximately 2:00pm.