Breadcrumb

School of Medicine Building 2

PDC Contacts

Project Manager: Mihai Gavan - 951-827-6959

Planner: Melissa Garrety - 951- 827-7376

Project Description

The University of California Riverside proposes to construct the School of Medicine (SOM) Education Building II, a new facility of approximately 57,000 assignable square feet (ASF) that will directly support the academic and programmatic mission of the UCR School of Medicine by providing adequate space for existing needs, as well as allowing for future expansion of the class size (up to 125 students per class).

The proposed building is anticipated to provide up to 57,000 assignable square feet (ASF) within approximately 90,000 gross square feet (GSF). The space program will incorporate the following types of spaces, to complement SOM's existing program:

  • instruction and instruction support spaces such as classrooms, specialized teaching spaces, and lecture halls;
  • student support and study facilities including study/lounge spaces necessary to comply with accreditation standards; and,
  • academic and administrative offices and support spaces

SOM Education Bldg 2

  • Project Details
  • Construction
  • News

Current Activity

  • Complete construction documents
  • Logistics at Parking Lot 10 and 41
  • Demolition
  • Excavation and grading
  • Building foundations
  • Wall panel fabrication
  • Headhouse buildout
  • Generator yard enclosure

 

Live Feed
Live Feed

 

 

 

 

 

Next Steps

  • Building structure
  • Utility connections
  • MEP interior infrastructure

Construction Notices

  • Please be advised that access to Greenhouse 6 and its associated Headhouse is no longer available.
  • Please be advised that access to the loading docks of Boyce Hall, Scotty’s, SOM ED, and the associated parking stalls in the area is no longer be available. This area will be permanently closed for construction activities. Please utilize the temporary loading dock at the West Courtyard accessible through Parking Lot 11.
  • Please be advised that the eastern most row of parking spots in Lot 10 will no longer be available for the duration of the SOM ED II project (summer 2023), as this will be impacted by the construction trailers area.

Project Location

Project Anticipated Timeline

Project Updates

School of Medicine Education Building II Updates
  • 954045 SOM ED II - Construction Alert #115

    954045 SOM ED II Construction Alert #115

     

    Please be advised that the following activities will be occurring from 5:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas during the week of September 5th  through September 12th The activities will occur within the areas identified in the attached exhibits and as shown in the map below.  

     

    Building Site:

     

    • Continue Interior punch items. (Equipment: Various hand and power tools).
    • Continue Exterior & Roof punch items. (Equipment: Various hand and power tools).
    • Continue Landscaping Installation. (Equipment: Various hand and power tools).
    • Continue Installation of Exterior Furniture over the course of the week. (Equipment: Various hand and power tools).
    • Installation of the Equipment Screening in the Breezeway of Boyce Hall 1st Floor. (Equipment: Various hand and power tools).

    Anticipated disturbances: Medium-level construction noise on Building Site.

     

     New Generator Yard: 

    • Continue Landscaping Installation.

    ·         Anticipated disturbances: Low level construction noise contained in the surrounding area.

     

    SOM ED I Existing Electrical Yard (South): 

    • No activities scheduled for the SOM ED I Generator Yard.  
    • Pedestrian access to surrounding buildings will remain open. 
    • Anticipated disturbances: Low level construction noise contained to SOM EDI Electrical Yard. 

     

     West Courtyard: 

     

    • The red temporary loading dock and concrete guard rails (K-Rail) will be removed on September 8th.  The loading dock at the School of Medicine Education Building II will available for use from that point on. (Equipment: Fork-lift and Lift Equipment, Various hand and power tools).
    • Continue Landscaping work, including the removal of temporary concrete pads and placement of concrete to complete the work in the fenced-in area to the west of the building.. (Equipment: Concrete trucks, Concrete Pump, Various hand and power tools).
    • Continue Please be advised that the West Courtyard and the new pathway being provided in this area will be open and ready to support activities within two weeks of this notice.  

     

    Parking Lot 11:  

    • Activities and access to loading docks will not be affected.  
    • Please be advised that the Parking Lot 11 existing access will be the new access road for deliveries into the West Courtyard Temporary Loading Dock. Please reference construction Alerts from Batchelor hall renovations for further access and activities considerations.

     

    Construction Trailer Area at Parking Lot 10: 

    • The Construction Trailers will be de-mobilized beginning Monday, September 11.  (Equipment: Lift Equipment, Tractor Tow Vehicles, Crane Equipment).  
    • Anticipated disturbances: Low level construction noise at Lot 10.   
    • Please be advised that the eastern most row of parking spots in Lot 10 will not be available for the duration of this work.

     

    Parking Lot 41 Laydown Area: 

    • The Lot 41 will be turned over to the University the week of September 18. As de-mobilization occurs over the next two weeks there will be work on-going in the lot to restore the lot.  (Equipment: delivery trucks, and various hand tools).  
    • Pedestrian access to GH/HH #11-14 and surrounding buildings will remain open. 
    • Activities and access to loading docks will not be affected.  
    • Anticipated disturbances: Low level construction noise at Lot 41.  

    Continuous noises on site: Delivery trucks, construction equipment (back-up alarms), jackhammers, saws, screw guns, and hammers. 

  • 954045 SOM ED II - Construction Alert #112

    08/05/2023- 08/12/2023

     

    954045 SOM ED II Construction Alert #112

     

    Please be advised that the following activities will be occurring from 6:00AM to 2:30PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas on Saturday, August 05th.

     

    Saturday, August 05th

     

    Building Site:

    • Continue re-installing Sunshades at the South side. (Equipment: Various hand and power tools).
    • Continue Stair 1 Stadium, Seating & Punchlist. (Equipment: Various hand and power tools).
    • Continue Paint Interior punch list & Exposed Fire Piping (Equipment: Various hand and power tools).
    • Continue SS Railing at Tiered Teaching. (Equipment: Various hand and power tools).
    • Continue landscaping activities. (Equipment: Various hand and power tools).
    • Continue South West Hardscape. (Equipment: Various hand and power tools).
    • Concrete polish Level 1 Vestibule by Restrooms. (Equipment: Various hand and power tools).
    • Continue commissioning. (Equipment: Various hand and power tools).
    • Continue Exterior & Interior Concrete Punchlist. (Equipment: Various hand and power tools).
    • Anticipated disturbances: Medium-level construction noise on Building Site.

     

     

    Please be advised that the following activities will be occurring from 5:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas during the week of August 07th through August 12th The activities will occur within the areas identified in the attached exhibits and as shown in the map below.  

     

    Building Site:

     

    • Continue Interior build-out & punch items. (Equipment: Various hand and power tools).
    • Continue Exterior & Roof punch items. (Equipment: Various hand and power tools).
    • Continue MEP activities on Levels 1-5.  (Equipment: Various hand and power tools).
    • Complete Air Barrier Application at the West Loading Dock. (Equipment: Various hand and power tools).
    • Continue Exterior BOK Modern Panel Installation (Equipment: Various hand and power tools).
    • Install Brick Ledger Angle at West Trash Enclosure. (Equipment: Various hand and power tools).
    • Continue Handrail & Guardrail installation. (Equipment: Various hand and power tools)

    Continue Deck Traffic Coating at Levels 3, 4 & 5 East Terraces. (Equipment: Various hand and power tools)

    Anticipated disturbances: Medium-level construction noise on Building Site.

     

     New Generator Yard: 

    • Pedestrian access to the North doors of Headhouses #7-10 will remain open.

    ·         Anticipated disturbances: Low level construction noise contained in the surrounding area.

     

    Headhouse 7: 

    • No activities are scheduled for the Headhouse. (Equipment: Various hand tools).
    • Anticipated disturbances: Low level construction noise contained to surrounding area.  

     

    SOM ED I Existing Electrical Yard (South): 

    • No activities scheduled for the SOM ED I Generator Yard.  
    • Pedestrian access to surrounding buildings will remain open. 
    • Anticipated disturbances: Low level construction noise contained to SOM EDI Electrical Yard. 

     

     West Courtyard: 

    • Please be advised that the West Courtyard and the new temporary loading dock in this area are open and ready to support activities until project completion.  

     

    Parking Lot 11:  

    • Activities and access to loading docks will not be affected.  
    • Please be advised that the Parking Lot 11 existing access will be the new access road for deliveries into the West Courtyard Temporary Loading Dock. Please reference construction Alerts from Batchelor hall renovations for further access and activities considerations.

     

    Construction Trailer Area at Parking Lot 10: 

    • Continue material deliveries to trailer lot (Equipment: delivery truck).  
    • Anticipated disturbances: Low level construction noise at Lot 10.   
    • Please be advised that the eastern most row of parking spots in Lot 10 will no longer be available for the duration of the SOM ED II project (summer 2023), as this will be impacted by the construction trailers area. 

     

    Parking Lot 41 Laydown Area: 

    • Material deliveries (Equipment: delivery trucks, and various hand tools).  
    • Pedestrian access to GH/HH #11-14 and surrounding buildings will remain open. 
    • Activities and access to loading docks will not be affected.  
    • Anticipated disturbances: Low level construction noise at Lot 41.  

     

    Items listed in red: Please note that this activity may potentially disrupt the pedestrian and/or vehicular pathways and the occupants in adjacent buildings.      

     

    Continuous noises on site: Delivery trucks, construction equipment (back-up alarms), jackhammers, saws, screw guns, and hammers. 

  • 954045 SOM ED II - Construction Alert #111

    07/29/2023- 08/05/2023

     

    954045 SOM ED II Construction Alert #111

     

    Please be advised that the following activities will be occurring from 6:00AM to 2:30PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas on Saturday, July 29th, and Sunday, July 30th.

     

    Saturday, July 22nd, and Sunday, July 23rd.

     

    Building Site:

    • C Continue punching lockers. (Equipment: Various hand and power tools).
    • Continue casework in Tiered Teaching (Equipment: Various hand and power tools).
    • Install trash enclosure ledger. (Equipment: Various hand and power tools).
    • Continue tile punch list. (Equipment: Various hand and power tools).
    • Continue painting GFRG. (Equipment: Various hand and power tools).
    • Continue installing the egress handrail. (Equipment: Various hand and power tools).
    • Install Stair 5 Angle Iron fixes. (Equipment: Various hand and power tools).
    • Continue Sunshade Re-install. (Equipment: Various hand and power tools).
    • Continue landscaping. (Equipment: Various hand and power tools).
    • Complete installing pavers at L2 and L3 Terraces. (Equipment: Various hand and power tools).
    • Install Level 1 hardscape pavers. (Equipment: Various hand and power tools).
    • Continue commissioning items on rooms 104, 105, and 106. (Equipment: Various hand and power tools).
    • Complete the Brick Screen at the Loading dock. (Equipment: Various hand and power tools).
    • Anticipated disturbances: Medium-level construction noise on Building Site.

     

    Sunday, July 30th

     

    • Continue casework in Tiered Teaching. (Equipment: Various hand and power tools).
    • Continue commissioning items in rooms 104, 105, and 106. (Equipment: Various hand and power tools).
    • Continue punching lockers. (Equipment: Various hand and power tools).

     

     

    Please be advised that the following activities will be occurring from 5:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas during the week of July 31st thru August 5th.. The activities will occur within the areas identified in the attached exhibits and as shown in the map below.  

     

    Building Site:

     

    • Continue Interior build-out & punch items. (Equipment: Various hand and power tools).
    • Continue Exterior & Roof punch items. (Equipment: Various hand and power tools).
    • Continue MEP activities on Levels 1-5.  (Equipment: Various hand and power tools).
    • Complete Air Barrier Application at the West Loading Dock. (Equipment: Various hand and power tools).
    • Continue Exterior BOK Modern Panel Installation (Equipment: Various hand and power tools).
    • Install Brick Ledger Angle at West Trash Enclosure. (Equipment: Various hand and power tools).
    • Continue Handrail & Guardrail installation. (Equipment: Various hand and power tools)
    • Continue Deck Traffic Coating at Levels 3, 4 & 5 East Terraces. (Equipment: Various hand and power tools)

    Anticipated disturbances: Medium-level construction noise on Building Site.

     

     New Generator Yard: 

    • Pedestrian access to the North doors of Headhouses #7-10 will remain open.

    ·         Anticipated disturbances: Medium level construction noise contained in the surrounding area.

     

    Headhouse 7: 

    • No activities are scheduled for the Headhouse. (Equipment: Various hand tools).
    • Anticipated disturbances: Low level construction noise contained to surrounding area.  

     

    SOM ED I Existing Electrical Yard (South): 

    • No activities scheduled for the SOM ED I Generator Yard.  
    • Pedestrian access to surrounding buildings will remain open. 
    • Anticipated disturbances: Low level construction noise contained to SOM EDI Electrical Yard. 

     

     West Courtyard: 

    • Please be advised that the West Courtyard and the new temporary loading dock in this area are open and ready to support activities until project completion.  

     

    Parking Lot 11:  

    • Activities and access to loading docks will not be affected.  
    • Please be advised that the Parking Lot 11 existing access will be the new access road for deliveries into the West Courtyard Temporary Loading Dock. Please reference construction Alerts from Batchelor hall renovations for further access and activities considerations.

     

    Construction Trailer Area at Parking Lot 10: 

    • Continue material deliveries to trailer lot (Equipment: delivery truck).  
    • Anticipated disturbances: Low level construction noise at Lot 10.   
    • Please be advised that the eastern most row of parking spots in Lot 10 will no longer be available for the duration of the SOM ED II project (summer 2023), as this will be impacted by the construction trailers area. 

     

    Parking Lot 41 Laydown Area: 

    • Material deliveries (Equipment: delivery trucks, and various hand tools).  
    • Pedestrian access to GH/HH #11-14 and surrounding buildings will remain open. 
    • Activities and access to loading docks will not be affected.  
    • Anticipated disturbances: Low level construction noise at Lot 41.  

     

    Items listed in red: Please note that this activity may potentially disrupt the pedestrian and/or vehicular pathways and the occupants in adjacent buildings.      

     

    Continuous noises on site: Delivery trucks, construction equipment (back-up alarms), jackhammers, saws, screw guns, and hammers. 

  • 954045 SOM ED II - Construction Alert #110

    954045 SOM ED II Construction Alert #110

     

    Please be advised that the following activities will be occurring from 6:00AM to 2:30PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas on Saturday, July 22nd, and Sunday, July 23rd.

     

    Saturday, July 22nd, and Sunday, July 23rd.

     

    Building Site:

    • Casework at Tiered Teaching and Countertop Touch-up. (Equipment: Various hand and power tools).
    • Continue Installing Guardrail/Handrail at Stairs 1,3, 5, & 6 (Equipment: Various hand and power tools).
    • Continue Installing Tiles in the Wellness Rooms on Levels 2 & 4. (Equipment: Various hand and power tools).
    • Continue Taping at GFRG and Misc. Patches. (Equipment: Various hand and power tools).
    • Continue Dropping Ceiling Tiles on Levels 1 and 2. (Equipment: Various hand and power tools).
    • Roof PVC Patching. (Equipment: Various hand and power tools).
    • Continue Installing BOK Modern Panels at Stair 4, Drill and Epoxy Required at Deck Edge. (Equipment: Boom Lift/Various hand and power tools).
    • Install Curb and Gutter at South Road (Equipment: Various hand and power tools).
    • Continue Installing Brick at the Bike Rack Wall (Equipment: Lift/Various hand and power tools).
    • Electrical Rough-in at Tiered Teaching for Countertop Receptacles + Light Fixture Install at Stair 6 and Site (Equipment: Various hand and power tools).
    • Punchlist Painting at Levels 1 and 2 Including the Grand Stair and GFRG Panels (Equipment: Various hand and power tools).
    • Grind and Polish at Level 2 + Concrete Seal at Back-of-House Rooms on Level 1. (Equipment: Various hand and power tools).
    • Install Key Switches at Fire Shutter Door (Equipment: Various hand and power tools).
    • Plaster at Loading Dock (Equipment: Various hand and power tools).
    • Concrete Demolition at Level 1 Main Entrance (Equipment: Various hand and power tools).
    • Continue Installing Pavers at the Level 2 Terrace (Equipment: Various hand and power tools).

    Anticipated disturbances: Medium-level construction noise on Building Site.

     

    Please be advised that the following activities will be occurring from 5:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas during the week of July 24th thru July 29th. The activities will occur within the areas identified in the attached exhibits and as shown in the map below.  

     

    Building Site:

     

    • Continue Interior build-out & punch items. (Equipment: Various hand and power tools).
    • Continue Site Hardscape Concrete Placement. (Equipment: Various hand and power tools).
      • Pour South Road Sidewalk by Greenhouses. (Equipment: Various hand and power tools).
        • Please be advised on Monday 7/24/23 we will be placing concrete. Anticipated timeline 6 AM – 12 PM. Please reference UCR EDII Concrete Truck Staging and Haul Route exhibit outlining haul routes and staging areas for the concrete trucks
    • Continue Exterior & Roof punch items. (Equipment: Various hand and power tools).
    • Continue MEP activities on Levels 1-5.  (Equipment: Various hand and power tools).
    • Complete Air Barrier Application at the West Loading Dock. (Equipment: Various hand and power tools).
    • Continue Exterior BOK Modern Panel Installation (Equipment: Various hand and power tools).
    • Install Brick Ledger Angle at West Trash Enclosure. (Equipment: Various hand and power tools).
    • Continue Brick Veneer Screen Vertical HSS posts installation at the Loading Dock & Bike Storage room. (Equipment: Various hand and power tools).
    • Brick Installation at Loading Dock & Bike Storage Room. (Equipment: Various hand and power tools).
    • Continue Handrail & Guardrail installation. (Equipment: Various hand and power tools)
    • Begin Deck Traffic Coating at decks.

    Anticipated disturbances: Medium-level construction noise on Building Site.

     

     New Generator Yard: 

    • Pedestrian access to the North doors of Headhouses #7-10 will remain open.

    ·         Anticipated disturbances: Medium level construction noise contained in the surrounding area.

     

    Headhouse 7: 

    • No activities are scheduled for the Headhouse. (Equipment: Various hand tools).
    • Anticipated disturbances: Low level construction noise contained to surrounding area.  

     

    SOM ED I Existing Electrical Yard (South): 

    • No activities scheduled for the SOM ED I Generator Yard.  
    • Pedestrian access to surrounding buildings will remain open. 
    • Anticipated disturbances: Low level construction noise contained to SOM EDI Electrical Yard. 

     

     West Courtyard: 

    • Please be advised that the West Courtyard and the new temporary loading dock in this area are open and ready to support activities until project completion.  

     

    Parking Lot 11:  

    • Activities and access to loading docks will not be affected.  
    • Please be advised that the Parking Lot 11 existing access will be the new access road for deliveries into the West Courtyard Temporary Loading Dock. Please reference construction Alerts from Batchelor hall renovations for further access and activities considerations.

     

    Construction Trailer Area at Parking Lot 10: 

    • Continue material deliveries to trailer lot (Equipment: delivery truck).  
    • Anticipated disturbances: Low level construction noise at Lot 10.   
    • Please be advised that the eastern most row of parking spots in Lot 10 will no longer be available for the duration of the SOM ED II project (summer 2023), as this will be impacted by the construction trailers area. 

     

    Parking Lot 41 Laydown Area: 

    • Material deliveries (Equipment: delivery trucks, and various hand tools).  
    • Pedestrian access to GH/HH #11-14 and surrounding buildings will remain open. 
    • Activities and access to loading docks will not be affected.  
    • Anticipated disturbances: Low level construction noise at Lot 41.  

     

    Items listed in red: Please note that this activity may potentially disrupt the pedestrian and/or vehicular pathways and the occupants in adjacent buildings.      

     

    Continuous noises on site: Delivery trucks, construction equipment (back-up alarms), jackhammers, saws, screw guns, and hammers. 

     

  • 954045 SOM ED II - Construction Alert #109

    07/15/2023- 07/22/2023

     

    954045 SOM ED II Construction Alert #109

     

    Please be advised that the following activities will be occurring from 6:00AM to 2:30PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas on Saturday, July 15th, and Sunday, July 16th.

     

    Saturday, July 15th  & Sunday July 16th

     

    Building Site:

    • Casework and countertop touch-up. (Equipment: Various hand and power tools).
    • Continue installing Guardrail at Levels 4 & 5 East Terrace, Stairs 1 and 3. (Equipment: Various hand and power tools).
    • Install trash enclosure ledger. (Equipment: Various hand and power tools).
    • Continue installing the level 1 operable partition door. (Equipment: Various hand and power tools).
    • Continue installing flooring on level 2 tiered teaching. (Equipment: Various hand and power tools).
    • Continue installing tile on level 4 coffee station and level 1 kitchenette. (Equipment: Various hand and power tools).
    • Continue taping on Stair 6 and misc. patches. (Equipment: Various hand and power tools).
    • Continue door push/pull adjustments. (Equipment: Various hand and power tools).
    • Continue dropping ceiling tiles. (Equipment: Various hand and power tools).
    • Continue adjusting the level 2 terrace door and level 2 lobby break metal panel.
    • Continue brick at stair 3 & trash enclosure. (Equipment: Various hand and power tools).
    • Continue installing coping cap on the roof. (Equipment: Various hand and power tools).

    Anticipated disturbances: Medium-level construction noise on Building Site.

     

    Please be advised that the following activities will be occurring from 5:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas during the week of July 17th through July 22nd. The activities will occur within the areas identified in the attached exhibits and as shown in the map below.  

     

    Building Site:

     

    • Continue Interior build-out & punch items. (Equipment: Various hand and power tools).
    • Continue Site Hardscape Concrete Placement. (Equipment: Various hand and power tools).
      • Pour North East Road. (Equipment: Various hand and power tools).
        • Please be advised on Monday 7/17/23 we will be placing concrete. Anticipated timeline 6 AM – 12 PM. Please reference UCR EDII Concrete Truck Staging and Haul Route exhibit outlining haul routes and staging areas for the concrete trucks
    • Continue Exterior & Roof punch items. (Equipment: Various hand and power tools).
    • Continue MEP activities on Levels 1-5.  (Equipment: Various hand and power tools).
    • Complete Air Barrier Application at the West Loading Dock. (Equipment: Various hand and power tools).
    • Continue Exterior BOK Modern Panel Installation (Equipment: Various hand and power tools).
    • Install Brick Ledger Angle at West Trash Enclosure. (Equipment: Various hand and power tools).
    • Continue Brick Veneer Screen Vertical HSS posts installation at the Loading Dock & Bike Storage room. (Equipment: Various hand and power tools).
    • Brick Installation at Loading Dock & Bike Storage Room. (Equipment: Various hand and power tools).
    • Continue Handrail & Guardrail installation. (Equipment: Various hand and power tools)

    Anticipated disturbances: Medium-level construction noise on Building Site.

     

     Chemistry Building:

    • Place New Concrete Sidewalk. (Equipment: Various hand and power tools).
      • Please be advised on Monday 7/17/23 we will be placing concrete. Anticipated timeline 6 AM – 12 PM. Please reference UCR EDII Concrete Truck Staging and Haul Route exhibit outlining haul routes and staging areas for the concrete trucks.

    Anticipated disturbances: Medium-level construction noise

     

    New Generator Yard: 

    • Pedestrian access to the North doors of Headhouses #7-10 will remain open.

    ·         Anticipated disturbances: Medium level construction noise contained in the surrounding area.

     

    Headhouse 7: 

    • No activities are scheduled for the Headhouse. (Equipment: Various hand tools).
    • Anticipated disturbances: Low level construction noise contained to surrounding area.  

     

    SOM ED I Existing Electrical Yard (South): 

    • No activities scheduled for the SOM ED I Generator Yard.  
    • Pedestrian access to surrounding buildings will remain open. 
    • Anticipated disturbances: Low level construction noise contained to SOM EDI Electrical Yard. 

     

     West Courtyard: 

    • Please be advised that the West Courtyard and the new temporary loading dock in this area are open and ready to support activities until project completion.  

     

    Parking Lot 11:  

    • Activities and access to loading docks will not be affected.  
    • Please be advised that the Parking Lot 11 existing access will be the new access road for deliveries into the West Courtyard Temporary Loading Dock. Please reference construction Alerts from Batchelor hall renovations for further access and activities considerations.

     

    Construction Trailer Area at Parking Lot 10: 

    • Continue material deliveries to trailer lot (Equipment: delivery truck).  
    • Anticipated disturbances: Low level construction noise at Lot 10.   
    • Please be advised that the eastern most row of parking spots in Lot 10 will no longer be available for the duration of the SOM ED II project (summer 2023), as this will be impacted by the construction trailers area. 

     

    Parking Lot 41 Laydown Area: 

    • Material deliveries (Equipment: delivery trucks, and various hand tools).  
    • Pedestrian access to GH/HH #11-14 and surrounding buildings will remain open. 
    • Activities and access to loading docks will not be affected.  
    • Anticipated disturbances: Low level construction noise at Lot 41.  

     

    Items listed in red: Please note that this activity may potentially disrupt the pedestrian and/or vehicular pathways and the occupants in adjacent buildings.      

     

    Continuous noises on site: Delivery trucks, construction equipment (back-up alarms), jackhammers, saws, screw guns, and hammers

  • 954045 SOM ED II - Construction Alert #108

    07/08/2023- 07/15/2023

     

    954045 SOM ED II Construction Alert #108

     

    Please be advised that the following activities will be occurring from 6:00AM to 2:30PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas on Saturday, July 08th.

     

    Saturday, July 08th

     

    Building Site:

    • Install Metal Panel Ceiling in Tiered Teaching room. (Equipment: Various hand and power tools).
    • Continue Brick Veneer Screen Vertical HSS posts installation at the Loading Dock & Bike Storage room. (Equipment: Various hand and power tools).
    • Tiered Teaching Access Floor Re-install. (Equipment: Various hand and power tools).
    • Apply Air Barrier Stair #3 & L3 Soffit Fire Caulking. (Equipment: Various hand and power tools).
    • Install Level 3 Shutter Door. (Equipment: Various hand and power tools).
    • Install Tiered Teaching Soffit. (Equipment: Various hand and power tools).
    • Install Dropping Remaining Tiles L5 down (Equipment: Various hand and power tools).
    • Install L4 Corridor Ceiling @ Stair 6. (Equipment: Various hand and power tools).
    • Form Stair 5 Curbs. (Equipment: Various hand and power tools).
    • Sweep Exterior Stairs & Terraces. (Equipment: Various hand and power tools).
    • Form North East Steps. (Equipment: Various hand and power tools).
    • Continue North Road Vent Activity. (Equipment: Various hand and power tools).
    • Continue L4 Corridor Ceiling @ Stair 6. (Equipment: Various hand and power tools).
    • Place SouthWest Concrete Bands. (Equipment: Various hand and power tools).
      • Please be advised on Saturday 7/8/23 we will be placing concrete. Anticipated timeline 6 AM – 12 PM. Please reference UCR EDII Concrete Truck Staging and Haul Route exhibit outlining haul routes and staging areas for the concrete trucks

    Anticipated disturbances: Medium-level construction noise on Building Site.

     

    Please be advised that the following activities will be occurring from 5:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas during the week of July 10th thru July 15th. The activities will occur within the areas identified in the attached exhibits and as shown in the map below.  

     

    Building Site:

     

    • Chlorination and Testing. (Equipment: Various hand and power tools).
        • Please be advised on Tuesday 7/11/23 we will be doing testing from 2 am to 7 am.
    • Continue Interior build-out & punch items. (Equipment: Various hand and power tools).
    • Continue Site Hardscape Concrete Placement. (Equipment: Various hand and power tools).
      • Pour North East Architectural Steps & Porch Slab. (Equipment: Various hand and power tools).
        • Please be advised on Tuesday 7/11/23 we will be placing concrete. Anticipated timeline 6 AM – 12 PM. Please reference UCR EDII Concrete Truck Staging and Haul Route exhibit outlining haul routes and staging areas for the concrete trucks
    • Continue Exterior & Roof punch items. (Equipment: Various hand and power tools).
    • Continue MEP activities on Levels 1-5.  (Equipment: Various hand and power tools).
    • Complete Air Barrier Application at the West Loading Dock. (Equipment: Various hand and power tools).
    • Continue Exterior BOK Modern Panel Installation (Equipment: Various hand and power tools).
    • Install Brick Ledger Angle at West Trash Enclosure. (Equipment: Various hand and power tools).
    • Brick Installation at Loading Dock & Bike Storage Room. (Equipment: Various hand and power tools).
    • Continue Handrail & Guardrail installation. (Equipment: Various hand and power tools)

    Anticipated disturbances: Medium-level construction noise on Building Site.

     

     Chemistry Building:

    • Demo New Concrete Sidewalk. (Equipment: Various hand and power tools).

    Please be advised on Tuesday 7/11 there will be no access at the entrance & exit door South of the Chemistry building

     

    West connector courtyard (South of Webber):

    • Continue grading at South of Webber. (Equipment: Various hand and power tools).
    • Pour Concrete Sidewalk South of Webber for Placement 2. (Equipment: Various hand and power tools).

    Anticipated disturbances: Medium-level construction noise

     

    New Generator Yard: 

    • Pedestrian access to the North doors of Headhouses #7-10 will remain open.

    ·         Anticipated disturbances: Medium level construction noise contained in the surrounding area.

     

    Headhouse 7: 

    • No activities are scheduled for the Headhouse. (Equipment: Various hand tools).
    • Anticipated disturbances: Low level construction noise contained to surrounding area.  

     

    SOM ED I Existing Electrical Yard (South): 

    • No activities scheduled for the SOM ED I Generator Yard.  
    • Pedestrian access to surrounding buildings will remain open. 
    • Anticipated disturbances: Low level construction noise contained to SOM EDI Electrical Yard. 

     

     West Courtyard: 

    • Please be advised that the West Courtyard and the new temporary loading dock in this area are open and ready to support activities until project completion.  

     

    Parking Lot 11:  

    • Activities and access to loading docks will not be affected.  
    • Please be advised that the Parking Lot 11 existing access will be the new access road for deliveries into the West Courtyard Temporary Loading Dock. Please reference construction Alerts from Batchelor hall renovations for further access and activities considerations.

     

    Construction Trailer Area at Parking Lot 10: 

    • Continue material deliveries to trailer lot (Equipment: delivery truck).  
    • Anticipated disturbances: Low level construction noise at Lot 10.   
    • Please be advised that the eastern most row of parking spots in Lot 10 will no longer be available for the duration of the SOM ED II project (summer 2023), as this will be impacted by the construction trailers area. 

     

    Parking Lot 41 Laydown Area: 

    • Material deliveries (Equipment: delivery trucks, and various hand tools).  
    • Pedestrian access to GH/HH #11-14 and surrounding buildings will remain open. 
    • Activities and access to loading docks will not be affected.  
    • Anticipated disturbances: Low level construction noise at Lot 41.  

     

    Items listed in red: Please note that this activity may potentially disrupt the pedestrian and/or vehicular pathways and the occupants in adjacent buildings.      

     

    Continuous noises on site: Delivery trucks, construction equipment (back-up alarms), jackhammers, saws, screw guns, and hammers.

  • 954045 SOM ED II - Construction Alert #107

    07/01/2023- 07/08/2023

     

    954045 SOM ED II Construction Alert #107

     

    Please be advised that the following activities will be occurring from 6:00AM to 2:30PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas on Saturday, July 01st.

     

    Saturday, July 1st

     

    Building Site:

    • Touch up casework and countertop. (Equipment: Various hand and power tools).
    • Install Stair 2, 3 & 4 Handrails. (Equipment: Various hand and power tools).
    • Install Trash Enclosure Gates. (Equipment: Various hand and power tools).
    • Install Shutter Door Support Steel. (Equipment: Various hand and power tools).
    • Install Level 1 Operable Partition Door. (Equipment: Various hand and power tools).
    • Install Level 1 Vinyl Flooring Under Stair 1 (Equipment: Various hand and power tools).
    • Install Level 2 Polished Concrete. (Equipment: Various hand and power tools).
    • Install Level 1 Kitchenette Backsplash. (Equipment: Various hand and power tools).
    • Install Level 1Gender Neutral Restroom. (Equipment: Various hand and power tools).
    • Continue North Road Vault work. (Equipment: Various hand and power tools).
    • Form Stair #3 Steps & Strip sidewalk at Southwest of Webber. (Equipment: Various hand and power tools).
    • Place Southwest Architectural Stairs & Topping Slab
      • Please be advised on Saturday 7/1/23 we will be placing concrete. Anticipated timeline 6 AM – 12 PM. Please reference UCR EDII Concrete Truck Staging and Haul Route exhibit outlining haul routes and staging areas for the concrete trucks

    Anticipated disturbances: Medium-level construction noise on Building Site.

     

     

    Chemistry Building:

    • Install no access/redirection signs inside the Chemistry Building. (Equipment: Various hand and power tools).

    Anticipated disturbances: Medium-level construction noise on Building Site.

     

     

    Please be advised that the following activities will be occurring from 5:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas during the week of July 03rd through July 08th. The activities will occur within the areas identified in the attached exhibits and as shown in the map below.  

     

    Building Site:

     

    • Continue Interior build-out & punch items. (Equipment: Various hand and power tools).
    • Continue Site Hardscape Concrete Placement. (Equipment: Various hand and power tools).
      • Pour Southwest Ramp (Equipment: Various hand and power tools).
        • Please be advised on Monday 7/3/23 we will be placing concrete. Anticipated timeline 6 AM – 12 PM. Please reference UCR EDII Concrete Truck Staging and Haul Route exhibit outlining haul routes and staging areas for the concrete trucks
    • Continue Exterior & Roof punch items. (Equipment: Various hand and power tools).
    • Continue MEP activities on Levels 1-5.  (Equipment: Various hand and power tools).
    • Continue Exterior BOK Modern Panel Installation (Equipment: Various hand and power tools).
    • Brick Installation at West Trash Enclosure & Stair 3 (Equipment: Various hand and power tools).
    • Continue Handrail & Guardrail installation. (Equipment: Various hand and power tools)
    • Anticipated disturbances: Medium-level construction noise on Building Site.

     

     Chemistry Building:

    • Demolition & Place New Concrete Sidewalk. (Equipment: Various hand and power tools).
      • Please be advised on Friday 7/6 there will be no access at the entrance & exit door South of the Chemistry building.
    • Begin Landscaping Additional Planting Areas at South of the Chemistry Building. (Equipment: Various hand and power tools).
    • Anticipated disturbances: Medium-level construction noise

     

    West connector courtyard (South of Webber):

    • Continue grading at South of Webber. (Equipment: Various hand and power tools).
    • Pour Concrete Sidewalk South of Webber for Placement 2. (Equipment: Various hand and power tools).

    Anticipated disturbances: Medium-level construction noise

     

    New Generator Yard: 

    • Pedestrian access to the North doors of Headhouses #7-10 will remain open.
    • Place Oak Grove Ramp. (Equipment: Various hand and power tools).
      • Please be advised on Thursday 7/6 we will be placing concrete. Anticipated timeline 6 AM – 12 PM. Please reference UCR EDII Concrete Truck Staging and Haul Route exhibit outlining haul routes and staging areas for the concrete trucks

    ·         Anticipated disturbances: Medium level construction noise contained in the surrounding area.

     

    Headhouse 7: 

    • No activities are scheduled for the Headhouse. (Equipment: Various hand tools).
    • Anticipated disturbances: Low level construction noise contained to surrounding area.  

     

    SOM ED I Existing Electrical Yard (South): 

    • No activities scheduled for the SOM ED I Generator Yard.  
    • Pedestrian access to surrounding buildings will remain open. 
    • Anticipated disturbances: Low level construction noise contained to SOM EDI Electrical Yard. 

     

     West Courtyard: 

    • Please be advised that the West Courtyard and the new temporary loading dock in this area are open at all other times and ready to support activities until project completion.  

     

    Parking Lot 11:  

    • Activities and access to loading docks will not be affected.  
    • Please be advised that the Parking Lot 11 existing access will be the new access road for deliveries into the West Courtyard Temporary Loading Dock. Please reference construction Alerts from Batchelor hall renovations for further access and activities considerations.

     

    Construction Trailer Area at Parking Lot 10: 

    • Continue material deliveries to trailer lot (Equipment: delivery truck).  
    • Anticipated disturbances: Low level construction noise at Lot 10.   
    • Please be advised that the eastern most row of parking spots in Lot 10 will no longer be available for the duration of the SOM ED II project (summer 2023), as this will be impacted by the construction trailers area. 

     

    Parking Lot 41 Laydown Area: 

    • Material deliveries (Equipment: delivery trucks, and various hand tools).  
    • Pedestrian access to GH/HH #11-14 and surrounding buildings will remain open. 
    • Activities and access to loading docks will not be affected.  
    • Anticipated disturbances: Low level construction noise at Lot 41.  

     

    Items listed in red: Please note that this activity may potentially disrupt the pedestrian and/or vehicular pathways and the occupants in adjacent buildings.      

     

    Continuous noises on site: Delivery trucks, construction equipment (back-up alarms), jackhammers, saws, screw guns, and hammers.

  • 954045 SOM ED II - Construction Alert #106

    06/24/2023-07/01/2023

     

    954045 SOM ED II Construction Alert #106

     

    Please be advised that the following activities will be occurring from 6:00AM to 2:30PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas on Saturday, June 24th

     

    Saturday, June 24th

     

    Building Site:

    • Polish & Sealing Concrete Floor on Level . (Equipment: Various hand and power tools).
    • Install Grand Stair Threads & Handrails. (Equipment: Various hand and power tools).
    • Install Acoustic Fabric Panels on Level 1. (Equipment: Various hand and power tools).
    • Install Elevator flooring. (Equipment: Various hand and power tools).
    • Install Kitchenette casework on level 5 & Conference casework on Level 4. (Equipment: Various hand and power tools).
    • Install Lockers. (Equipment: Various hand and power tools).
    • Hoist & Install L4 & L5 Baguettes at the East Terraces. (Equipment: Various hand and power tools).
    • Pour West Site Concrete by Stair 3. (Equipment: Various hand and power tools).
      • Please be advised on Saturday 6/24/23 we will be placing concrete. Anticipated timeline 6 AM – 12 PM. Please reference UCR EDII Concrete Truck Staging and Haul Route exhibit outlining haul routes and staging areas for the concrete trucks

     

    West connector courtyard (South of Webber):

    • Sawcut Concrete at South of Webber for placement 1. (Equipment: Various hand and power tools).

     

    Please be advised that the following activities will be occurring from 5:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas during the week of June 26th thru July 01st. The activities will occur within the areas identified in the attached exhibits and as shown in the map below.  

     

    Building Site:

     

    • Continue Interior build-out. (Equipment: Various hand and power tools).
    • Continue Exterior Air Barrier application (Equipment: Various hand and power tools).
    • Continue MEP activities on Levels 1-5.  (Equipment: Various hand and power tools).
    • Continue Exterior ACM Metal Panel Installation & Flashings (Equipment: Various hand and power tools).
    • Continue Curtain Wall Framing & Glazing at all levels. (Equipment: Various hand and power tools).
    • Brick Installation at West Trash Enclosure (Equipment: Various hand and power tools)
    • Anticipated disturbances: Medium-level construction noise on Building Site.

     

     Chemistry Building:

    • Demolition & Place New Concrete Sidewalk. (Equipment: Various hand and power tools).
      • Please be advised on Friday 6/30 there will be no access at the entrance & exit door South of the Chemistry building.
    • Begin Landscaping Additional Planting Areas at South of the Chemistry Building. (Equipment: Various hand and power tools).
    • Anticipated disturbances: Medium-level construction noise

     

    West connector courtyard (South of Webber):

    • Continue grading at South of Webber. (Equipment: Various hand and power tools).
    • Pour Concrete Sidewalk South of Webber for Placement 2. (Equipment: Various hand and power tools).
      • Please be advised on Monday 6/26 we will be placing concrete. Anticipated timeline 6 AM – 12 PM. Please reference UCR EDII Concrete Truck Staging and Haul Route exhibit outlining haul routes and staging areas for the concrete trucks.

    Anticipated disturbances: Medium-level construction noise

     

    New Generator Yard: 

    • Pedestrian access to the North doors of Headhouses #7-10 will remain open.

    ·         Anticipated disturbances: Low-level construction noise contained in the surrounding area.

     

    Headhouse 7: 

    • No activities are scheduled for the Headhouse. (Equipment: Various hand tools).
    • Anticipated disturbances: Low level construction noise contained to surrounding area.  

     

    SOM ED I Existing Electrical Yard (South): 

    • No activities scheduled for the SOM ED I Generator Yard.  
    • Pedestrian access to surrounding buildings will remain open. 
    • Anticipated disturbances: Low level construction noise contained to SOM EDI Electrical Yard. 

     

     West Courtyard: 

    • Please be advised that the West Courtyard and the new temporary loading dock in this area are open at all other times and ready to support activities until project completion.  

     

    Parking Lot 11:  

    • Activities and access to loading docks will not be affected.  
    • Please be advised that the Parking Lot 11 existing access will be the new access road for deliveries into the West Courtyard Temporary Loading Dock. Please reference construction Alerts from Batchelor hall renovations for further access and activities considerations.

     

    Construction Trailer Area at Parking Lot 10: 

    • Continue material deliveries to trailer lot (Equipment: delivery truck).  
    • Anticipated disturbances: Low level construction noise at Lot 10.   
    • Please be advised that the eastern most row of parking spots in Lot 10 will no longer be available for the duration of the SOM ED II project (summer 2023), as this will be impacted by the construction trailers area. 

     

    Parking Lot 41 Laydown Area: 

    • Material deliveries (Equipment: delivery trucks, and various hand tools).  
    • Pedestrian access to GH/HH #11-14 and surrounding buildings will remain open. 
    • Activities and access to loading docks will not be affected.  
    • Anticipated disturbances: Low level construction noise at Lot 41.  

     

    Items listed in red: Please note that this activity may potentially disrupt the pedestrian and/or vehicular pathways and the occupants in adjacent buildings.      

     

    Continuous noises on site: Delivery trucks, construction equipment (back-up alarms), jackhammers, saws, screw guns, and hammers. 

  • 954045_SOM ED 2- Potential Construction Impact- Site Utilization-3 Construction Alert for Chemical Science Faculty, Staff, & Students

    SOM ED 2 Neighborhood Community and Chemical Science Faculty, Staff and Students

     

    To provide more information to the construction notification sent last week, the construction on the SOM ED 2 building has been steadfastly moving ahead and as we move forward areas of the concrete around the Chemical Science Building were found to be non-compliant for ADA access. As such the contractor is required to do some additional site work in the adjacent areas to the chemical science building. This will impact some of the pedestrian access paths that you have become accustomed to, and have some sound impact during the demolition of the existing concrete. We want to send a notification out to you informing you of changes in access around Chemical Sciences and SOM ED 1, we will work with the contractor to maintain access to the adjacent buildings, and chemical sciences.  Alternative paths as identified below have been designated so that there is access to the buildings.

     

    Chemical Sciences Building- Alternate Pedestrian Paths

    School of Medicine Education Building 01- Alternate Pedestrian Paths

     

    Please see attached revised fencing layout. We would like to begin these activities at the end of this week. This revised fencing layout will remain in effect till July 19th.  Please see below exhibit of fencing with access/ egress pathways identified, this revised fencing will impact Chemical Sciences. We understand that construction activities can be disruptive and pose inconveniences. In an effort to minimize disruptions and being mindful of the access you have become accustomed to since construction has begun, we want to send out an advance notification and plan for any potential challenges that you may foresee.

  • 954045 SOM ED II - Construction Alert #105

    06/17/2023-06/24/2023

     

    954045 SOM ED II Construction Alert #105

     

    Please be advised that the following activities will be occurring from 6:00AM to 2:30PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas on Saturday, June 17th

    Saturday, June 10th

     

    Saturday, June 17th

     

    Building Site:

    • GFRG Mural wall Insulation
    • L3-L5 Casework, L3-L5 Furniture, Stair 5 & 6 Railing, Grand Stair Railing Installation
    • N. Rd. Sewer
    • Stair 2 Formwork Installation
    • Sitework Clean up
    • Sawcut Concrete Area 4
    • L1 Prefunction Area Ceiling Cleanup, Interior Building Clean L1 and L2
    • Gender Neutral Flooring & Backsplash installation
    • L1 Final Painting
    • L2 Wood Slats; L3-L5 Misc. Tiles, L3 Fire Shutter Doors Installation

     

    Please be advised that the following activities will be occurring from 5:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas during the week of June 19th thru June 24th. The activities will occur within the areas identified in the attached exhibits and as shown in the map below.  

     

    Building Site:

     

    • Pour North Site Hardscape Near SOM EDI. (Equipment: Various hand and power tools).
      • Please be advised on Tuesday June 20th we will be placing concrete. Anticipated timeline 6 AM to 12 PM. Please reference UCR EDII Concrete Truck Staging and Haul Route exhibit outlining haul routes and staging areas for the concrete trucks
    • Adjust the Northeast fence line at SOM EDI. (Equipment: Various hand and power tools).
      • Please note: South East Entry from East Campus will be available for emergency access/ Egress only.
    • Load Jobsite K-Rails Delivery
      • Please be advised on Monday June 19th the loading dock will be closed from 7 am to 9 am to load K-Rails.  
    • Continue Interior build-out. (Equipment: Various hand and power tools).
    • Start Level 2 Roof paver layout. (Equipment: Various hand and power tools).
    • Continue Exterior Air Barrier application (Equipment: Various hand and power tools).
    • Continue MEP activities on Levels 1-5.  (Equipment: Various hand and power tools).
    • Continue Exterior ACM Metal Panel Installation & Flashings (Equipment: Various hand and power tools).
    • Continue Curtain Wall Framing & Glazing at all levels. (Equipment: Various hand and power tools).
    • Brick Installation at West Trash Enclosure (Equipment: Various hand and power tools)
    • Anticipated disturbances: Medium-level construction noise on Building Site.

     

    West connector courtyard (South of Webber), East Campus Drive and School of Medicine 01:

    • Continue grading at South of Webber. (Equipment: Various hand and power tools).
    • Pour Concrete Sidewalk at South of the Chemistry Building. (Equipment: Various hand and power tools).