School of Medicine Building 2

PDC Contacts

Project Manager: Mihai Gavan - 951-827-6959

Planner: Melissa Garrety - 951- 827-7376

Project Description

The University of California Riverside proposes to construct the School of Medicine (SOM) Education Building II, a new facility of approximately 57,000 assignable square feet (ASF) that will directly support the academic and programmatic mission of the UCR School of Medicine by providing adequate space for existing needs, as well as allowing for future expansion of the class size (up to 125 students per class).

The proposed building is anticipated to provide up to 57,000 assignable square feet (ASF) within approximately 90,000 gross square feet (GSF). The space program will incorporate the following types of spaces, to complement SOM's existing program:

  • instruction and instruction support spaces such as classrooms, specialized teaching spaces, and lecture halls;
  • student support and study facilities including study/lounge spaces necessary to comply with accreditation standards; and,
  • academic and administrative offices and support spaces

SOM Education Bldg 2

  • Project Details
  • Construction
  • News

Current Activity

  • Construction Documents
  • Modular Relocation
  • Logistics at Parking Lot 10 and 41
  • Electrical Infrastructure and equipment
  • Demolition of existing landscape and hardscape
  • Temporary utilities related work
  • Electrical infrastructure

 

Live Feed
Live Feed

 

 

 

Next Steps

  • Excavation and groundwork
  • Foundations

Construction Notices

  • Please be advised that the southern building entrances to Webber and Boyce Hall will be temporarily closed  between mid-July and November.
  • Please be advised that access to Greenhouse 6 and its associated Headhouse is no longer available.
  • Please be advised that vehicular access to Parking Lot 11 from Eucalyptus Dr. and various parking spots within the parking lot may be temporarily impacted.

Project Location

Project Anticipated Timeline

Project Updates

  • 954045 SOM ED II Construction Alert #17

    954045 SOM ED II Construction Alert #17

     

    Please be advised that the following activities will be occurring from 6:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas during the week of October 11th through October 17th. The activities will occur within the areas identified in the attached exhibits and as shown in the map below.

    SOM ED I Existing Electrical Yard (South):

    • Add base in yard for drainage ( Equipment: Delivery truck, skid steer, tamper hammer, various hand tools).
    • Pedestrian access to surrounding buildings will remain open.
    • Activities and access to loading docks will not be affected.
    • Anticipated disturbances: Low level construction noise contained to SOM EDI Electrical Yard.
    • Please be advised that the accessible parking stalls on the south side of the lot will be unavailable due to the backup generator and associated equipment in order to support the de-energizing of the equipment in the existing electrical yard (please see attached exhibit).

    West Courtyard:

    • Continue work for courtyard lighting (Equipment: Mini excavator, forklift, various hand tools).
    • Continue layout and excavating of miscellaneous footings and curbs (Equipment: Mini excavator, skid steer, shovels, various hand tools).
    • Begin FRP of footings and curbs (Equipment: Concrete trucks, forklift for washout, various hand tools).
    • Activities and access to loading docks will not be affected.
    • Anticipated disturbances: Medium level construction noise contained to West Courtyard.
    • Please be advised that the southern building entrances to Webber and Boyce Hall will be temporarily closed for the duration of the early construction phase of work which is anticipated between mid-July and November. Appropriate signage will be provided inside the buildings to alert the occupants.

    Greenhouse/Headhouse #6 / New Generator Yard:

    • Continue forming, rebar and placement of West pads in new generator yard (Equipment: Delivery trucks, forklift, various power tools, various hand tools).
    • Continue trenching for steam, gas and compressed air from TV23 up to headhouse 7 (Equipment: Excavator, skid steer, shovels, various hand tools).
    • Continue trenching storm drain line on the north side of headhouse 7 – 10. (Equipment: Mini excavator, skid steer, shovels, various hand tools).
    • Begin relocation of 2.5MW generator and associated equipment. Crane onsite 10/16 (Equipment: 350 ton Crane, haul trucks, various rigging equipment, traffic control.)
    • Activities and access to loading docks will not be affected.
    • Pedestrian access to the north doors of Headhouses 7-10 will remain open and protected by trench-plates.
    • Anticipated disturbances: Medium level construction noise contained to surrounding area.
    • Please be advised that access to Greenhouse #6 and its associated Headhouse is no longer available.
    • Please see attached reminder notifications from Facilities for the scheduled electrical power service interruptions anticipated for October 12th.
    • Please be advised that East Campus Drive directly East of SOM EDI will be closed on Saturday 10/16 from 4AM to 11PM to accommodate the crane operation (see attached traffic control plan).
    • Please be advised that Parking Lot 11 will be closed to parking on 10/16 and 10/17 to accommodate the crane operation. The loading dock and pedestrian access to surrounding buildings will remain open (see attached traffic control plan).

    Parking Lot 11:

    • Continue material deliveries through lot 11 down to the West courtyard (Equipment: Delivery truck).
    • Activities and access to loading docks will not be affected.
    • Anticipated disturbances: Medium level construction noise contained to surrounding area.

    SOM Modular Complex:

    • 10/11/21 – Crane and truck modules to new location (Equipment: 500 ton Crane, two low boy haul trucks, various rigging equipment, traffic control).
      • 6PM – 9PM: Crane arrives and setup begins
      • 9PM – 2AM: Truck to new location
      • 2AM – 4AM: Disassemble crane
    • Begin reassembly of modular complex at new location (Equipment: Generator, drills, hammers, various hand tools).
    • Anticipated disturbances: Medium level construction noise at Modular Complex.   
    • Please be advised that access to the Modular Building is no longer available.
    • Please be advised that access to the Dock 17 parking area (Boyce and SOM plaza) will be intermittently impacted on 10/11-10/12 from 6PM-4AM.

    Construction Trailer Area at Parking Lot 10:

    • Continue installation of trailer deck (Equipment: Saws, generator, drills, hammers, various hand tools).
    • Anticipated disturbances: Medium level construction noise at Lot 10.  
    • Please be advised that the eastern most row of parking spots in Lot 10 will be no longer available for the duration of the SOM ED II project (summer 2023), as this will be impacted by the construction trailers area.

    Parking Lot 41 Laydown Area:

    • Material deliveries (Equipment: Delivery trucks, and various hand tools).
    • Pedestrian access to GH/HH #11-14 and surrounding buildings will remain open.
    • Activities and access to loading docks will not be affected.
    • Anticipated disturbances: Low level construction noise at Lot 41.

    Items listed in red: Please note that this activity may potentially disrupt the pedestrian and/or vehicular pathways and the occupants in adjacent buildings.     

    Continuous noises on site: Delivery trucks (back-up alarms), saws, screw guns, and hammers.

    The School of Medicine Education II Building Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.

  • 954045 SOM ED II Construction Alert #16

    954045 SOM ED II Construction Alert #16

    Please be advised that the following activities will be occurring from 6:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas during the week of October 4th through October 9th. The activities will occur within the areas identified in the attached exhibits and as shown in the map below.

    SOM ED I Existing Electrical Yard (South):

    • Add base in yard for drainage ( Equipment: Delivery truck, skid steer, tamper hammer, various hand tools).
    • Pedestrian access to surrounding buildings will remain open.
    • Activities and access to loading docks will not be affected.
    • Anticipated disturbances: Low level construction noise contained to SOM EDI Electrical Yard.
    • Please be advised that the accessible parking stalls on the south side of the lot will be unavailable due to the backup generator and associated equipment in order to support the de-energizing of the equipment in the existing electrical yard (please see attached exhibit).

    West Courtyard:

    • Soil export and fine grade of courtyard (Equipment: Haul trucks, dozer, skip loader, skid steer).
    • Continue trenching for underground storm drain (Equipment: Mini excavator, skid steer, shovels, various hand tools).
    • Activities and access to loading docks will not be affected.
    • Anticipated disturbances: Medium level construction noise contained to West Courtyard.
    • Please be advised that the southern building entrances to Webber and Boyce Hall will be temporarily closed for the duration of the early construction phase of work which is anticipated between mid-July and November. Appropriate signage will be provided inside the buildings to alert the occupants.

    Greenhouse/Headhouse #6 / New Generator Yard:

    • Begin forming, rebar and placement of West pads in new generator yard (Equipment: Delivery trucks, forklift, various power tools, various hand tools).
    • Begin trenching for gas and steam from TV23 up to headhouse 7 (Equipment: Excavator, skid steer, shovels, various hand tools).
    • Activities and access to loading docks will not be affected.
    • Pedestrian access to the north doors of Headhouses 7-10 will remain open and protected by trench-plates.
    • Anticipated disturbances: Medium level construction noise contained to surrounding area.
    • Please be advised that access to Greenhouse #6 and its associated Headhouse is no longer available.
    • Please see attached notifications from Facilities for the scheduled electrical power service interruptions anticipated for October 12th.

    Parking Lot 11:

    • Continue material deliveries through lot 11 down to the west courtyard (Equipment: Delivery truck).
    • Activities and access to loading docks will not be affected.
    • Anticipated disturbances: Medium level construction noise contained to surrounding area.

    SOM Modular Complex:

    • Begin separation of modular complex (Equipment: Saws, generator, drills, hammers, various hand tools).
    • Anticipated disturbances: Medium level construction noise at Modular Complex.   
    • Please be advised that access to the Modular Building is no longer available.

    Construction Trailer Area at Parking Lot 10:

    • Continue installation of trailer deck (Equipment: Saws, generator, drills, hammers, various hand tools).
    • Anticipated disturbances: Medium level construction noise at Lot 10.  
    • Please be advised that the eastern most row of parking spots in Lot 10 will be no longer available for the duration of the SOM ED II project (summer 2023), as this will be impacted by the construction trailers area.

    Parking Lot 41 Laydown Area:

    • Material deliveries (Equipment: Delivery trucks, and various hand tools).
    • Pedestrian access to GH/HH #11-14 and surrounding buildings will remain open.
    • Activities and access to loading docks will not be affected.
    • Anticipated disturbances: Low level construction noise at Lot 41.

    Items listed in red: Please note that this activity may potentially disrupt the pedestrian and/or vehicular pathways and the occupants in adjacent buildings.     

    Continuous noises on site: Delivery trucks (back-up alarms), saws, screw guns, and hammers.

    The School of Medicine Education II Building Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.

  • 954045 SOM ED II Construction Alert #15

    Please be advised that the following activities will be occurring from 6:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas during the week of September 27th through October 2nd. The activities will occur within the areas identified in the attached exhibits and as shown in the map below.

    SOM ED I Existing Electrical Yard (South):

    • Begin enclosure layout ( Equipment: Survey tools).
    • Pedestrian access to surrounding buildings will remain open.
    • Activities and access to loading docks will not be affected.
    • Anticipated disturbances: Low level construction noise contained to SOM EDI Electrical Yard.
    • Please be advised that the accessible parking stalls on the south side of the lot will be unavailable due to the backup generator and associated equipment in order to support the de-energizing of the equipment in the existing electrical yard (please see attached exhibit).

    West Courtyard:

    • Continue trenching for underground electrical (Equipment: Excavator, skid steer, shovels, various hand tools).
    • Continue trenching for underground storm drain (Equipment: Mini excavator, skid steer, shovels, various hand tools).
    • Continue installing underground electrical conduit (Equipment: Mini excavator, skid steer, shovels, various hand tools).
    • Activities and access to loading docks will not be affected.
    • Anticipated disturbances: Medium level construction noise contained to West Courtyard.
    • Please be advised that the southern building entrances to Webber and Boyce Hall will be temporarily closed for the duration of the early construction phase of work which is anticipated between mid-July and November. Appropriate signage will be provided inside the buildings to alert the occupants.

    Greenhouse/Headhouse #6 / New Generator Yard:

    • Continue backfill and compaction of electrical duct bank trenches (Equipment: Excavator, backhoe, whacker, shovels, various hand tools).
    • Continue forming, rebar and placement of new generator yard pads (Equipment: Delivery trucks, forklift, various power tools, various hand tools).
    • Continue trenching on the north side of headhouse 7 – 10 (Equipment: Mini excavator, skid steer, shovels, various hand tools).
    • Activities and access to loading docks will not be affected.
    • Pedestrian access to the north doors of Headhouses 7-10 will remain open and protected by trench-plates.
    • Anticipated disturbances: Medium level construction noise contained to surrounding area.
    • Please be advised that access to Greenhouse #6 and its associated Headhouse is no longer available.
    • Please see attached notifications from Facilities for the potential and scheduled electrical power service interruptions anticipated for September 21st and 22nd.

    Parking Lot 11:

    • Continue material deliveries through lot 11 down to the west courtyard (Equipment: Delivery truck).
    • Activities and access to loading docks will not be affected.
    • Anticipated disturbances: Medium level construction noise contained to surrounding area.

    Construction Trailer Area at Parking Lot 10:

    • Continue installation of trailer deck (Equipment: Saws, generator, drills, hammers, various hand tools).
    • Anticipated disturbances: Medium level construction noise at Lot 10.  
    • Please be advised that the eastern most row of parking spots in Lot 10 will be no longer available for the duration of the SOM ED II project (summer 2023), as this will be impacted by the construction trailers area.

    SOM Modular Complex:

    • Begin demolition of flatwork around modular building (Equipment: Mini excavator, skid steer, concrete saw, various hand tools).
    • Anticipated disturbances: Medium level construction noise at Modular Complex.   
    • Please be advised that access to the Modular Building is no longer available.

    Parking Lot 41 Laydown Area:

    • Material deliveries (Equipment: Delivery trucks, and various hand tools);
    • Pedestrian access to GH/HH #11-14 and surrounding buildings will remain open.
    • Activities and access to loading docks will not be affected.
    • Anticipated disturbances: Low level construction noise at Lot 41.

    Items listed in red: Please note that this activity may potentially disrupt the pedestrian and/or vehicular pathways and the occupants in adjacent buildings.     

    The School of Medicine Education II Building Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.

  • 954045 SOM ED II Construction Alert #14

    954045 SOM ED II Construction Alert #14

    Please be advised that the following activities will be occurring from 6:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas on Saturday, September 18th.

    Greenhouse/Headhouse #6 / New Generator Yard:

    • Continue backfill and prep for concrete pads at New Generator Yard (Equipment: Excavator, skid steer, various hand tools).

    Please be advised that the following activities will be occurring from 6:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas during the week of September 20th through September 25th. The activities will occur within the areas identified in the attached exhibits and as shown in the map below.

    SOM ED I Existing Electrical Yard (South):

    • Begin enclosure layout ( Equipment: Survey tools).
    • Pedestrian access to surrounding buildings will remain open.
    • Activities and access to loading docks will not be affected.
    • Anticipated disturbances: Low level construction noise contained to SOM EDI Electrical Yard.
    • Please be advised the accessible parking stalls on the south side of the lot will be unavailable due to the backup generator and associated equipment in order to support the de-energizing of the equipment in the existing electrical yard (please see second attached exhibit to this email).

    West Courtyard:

    • Continue trenching for underground electrical (Equipment: Excavator, skid steer, shovels, various hand tools).
    • Continue trenching for underground storm drain (Equipment: Mini excavator, skid steer, shovels, various hand tools).
    • Continue installing underground electrical conduit (Equipment: Mini excavator, skid steer, shovels, various hand tools).
    • Activities and access to loading docks will not be affected.
    • Anticipated disturbances: Medium level construction noise contained to West Courtyard.
    • Please be advised that the southern building entrances to Webber and Boyce Hall will be temporarily closed for the duration of the early construction phase of work which is anticipated between mid-July and November. Appropriate signage will be provided inside the buildings to alert the occupants.

    Greenhouse/Headhouse #6 / New Generator Yard:

    • Begin forming, rebar and placement of new generator yard pads (Equipment: Delivery trucks, forklift, various power tools, various hand tools).
    • Activities and access to loading docks will not be affected.
    • Begin trenching on the north side of headhouse 7 – 10. (Equipment: Mini excavator, skid steer, shovels, various hand tools).
    • Pedestrian access to the north doors of Headhouses 7-10 will remain open and protected by trench-plates.
    • Anticipated disturbances: Medium level construction noise contained to surrounding area.
    • Please be advised that access to Greenhouse #6 and its associated Headhouse is no longer available.
    • Please see attached notifications from Facilities for the potential and scheduled electrical power service interruptions anticipated for September 21st and 22nd.

    Parking Lot 11:

    • Remove fence around parking stalls (Equipment: Delivery truck, various hand tools).
    • Activities and access to loading docks will not be affected.
    • Anticipated disturbances: Medium level construction noise contained to surrounding area.
    • Please be advised that portions of Parking Lot 11 may be temporarily unavailable – please see attached exhibits.  

    Parking Lot 10 and Co-Location Trailer Area:

    • Continue forming, rebar and placement of sidewalk (Equipment: Concrete truck, various hand and power tools).
    • Begin asphalt and base (Equipment: Haul trucks, roller, water truck, skid steer, various hand tools).
    • Continue installation of trailer deck (Equipment: Saws, generator, drills, hammers, various hand tools)
    • Anticipated disturbances: Medium level construction noise at Lot 10.  
    • Please be advised that the eastern most row of parking spots in Lot 10 will be no longer available for the duration of the SOM ED II project (summer 2023), as this will be impacted by the construction trailers area.
    • Please be advised that Parking Lot 10 will be temporarily unavailable between September 20th – September 25th.

    Parking Lot 41 Laydown Area:

    • Material deliveries (Equipment: Delivery trucks, and various hand tools);
    • Pedestrian access to GH/HH #11-14 and surrounding buildings will remain open.
    • Activities and access to loading docks will not be affected.
    • Anticipated disturbances: Low level construction noise at Lot 41.

    Items listed in red: Please note that this activity may potentially disrupt the pedestrian and/or vehicular pathways and the occupants in adjacent buildings.     

    Continuous noises on site: Delivery trucks (back-up alarms), saws, screw guns, and hammers.

    The School of Medicine Education II Building Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.

  • 954045 SOM ED II - Construction Alert #13

    954045 SOM ED II Construction Alert #13

    Please be advised that the following activities will be occurring from 6:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas during the week of September 13th through September 18th. The activities will occur within the areas identified in the attached exhibits and as shown in the map below.

    SOM ED I Existing Electrical Yard (South):

    • Finalize connection and commissioning of 500kW generator (Equipment: Power tools, various hand tools).
    • Pedestrian access to surrounding buildings will remain open.
    • Activities and access to loading docks will be affected.
    • Anticipated disturbances: Low level construction noise contained to SOM EDI Electrical Yard.

    West Courtyard:

    • Continue trenching for underground electrical (Equipment: Excavator, skid steer, shovels, various hand tools).
    • Continue trenching for underground storm drain (Equipment: Mini excavator, skid steer, shovels, various hand tools).
    • Continue work for underground electrical (Equipment: Mini excavator, skid steer, shovels, various hand tools).
    • Activities and access to loading docks will not be affected.
    • Anticipated disturbances: Medium level construction noise contained to West Courtyard and SOM Modular complex.
    • Please be advised that the southern building entrances to Webber and Boyce Hall will be temporarily closed for the duration of the early construction phase of work which is anticipated between mid-July and November. Appropriate signage will be provided inside the buildings to alert the occupants.

    Greenhouse/Headhouse #6 / New Generator Yard:

    • Continue excavating vaults and installing conduit (Equipment: Mini excavator, skid steer, shovels, various hand tools).
    • Continue interior build out of headhouse (Equipment: Delivery trucks, hand power tools, various hand tools).
    • Continue backfill of trenches (Equipment: Excavator, skid steer, various hand tools).
    • Begin forming and installing rebar of new generator yard pads (Equipment: Delivery trucks, forklift, various power tools, various hand tools).
    • Activities and access to loading docks will not be affected.
    • Anticipated disturbances: Medium level construction noise contained to surrounding area.
    • Please be advised that access to Greenhouse #6 and its associated Headhouse is no longer available.

    Parking Lot 11:

    • Continue trenching and rough in of conduit at planter south of Eucalyptus (Equipment: Mini excavator, skid steer, various hand tools).
    • Activities and access to loading docks will not be affected.
    • Anticipated disturbances: Medium level construction noise contained to surrounding area.
    • Please be advised that portions of Parking Lot 11 will be temporarily unavailable – please see attached exhibits.  

    Parking Lot 10 and Co-Location Trailer Area:

    • Hot tap domestic water line (Equipment: Mini excavator, concrete / asphalt saw, shovel, various hand tools).
    • Begin FRP of curb and sidewalk in Lot 10 (Equipment: Skid steer, tamper hammer, various small grading equipment).
    • Begin demolition of asphalt in lot 10 (Equipment: Haul trucks, excavator, water truck, skid steer, various hand tools).
    • Grading, base and asphalt at Lot 10 ( Equipment: Haul trucks, excavators, loader, asphalt trucks, roller, various hand tools);
    • Continue installation of trailer deck (Equipment: Saws, generator, drills, hammers, various hand tools).
    • Anticipated disturbances: Medium level construction noise at Lot 10.  
    • Please be advised that the eastern most row of parking spots in Lot 10 will be no longer available for the duration of the SOM ED II project (summer 2023), as this will be impacted by the construction trailers area.
    • Please be advised that Parking Lot 10 will be temporarily unavailable between September 13th – September 18th.

    Parking Lot 41 Laydown Area:

    • Material deliveries (Equipment: Delivery trucks, and various hand tools);
    • Pedestrian access to GH/HH #11-14 and surrounding buildings will remain open.
    • Activities and access to loading docks will not be affected.
    • Anticipated disturbances: Low level construction noise at Lot 41.

    Items listed in red: Please note that this activity may potentially disrupt the pedestrian and/or vehicular pathways and the occupants in adjacent buildings.     

    Continuous noises on site: Delivery trucks (back-up alarms), saws, screw guns, and hammers.

    The School of Medicine Education II Building Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.

  • 954045 SOM ED II Construction Alert #12

    954045 SOM ED II Construction Alert #12

    Please be advised that the following activities will be occurring from 6:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas during the week of September 7th through September 11th. The activities will occur within the areas identified in the attached exhibits and as shown in the map below.

    SOM ED I Existing Electrical Yard (South):

    • Connect temporary generator in preparation for the existing 500kW generator relocation (Equipment: Delivery truck, various hand tools).
    • Relocate and reconnect 500kW generator (Equipment: Crane, various rigging equipment, various hand tools).
    • Pedestrian access to surrounding buildings will remain open.
    • Activities and access to loading docks will be affected.
    • Anticipated disturbances: Medium level construction noise contained to SOM EDI Electrical Yard.
    • Please be advised the SOM Modular Building Parking Lot will be temporarily unavailable between September 7th – September 9th – please see attached exhibits.
    • Please be advised that vehicular access to the Boyce Hall/SOM ED loading dock and adjacent parking areas will be intermittently inaccessible for up to 2 hours on Wednesday September 8th due to construction crane activities – please see attached exhibits.

    West Courtyard:

    • Backfill of trench for underground electrical (Equipment: Mini excavator, skid steer, shovels, various hand tools).
    • Continue trenching for underground storm drain (Equipment: Mini excavator, skid steer, shovels, various hand tools).
    • Continue work for underground electrical (Equipment: Mini excavator, skid steer, shovels, various hand tools).
    • Activities and access to loading docks will not be affected.
    • Anticipated disturbances: Medium level construction noise contained to West Courtyard and SOM Modular complex.
    • Please be advised that the southern building entrances to Webber and Boyce Hall will be temporarily closed for the duration of the early construction phase of work which is anticipated between mid-July and November. Appropriate signage will be provided inside the buildings to alert the occupants.

    Greenhouse/Headhouse #6 / New Generator Yard:

    • Continue excavating vaults and installing conduit (Equipment: Mini excavator, skid steer, shovels, various hand tools).
    • Continue interior build out of headhouse (Equipment: Delivery trucks, hand power tools, various hand tools).
    • Activities and access to loading docks will not be affected.
    • Anticipated disturbances: Medium level construction noise contained to surrounding area.
    • Please be advised that access to Greenhouse #6 and its associated Headhouse is no longer available.

    Parking Lot 11:

    • Begin trenching and rough in of conduit at planter south of Eucalyptus (Equipment: Mini excavator, skid steer, various hand tools).
    • Activities and access to loading docks will not be affected.
    • Anticipated disturbances: Medium level construction noise contained to surrounding area.
    • Please be advised that vehicular access to Parking Lot 11 from Eucalyptus Dr. and various parking spots within the parking lot may be temporarily impacted – please see attached exhibits.
    • Please be advised that portions of Parking Lot 11 will be temporarily unavailable – please see attached exhibits.  

    Parking Lot 10 and Co-Location Trailer Area:

    • Continue work for trailer utility hook ups (Equipment: Material deliveries, ladders, shovels, and various hand tools).
    • Hot tap domestic water line (Equipment: Mini excavator, concrete / asphalt saw, shovel, various hand tools).
    • Begin FRP of curb and sidewalk in Lot 10 (Equipment: Skid steer, tamper hammer, various small grading equipment).
    • Anticipated disturbances: Medium level construction noise at Lot 10.  
    • Please be advised that the eastern most row of parking spots in Lot 10 will be no longer available for the duration of the SOM ED II project (summer 2023), as this will be impacted by the construction trailers area.
    • Please be advised that the middle aisles from Parking Lot 10 will be temporarily unavailable in order to complete the accessibility improvements within the lot – please see attached exhibits.
    • Please be advised that Parking Lot 10 will be temporarily unavailable between September 13th – September 18th.

    Parking Lot 41 Laydown Area:

    • Material deliveries (Equipment: Delivery trucks, and various hand tools);
    • Pedestrian access to GH/HH #11-14 and surrounding buildings will remain open.
    • Activities and access to loading docks will not be affected.
    • Anticipated disturbances: Low level construction noise at Lot 41.

    Items listed in red: Please note that this activity may potentially disrupt the pedestrian and/or vehicular pathways and the occupants in adjacent buildings.     

    Continuous noises on site: Delivery trucks (back-up alarms), saws, screw guns, and hammers.

    The School of Medicine Education II Building Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.

  • 954045 SOM ED II Construction Alert #11

    954045 SOM ED II Construction Alert #11

    Please be advised that the following activities will be occurring from 6:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II), School of Medicine Education Building (SOM ED I) and adjacent areas during the week of August 30th through September 3rd. The activities will occur within the areas identified in the attached exhibits and as shown in the map below.

    SOM ED I Ground Floor Tenant Improvements:

    • Start UCR Move in.
    • Pedestrian access to surrounding buildings will remain open.
    • Activities and access to loading docks will not be affected.
    • Anticipated disturbances: Low level construction noise contained to Simulation rooms, Control rooms, and Exam rooms as indicated in the attached exhibit.

    SOM ED I Existing Electrical Yard (South):

    • Place concrete for new generator pads (Equipment: Concrete truck, concrete vibrator, various concrete hand tools).
    • Deliver temporary generator in preparation for the existing 500kW generator relocation (Equipment: Delivery , various hand tools).
    • Pedestrian access to surrounding buildings will remain open.
    • Activities and access to loading docks will not be affected.
    • Anticipated disturbances: Medium level construction noise contained to SOM EDI Electrical Yard.

    West Courtyard:

    • Begin trenching for underground electrical (Equipment: Mini excavator, skid steer, shovels, various hand tools).
    • Continue trenching for underground storm drain (Equipment: Mini excavator, skid steer, shovels, various hand tools).
    • Existing duct bank abatement begins 9/1/21.
    • Activities and access to loading docks will not be affected.
    • Anticipated disturbances: Medium level construction noise contained to West Courtyard and SOM Modular complex.
    • Please be advised that the southern building entrances to Webber and Boyce Hall will be temporarily closed for the duration of the early construction phase of work which is anticipated between mid-July and November. Appropriate signage will be provided inside the buildings to alert the occupants.

    Greenhouse/Headhouse #6 / New Generator Yard:

    • Begin excavating vaults and installing conduit (Equipment: Mini excavator, skid steer, shovels, various hand tools).
    • Begin interior build out of headhouse (Equipment: Delivery trucks, hand power tools, various hand tools).
    • Activities and access to loading docks will not be affected.
    • Anticipated disturbances: Medium level construction noise contained to surrounding area.
    • Please be advised that access to Greenhouse #6 and its associated Headhouse is no longer available.

    Lot 11 and Eucalyptus Drive:

    • Begin re-striping of trenched area (Equipment: Paint truck, various hand tools).
    • Begin trenching and rough in of conduit at planter south of Eucalyptus (Equipment: Mini excavator, skid steer, various hand tools).
    • Activities and access to loading docks will not be affected.
    • Anticipated disturbances: Medium level construction noise contained to surrounding area.
    • Please be advised that vehicular access to Parking Lot 11 from Eucalyptus Dr. and various parking spots within the parking lot may be temporarily impacted – please see attached exhibits.
    • Please be advised that portions of Parking Lot 11 will be temporarily unavailable – please see attached exhibits.  

    Parking Lot 10 and Co-Location Trailer Area:

    • Continue trailer delivery and setup. (Equipment: Delivery truck, air compressors, pneumatic tools, ladders & various hand tools).
    • Continue work for trailer utility hook ups (Equipment: Material deliveries, ladders, shovels, and various hand tools).
    • Hot tap domestic water line (Equipment: Mini excavator, concrete / asphalt saw, shovel, various hand tools).
    • Begin rough grade of lot 10 (Equipment: Skid steer, tamper hammer, various small grading equipment).
    • Anticipated disturbances: Medium level construction noise at Lot 10.  
    • Please be advised that the eastern most row of parking spots in Lot 10 will be no longer available for the duration of the SOM ED II project (summer 2023), as this will be impacted by the construction trailers area.
    • Please be advised that the middle aisles from Parking Lot 10 will be temporarily unavailable in order to complete the accessibility improvements within the lot – please see attached exhibits.

    Parking Lot 41 Laydown Area:

    • Material deliveries (Equipment: Delivery trucks, and various hand tools);
    • Pedestrian access to GH/HH #11-14 and surrounding buildings will remain open.
    • Activities and access to loading docks will not be affected.
    • Anticipated disturbances: Low level construction noise at Lot 41.

    Items listed in red: Please note that this activity may potentially disrupt the pedestrian and/or vehicular pathways and the occupants in adjacent buildings.     

    Continuous noises on site: Delivery trucks (back-up alarms), saws, screw guns, and hammers.

     

    The School of Medicine Education II Building Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.

     

  • 954045 SOM ED II Construction Alert #10

    954045 SOM ED II Construction Alert #10

    Please be advised that the following activities will be occurring from 6:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas on Saturday, August 21st:

    West Courtyard:

    • Continue demolition of West Courtyard section and GH 6 (Equipment: excavator w/ breaker, sledgehammers, shovels, and various hand tools).
    • Anticipated disturbances: Medium-high level construction noise contained to West Courtyard and SOM Modular complex.

    SOM EDI Electrical Yard:

    • Clean up at yard in preparation of the grading activity (Equipment: Service truck, skid steer, shovels, brooms and various hand tools).
    • Anticipated disturbances: Low level construction noise at SOM EDI electrical yard.

    Please be advised that the following activities will be occurring from 6:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II), School of Medicine Education Building (SOM ED I) and adjacent areas during the week of August 23rd  through August 28th. The activities will occur within the areas identified in the attached exhibits and as shown in the map below.

    SOM ED I Ground Floor Tenant Improvements:

    • Begin installing room signage (Equipment: Various hand tools).
    • Modify corridor door swing (Equipment: delivery truck, power tools, various hand tools).
    • Continue punchlist and repairs (Equipment: Various hand tools).
    • Pedestrian access to surrounding buildings will remain open.
    • Activities and access to loading docks will not be affected.
    • Anticipated disturbances: Low level construction noise contained to Simulation rooms, Control rooms, and Exam rooms as indicated in the attached exhibit.

    SOM ED I Existing Electrical Yard (South):

    • Begin rough grade (Equipment: Skid steer, tamper hammer, various small grading equipment).
    • Begin excavating and installing conduit (Equipment: Mini excavator, skid steer, shovels, various hand tools).
    • Pedestrian access to surrounding buildings will remain open.
    • Activities and access to loading docks will not be affected.
    • Anticipated disturbances: Low level construction noise contained to SOM EDI Electrical Yard.

    West Courtyard:

    • Begin rough grade of courtyard (Equipment: delivery trucks, mini-excavator, loader, skid-steer, shovels, rakes, various hand tools).
    • Begin trenching for underground electrical (Equipment: Mini excavator, skid steer, shovels, various hand tools).
    • Activities and access to loading docks will not be affected.
    • Anticipated disturbances: Medium level construction noise contained to West Courtyard and SOM Modular complex.
    • Please be advised that the southern building entrances to Webber and Boyce Hall will be temporarily closed for the duration of the early construction phase of work which is anticipated between mid-July and November. Appropriate signage will be provided inside the buildings to alert the occupants.

    Greenhouse/Headhouse #6 / New Generator Yard:

    • Begin rough grade of new generator yard (Equipment: Delivery trucks, mini-excavator, dozer, loader, skid-steer, shovels, rakes, various hand tools).
    • Begin excavating vaults and installing conduit (Equipment: Mini excavator, skid steer, shovels, various hand tools).
    • Begin interior build out of headhouse (Equipment: Delivery trucks, hand power tools, various hand tools).
    • Activities and access to loading docks will not be affected.
    • Anticipated disturbances: Medium level construction noise contained to surrounding area.
    • Please be advised that access to Greenhouse #6 and its associated Headhouse is no longer available.

    Lot 11 and Eucalyptus Drive:

    • Continue asphalt patch and re-striping of trenched area (Equipment: Mini excavator, roller, skid steer, haul truck, various hand tools).
    • Begin trenching and rough in of conduit at planter (Equipment: Mini excavator, skid steer, various hand tools).
    • Adjust fence line to a smaller footprint (Equipment: Delivery truck, various hand tools).
    • Activities and access to loading docks will not be affected.
    • Anticipated disturbances: Medium level construction noise contained to surrounding area.
    • Please be advised that vehicular access to Parking Lot 11 from Eucalyptus Dr. and various parking spots within the parking lot may be temporarily impacted – please see attached exhibits.
    • Please be advised that portions of Parking Lot 11 will be temporarily unavailable – please see attached exhibits.  

    Parking Lot 10 and Co-Location Trailer Area:

    • Continue trailer delivery and setup. (Equipment: Delivery truck, air compressors, pneumatic tools, ladders & various hand tools);
    • Continue work for trailer temporary power (Equipment: ladders, shovels, and various hand tools);
    • Continue trenching for temporary domestic water line (Equipment: Mini excavator, concrete / asphalt saw, shovel, various hand tools);
    • Begin rough grade of lot 10 (Equipment: Skid steer, tamper hammer, various small grading equipment).
    • Anticipated disturbances: Medium level construction noise at Lot 10.  
    • Please be advised that the eastern most row of parking spots in Lot 10 will be no longer available for the duration of the SOM ED II project (summer 2023), as this will be impacted by the construction trailers area.
    • Please be advised that the middle aisles from Parking Lot 10 will be temporarily unavailable in order to complete the accessibility improvements within the lot – please see attached exhibits.

    Parking Lot 41 Laydown Area:

    • Material deliveries (Equipment: Delivery trucks, and various hand tools);
    • Pedestrian access to GH/HH #11-14 and surrounding buildings will remain open.
    • Activities and access to loading docks will not be affected.
    • Anticipated disturbances: Low level construction noise at Lot 41.

     

    Items listed in red: Please note that this activity may potentially disrupt the pedestrian and/or vehicular pathways and the occupants in adjacent buildings.     

     

    Continuous noises on site: Delivery trucks (back-up alarms), saws, screw guns, and hammers.

  • 954045 SOM ED II Construction Alert #9

    954045 SOM ED II Construction Alert #9

    Please be advised that the following activities will be occurring from 6:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas on Saturday, August 14th:

    West Courtyard:

    • Continue demolition of retaining wall and stairs to GH/HH #6 (Equipment: excavator w/ breaker, sledgehammers, shovels, and various hand tools);
    • Anticipated disturbances: Medium-high level construction noise contained to West Courtyard and SOM Modular complex.

    SOM EDI Electrical Yard:

    • Clean up at yard in preparation of the grading activity (Equipment: Service truck, skid steer, shovels, brooms and various hand tools);
    • Anticipated disturbances: Low level construction noise at SOM EDI electrical yard.

    Please be advised that the following activities will be occurring from 6:00AM to 5:00PM on the School of Medicine Education Building II Site (SOM ED II), School of Medicine Education Building (SOM ED I) and adjacent areas during the week of August 16th through August 21st. The activities will occur within the areas identified in the attached exhibits and as shown in the map below.

    SOM ED I Ground Floor Tenant Improvements:

    • Modify corridor door swing (Equipment: delivery truck, power tools, various hand tools);
    • Begin installing room signage (Equipment: Various hand tools);
    • Pedestrian access to surrounding buildings will remain open.
    • Activities and access to loading docks will not be affected.
    • Anticipated disturbances: Low level construction noise contained to Simulation rooms, Control rooms, and Exam rooms as indicated in the attached exhibit.

    SOM ED I Existing Electrical Yard (South):

    • Continue demo of enclosure and landscaping (Equipment: Skid steer, various hand and power tools);
    • Begin rough grade (Equipment: Skid steer, tamper hammer, various small grading equipment);
    • Begin excavating and installing conduit (Equipment: Mini excavator, skid steer, shovels, various hand tools).
    • Pedestrian access to surrounding buildings will remain open.
    • Activities and access to loading docks will not be affected.
    • Anticipated disturbances: Low level construction noise contained to SOM EDI Electrical Yard.

    West Courtyard:

    • Continue demolition of retaining wall and stairs to GH/HH #6 (Equipment: excavator w/ breaker, sledgehammers, shovels, and various hand tools);
    • Mobilize for rough grade of courtyard (Equipment: delivery trucks, mini-excavator, loader, skid-steer, shovels, rakes, various hand tools).
    • Activities and access to loading docks will not be affected.
    • Anticipated disturbances: Medium-high level construction noise contained to West Courtyard and SOM Modular complex.
    • Please be advised that the southern building entrances to Webber and Boyce Hall will be temporarily closed for the duration of the early construction phase of work which is anticipated between mid-July and November. Appropriate signage will be provided inside the buildings to alert the occupants.

    Greenhouse/Headhouse #6 / New Generator Yard:

    • Continue demolition of retaining wall and stairs to GH/HH #6 (Equipment: excavator, sledgehammers, shovels, and various hand tools);
    • Mobilize for rough grade of courtyard (Equipment: Delivery trucks, mini-excavator, loader, skid-steer, shovels, rakes, various hand tools);
    • Begin excavating vaults and installing conduit (Equipment: Mini excavator, skid steer, shovels, various hand tools);
    • Activities and access to loading docks will not be affected.
    • Anticipated disturbances: Medium-high level construction noise contained to surrounding area and GH/HH #6.
    • Please be advised that access to Greenhouse #6 and its associated Headhouse is no longer available.

    Lot 11 and Eucalyptus Drive:

    • Begin asphalt patch and re-striping of trenched area (Equipment: Mini excavator, roller, skid steer, haul truck, various hand tools);
    • Begin demolition of existing fence and equipment at planter (Equipment: Mini excavator, skid steer, various hand tools);
    • Activities and access to loading docks will not be affected.
    • Anticipated disturbances: Medium level construction noise contained to surrounding area.
    • Please be advised that vehicular access to Parking Lot 11 from Eucalyptus Dr. and various parking spots within the parking lot may be temporarily impacted – please see attached exhibits.
    • Please be advised that portions of Parking Lot 11 will be temporarily unavailable – please see attached exhibits.  
    • Please be advised that Eucalyptus Dr. will be temporarily closed – please see attached traffic plan exhibit.

    Parking Lot 10 and Co-Location Trailer Area:

    • Continue trailer delivery and setup. (Equipment: Delivery truck, air compressors, pneumatic tools, ladders & various hand tools);
    • Continue work for trailer temporary power (Equipment: ladders, shovels, and various hand tools);
    • Continue trenching for temporary domestic water line (Equipment: Mini excavator, concrete / asphalt saw, shovel, various hand tools);
    • Continue demolition of Lot 10 curb, gutter, flatwork, and landscape (Equipment: Mini excavator, skid steer, concrete saw, sledgehammer, various hand tools);
    • Anticipated disturbances: Medium level construction noise at Lot 10.  
    • Please be advised that the eastern most row of parking spots in Lot 10 will be no longer available for the duration of the SOM ED II project (summer 2023), as this will be impacted by the construction trailers area.
    • Please be advised that the middle aisles from Parking Lot 10 will be temporarily unavailable in order to complete the accessibility improvements within the lot – please see attached exhibits.

    Parking Lot 41 Laydown Area:

    • Material deliveries (Equipment: Delivery trucks, and various hand tools);
    • Pedestrian access to GH/HH #11-14 and surrounding buildings will remain open.
    • Activities and access to loading docks will not be affected.
    • Anticipated disturbances: Low level construction noise at Lot 41.

    Items listed in red: Please note that this activity may potentially disrupt the pedestrian and/or vehicular pathways and the occupants in adjacent buildings.     

    Continuous noises on site: Delivery trucks (back-up alarms), saws, screw guns, and hammers.

    The School of Medicine Education II Building Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.

  • 954045 SOM ED II Construction Alert #8

    954045 SOM ED II Construction Alert #8

    Please be advised that the following activities will be occurring from 6:00AM to 4:00PM on the School of Medicine Education Building II Site (SOM ED II) and adjacent areas on Saturday, August 7th:

    West Courtyard:

    • Continue demolition of retaining wall and stairs to GH/HH #6 (Equipment: excavator w/ breaker, sledgehammers, shovels, and various hand tools);
    • Anticipated disturbances: Medium-high level construction noise contained to West Courtyard and SOM Modular complex.

    Parking Lot 41 Laydown Area:

    • Continue installation of power poles for temporary trailer power (Equipment: Equipment truck for setting pole, ladders and various hand tools);
    • Anticipated disturbances: Low level construction noise at Lot 41.

    Please be advised that the following activities will be occurring from 6:00AM to 4:00PM on the School of Medicine Education Building II Site (SOM ED II), School of Medicine Education Building (SOM ED I) and adjacent areas during the week of August 9th through August 13th. The activities will occur within the areas identified in the attached exhibits and as shown in the map below.

    SOM ED I Ground Floor Tenant Improvements:

    • Continue flooring and base install (Equipment: heat gun, various hand tools);
    • Begin installing room signage (Equipment: Various hand tools);
    • Pedestrian access to surrounding buildings will remain open.
    • Activities and access to loading docks will not be affected.
    • Anticipated disturbances: Low level construction noise contained to Simulation rooms, Control rooms, and Exam rooms as indicated in the attached exhibit.

    SOM ED I Existing Electrical Yard (South):

    • Begin demo of enclosure and landscaping (Equipment: Skid steer, various hand and power tools).
    • Pedestrian access to surrounding buildings will remain open.
    • Activities and access to loading docks will not be affected.
    • Anticipated disturbances: Low level construction noise contained to SOM EDI Electrical Yard.

    West Courtyard:

    • Continue demolition of retaining wall and stairs to GH/HH #6 (Equipment: excavator w/ breaker, sledgehammers, shovels, and various hand tools);
    • Mobilize for rough grade of courtyard (Equipment: delivery trucks, mini-excavator, loader, skid-steer, shovels, rakes, various hand tools).
    • Activities and access to loading docks will not be affected.
    • Anticipated disturbances: Medium-high level construction noise contained to West Courtyard and SOM Modular complex.
    • Please be advised that the southern building entrances to Webber and Boyce Hall will be temporarily closed for the duration of the early construction phase of work which is anticipated between mid-July and November. Appropriate signage will be provided inside the buildings to alert the occupants.

    Greenhouse/Headhouse #6:

    • Continue demolition of retaining wall and stairs to GH/HH #6 (Equipment: excavator, sledgehammers, shovels, and various hand tools);
    • Demolition of Greenhouse and associated Headhouse (Equipment: excavator, loader, shovels, sledgehammers, various hand tools).
    • Activities and access to loading docks will not be affected.
    • Anticipated disturbances: Medium-high level construction noise contained to surrounding area and GH/HH #6.
    • Please be advised that access to Greenhouse #6 and its associated Headhouse is no longer available.
    • Please be advised that vehicular access to Parking Lot 11 from Eucalyptus Dr. and various parking spots within the parking lot may be temporarily impacted.

    Lot 11 and Eucalyptus Drive:

    • Continue excavating for electrical duct banks at Lot 11 and Eucalyptus Drive (Equipment: delivery truck, mini-excavator, shovels, trench plate, brooms, and various hand tools).
    • Activities and access to loading docks will not be affected.
    • Anticipated disturbances: Medium level construction noise contained to surrounding area.
    • Please be advised that vehicular access to Parking Lot 11 from Eucalyptus Dr. and various parking spots within the parking lot may be temporarily impacted – please see attached exhibits.
    • Please be advised that portions of Parking Lot 11 will be temporarily unavailable – please see attached exhibits.  
    • Please be advised that Eucalyptus Dr. will be temporarily closed – please see attached traffic plan exhibit.

    Parking Lot 10 and Co-Location Trailer Area:

    • Continue work for temporary trailer power (Equipment: Equipment truck for setting pole, ladders and various hand tools);
    • Begin trenching for temporary domestic water line (Equipment: mini excavator, concrete / asphalt saw, shovel, various hand tools);
    • Begin cut and cap of utilities in Lot 10 (Equipment: various hand tools);
    • Begin demolition of Lot 10 curb, gutter, flatwork, and landscape (Equipment: Mini excavator, skid steer, concrete saw, sledgehammer, various hand tools).
    • Anticipated disturbances: Medium level construction noise at Lot 10.  
    • Please be advised that the eastern most row of parking spots in Lot 10 will be no longer available for the duration of the SOM ED II project (summer 2023), as this will be impacted by the construction trailers area.
    • Please be advised that the middle aisles from Parking Lot 10 will be temporarily unavailable in order to complete the accessibility improvements within the lot – please see attached exhibits.

    Parking Lot 41 Laydown Area:

    • Continue installation of power poles for temporary trailer power (Equipment: Equipment truck for setting pole, ladders and various hand tools);
    • Small material deliveries (Equipment: Delivery trucks, and various hand tools);
    • Pedestrian access to Greenhouses #11-14 and surrounding buildings will remain open.
    • Activities and access to loading docks will not be affected.
    • Anticipated disturbances: Low level construction noise at Lot 41.

    Items listed in red: Please note that this activity may potentially disrupt the pedestrian and/or vehicular pathways and the occupants in adjacent buildings.     

    Continuous noises on site: Delivery trucks (back-up alarms), saws, screw guns, and hammers.

    The School of Medicine Education II Building Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.

  • 954045 SOM ED II Construction Alert #7

    954045 SOM ED II Construction Alert #7

    Please be advised that the following activities will be occurring from 6:00AM to 4:00PM on the School of Medicine Education Building II Site (SOM ED II), School of Medicine Education Building (SOM ED I) and adjacent areas during the week of August 2nd through August 6th. The activities will occur within the areas identified in the attached exhibits and as shown in the map below.

    SOM ED I Ground Floor Tenant Improvements:

    • Begin flooring and base install (Equipment: heat gun, various hand tools);
    • Pedestrian access to surrounding buildings will remain open.
    • Activities and access to loading docks will not be affected.
    • Anticipated disturbances: Low level construction noise contained to Simulation rooms, Control rooms, and Exam rooms as indicated in the attached exhibit.

    West Courtyard:

    • Begin safe off of site lighting in courtyard (Equipment: hand power tools, various hand tools);
    • Continue demolition of retaining wall and stairs to GH/HH #6 (Equipment: excavator w/ breaker, sledgehammers, shovels, and various hand tools);
    • Mobilize for rough grade of courtyard (Equipment: delivery trucks, mini-excavator, loader, skid-steer, shovels, rakes, various hand tools).
    • Activities and access to loading docks will not be affected.
    • Anticipated disturbances: Medium level construction noise contained to West Courtyard and SOM Modular complex.
    • Please be advised that the southern building entrances to Webber and Boyce Hall will be temporarily closed for the duration of the early construction phase of work which is anticipated between mid-July and November. Appropriate signage will be provided inside the buildings to alert the occupants.

    Greenhouse/Headhouse #6:

    • Continue safe-off of MEPF utilities in GH/HH #6. (Equipment: ladders, and various power tools);
    • Temporary services for steam, gas, compressed air, and domestic water (Equipment: steam and gas skids, generator, ladders, and various hand and power tools);
    • Begin demolition of retaining wall and stairs to GH/HH #6 (Equipment: excavator, sledgehammers, shovels, and various hand tools);
    • Continue demolition of Greenhouse and associated Headhouse (Equipment: excavator, loader, shovels, sledgehammers, various hand tools).
    • Activities and access to loading docks will not be affected.
    • Anticipated disturbances: Medium level construction noise contained to surrounding area and GH/HH #6.
    • Please be advised that access to Greenhouse 6 and its associated Headhouse is no longer available.
    • Please be advised that vehicular access to Parking Lot 11 from Eucalyptus Dr. and various parking spots within the parking lot may be temporarily impacted.

    Lot 11 and Eucalypts Drive:

    • Begin excavating Vault 10 in the street to planter off Eucalyptus (Equipment: delivery truck, mini-excavator, shovels, trench plate, brooms, and various hand tools);
    • Install temporary perimeter site fence in section of Lot 11 (Equipment: delivery truck, impact driver, various hand tools);
    • Activities and access to loading docks will not be affected.
    • Anticipated disturbances: Medium level construction noise contained to surrounding area.
    • Please be advised that vehicular access to Parking Lot 11 from Eucalyptus Dr. and various parking spots within the parking lot may be temporarily impacted – please see attached exhibits.
    • Please be advised that portions of Parking Lot 11 will be temporarily unavailable – please see attached exhibits.  
    • Please be advised that Eucalyptus Dr. will be temporarily closed – please see attached traffic plan exhibit.

     

    Parking Lot 10 and Co-Location Trailer Area:

    • Continue work for temporary trailer power (Equipment: Equipment truck for setting pole, ladders and various hand tools);
    • Begin trenching for temporary domestic water line (Equipment: mini excavator, concrete / asphalt saw, shovel, various hand tools);
    • Begin cut and cap of utilities in Lot 10 (Equipment: various hand tools);
    • Install temporary perimeter site fence and SWPPP (Equipment: delivery truck, impact driver, various hand tools).
    • Anticipated disturbances: Medium level construction noise at Lot 10.  
    • Please be advised that the eastern most row of parking spots in Lot 10 will be no longer available for the duration of the SOM ED II project (summer 2023), as this will be impacted by the construction trailers area.
    • Please be advised that the middle aisles from Parking Lot 10 will be temporarily unavailable in order to complete the accessibility improvements within the lot – please see attached exhibits.

    Parking Lot 41 Laydown Area:

    • Continue installation of power poles for temporary trailer power (Equipment: Equipment truck for setting pole, ladders and various hand tools);
    • Small material deliveries (Equipment: Delivery trucks, and various hand tools);
    • Pedestrian access to Greenhouses #11-14 and surrounding buildings will remain open.
    • Activities and access to loading docks will not be affected.
    • Anticipated disturbances: Low level construction noise at Lot 41.

    Items listed in red: Please note that this activity may potentially disrupt the pedestrian and/or vehicular pathways and the occupants in adjacent buildings.     

    Continuous noises on site: Delivery trucks (back-up alarms), saws, screw guns, and hammers.

    The School of Medicine Education II Building Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.

  • 954045 SOM ED II Construction Alert #6

    954045 SOM ED II Construction Alert #6

    Please be advised that the following activities will be occurring from 6:00AM to 4:00PM on the School of Medicine Education Building II Site (SOM ED II), School of Medicine Education Building (SOM ED I) and adjacent areas on during the week of July 26th through July 30th. The activities will occur within the areas identified in the attached exhibit and as shown in the maps below.

    SOM ED I Ground Floor Tenant Improvements:

    • Continue final paint (Equipment: ladders, tarps, and various painting tools);
    • Begin Floor Prep (Flooring Starts 8/2/21) (Drills, floats and various hand tools);
    • Pedestrian access to surrounding buildings will remain open.
    • Activities and access to loading docks will not be affected.
    • Anticipated disturbances: Low level construction noise contained to Simulation rooms, Control rooms, and Exam rooms as indicated in the attached exhibit

    West Courtyard:

    • Continue installation of SWPPP around fence line and storm drain inlets (Equipment: Delivery truck, hammers and various hand tools);
    • Continue clear and grub of trees and landscape at West Courtyard and GH/HH #6 (Equipment: Wood chipper, chainsaws, leaf blowers, ladders, rakes, brooms, and various hand tools);
    • Begin demolition of retaining wall and stairs to GH/HH #6 (Equipment: Excavator w/ breaker, sledgehammers, shovels, and various hand tools);
    • Modify fence line to close Southeast entrances / exits to Boyce and Webber Hall (Equipment: Delivery truck, impact driver, various hand tools);
    • Add signage inside Boyce and Webber Hall for adjusted fence line. (Equipment: Various hand tools).
    • Activities and access to loading docks will not be affected.
    • Anticipated disturbances: Medium level construction noise contained to West Courtyard and SOM Modular complex.
    • Please be advised that the southern building entrances to Webber and Boyce Hall will be temporarily closed for the duration of the early construction phase of work which is anticipated between mid-July and November. Appropriate signage will be provided inside the buildings to alert the occupants.

    Greenhouse/Headhouse #6 and Parking Lot 11:

    • Continue asbestos abatement in GH/HH#6 (Equipment: Dumpster, generator, negative air machines, and various hand tools);
    • Continue safe-off of MEPF utilities in GH/HH #6. (Equipment: Ladders, and various power tools);
    • Temporary services for steam, gas, compressed air, and domestic water (Equipment: Steam and gas skids, generator, ladders, and various hand and power tools);
    • Continue installation of SWPPP around fence line and storm drain inlets (Equipment: Delivery truck, hammers and various hand tools);
    • Continue clear and grub of trees and landscape at West Courtyard and GH/HH #6 (Equipment: Wood chipper, chainsaws, leaf blowers, ladders, rakes, brooms, and various hand tools);
    • Begin demolition of retaining wall and stairs to GH/HH #6 (Equipment: Excavator, sledgehammers, shovels, and various hand tools);
    • Begin exploratory excavation for vaults at Lot 11 (Equipment: delivery truck, mini-excavator, shovels, trench plate, brooms, and various hand tools);
    • Activities and access to loading docks will not be affected.
    • Anticipated disturbances: Medium level construction noise contained to surrounding area and GH/HH #6.
    • Please be advised that access to Greenhouse 6 and its associated Headhouse is no longer available.
    • Please be advised that vehicular access to Parking Lot 11 from Eucalyptus Dr. and various parking spots within the parking lot may be temporarily impacted.
    • Please be advised that GH/HH #6 and 7 will be affected by a scheduled power and water interruption on Wednesday July 28.

    Parking Lot 10 and Co-Location Trailer Area:

    • Continue work for temporary trailer power (Equipment: Equipment truck for setting pole, ladders and various hand tools);
    • Begin trenching for temporary domestic water line (Equipment: Mini excavator, concrete / asphalt saw, shovel, various hand tools);
    • Form, rebar, and place temporary electrical equipment pad (Equipment: Concrete truck, hand power tools, various hand tools).
    • Anticipated disturbances: Medium level construction noise at Lot 10.  
    • Please be advised that the eastern most row of parking spots in Lot 10 will be no longer available for the duration of the SOM ED II project (summer 2023), as this will be impacted by the construction trailers area.

    Parking Lot 41 Laydown Area:

    • Continue installation of power poles for temporary trailer power (Equipment: Equipment truck for setting pole, ladders and various hand tools);
    • Small material deliveries (Equipment: Delivery trucks, and various hand tools);
    • Pedestrian access to Greenhouses #11-14 and surrounding buildings will remain open.
    • Activities and access to loading docks will not be affected.
    • Anticipated disturbances: Low level construction noise at Lot 41.

    Items listed in red: Please note that this activity may potentially disrupt the pedestrian and/or vehicular pathways and the occupants in adjacent buildings. 

    The School of Medicine Education II Building Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.

  • 954045 SOM ED II Construction Alert #5

    954045 SOM ED II Construction Alert #5

    Please be advised that the following activities will be occurring from 6:00AM to 4:00PM on the School of Medicine Education Building II Site (SOM ED II), School of Medicine Education Building (SOM ED I) and adjacent areas on during the week of July 19th through July 24th. The activities will occur within the areas identified in the attached exhibit and as shown in the maps below.

    SOM ED I Ground Floor Tenant Improvements:

    • Continue ceiling tile and grid repairs (Equipment: ladders, brooms, and various hand tools);
    • Begin final paint (Equipment: ladders, tarps, and various painting tools);
    • Pedestrian access to surrounding buildings will remain open.
    • Activities and access to loading docks will not be affected.
    • Anticipated disturbances: Low level construction noise contained to Simulation rooms, Control rooms, and Exam rooms as indicated in the attached exhibit.

    West Courtyard:

    • Installation of SWPPP around fence line and storm drain inlets (Equipment: Delivery truck, hammers and various hand tools);
    • Begin clear and grub of trees and landscape at West Courtyard and GH/HH #6 (Equipment: Wood chipper, chainsaws, leaf blowers, ladders, rakes, brooms, and various hand tools);
    • Begin demolition of retaining wall and stairs to GH/HH #6 (Equipment: Excavator w/ breaker, sledgehammers, shovels, and various hand tools).
    • Activities and access to loading docks will not be affected.
    • Anticipated disturbances: Medium level construction noise contained to West Courtyard and SOM Modular complex.
    • Please be advised that the southern building entrances to Webber and Boyce Hall will be temporarily closed for the duration of the early construction phase of work which is anticipated between mid-July and November. Appropriate signage will be provided inside the buildings to alert the occupants.

    Greenhouse/Headhouse #6 and Parking Lot 11:

    • Continue asbestos abatement in GH/HH#6 (Equipment: Dumpster, generator, negative air machines, and various hand tools);
    • Continue safe-off of MEPF utilities in GH/HH #6. (Equipment: Ladders, and various power tools);
    • Temporary services for steam, gas, compressed air, and domestic water (Equipment: Steam and gas skids, generator, ladders, and various hand and power tools);
    • Installation of SWPPP around fence line and storm drain inlets (Equipment: Delivery truck, hammers and various hand tools);
    • Begin clear and grub of trees and landscape at West Courtyard and GH/HH #6 (Equipment: Wood chipper, chainsaws, leaf blowers, ladders, rakes, brooms, and various hand tools);
    • Begin demolition of retaining wall and stairs to GH/HH #6 (Equipment: Excavator, sledgehammers, shovels, and various hand tools);
    • Begin excavating for vaults at Lot 11 (Equipment: delivery truck, mini-excavator, shovels, trench plate, brooms, and various hand tools).
    • Activities and access to loading docks will not be affected.
    • Anticipated disturbances: Medium level construction noise contained to surrounding area and GH/HH #6.
    • Please be advised that access to Greenhouse 6 and its associated Headhouse is no longer available.
    • Please be advised that vehicular access to Parking Lot 11 from Eucalyptus Dr. and various parking spots within the parking lot may be temporarily impacted.

    Parking Lot 10 and Co-Location Trailer Area:

    • Continue work for trailer temporary power (Equipment: ladders and various hand tools).
    • Anticipated disturbances: Medium level construction noise at Lot 10.  
    • Please be advised that the eastern most row of parking spots in Lot 10 will be no longer available for the duration of the SOM ED II project (summer 2023), as this will be impacted by the construction trailers area.

    Parking Lot 41 Laydown Area:

    • Begin installation of power poles for temporary trailer power (Equipment: Equipment truck for setting pole, ladders and various hand tools);
    • Small material deliveries (Equipment: Delivery trucks, and various hand tools);
    • Pedestrian access to Greenhouses #11-14 and surrounding buildings will remain open.
    • Activities and access to loading docks will not be affected.
    • Anticipated disturbances: Low level construction noise at Lot 41.

    Items listed in red: Please note that this activity may potentially disrupt the pedestrian and/or vehicular pathways and the occupants in adjacent buildings.     

    Continuous noises on site: Delivery trucks (back-up alarms), saws, screw guns, and hammers.

  • 954045 SOM ED II Construction Alert #4

    954045 SOM ED II Construction Alert #4

    Please be advised that the following activities will be occurring from 6:00AM to 4:00PM on the School of Medicine Education Building II Site (SOM ED II), School of Medicine Education Building (SOM ED I) and adjacent areas on during the week of July 12th through July 17th. The activities will occur within the areas identified in the attached exhibit and as shown in the maps below.

    SOM ED I Ground Floor Tenant Improvements:

    • Continue drywall patching and taping (Equipment: ladders, drills, impact driver, brooms, and various hand tools);
    • Begin ceiling tile and grid repairs (Equipment: ladders, brooms, and various hand tools);
    • Pedestrian access to surrounding buildings will remain open.
    • Activities and access to loading docks will not be affected at SOM EDI, Boyce or Batchelor Hall.
    • Anticipated disturbances: Low level construction noise contained to Simulation rooms, Control rooms, and Exam rooms as indicated in the attached exhibit

    Greenhouse/Headhouse #6 and West Courtyard:

    • Verify electrical circuits (Equipment: ladders, drills, brooms, and various hand tools);
    • Begin HH #6 abatement process (Equipment: Service truck, ladders, drills, hammers, shovels, brooms, and various hand tools) – all required containment and oversight will be provided;
    • Begin establishing temporary utility services (Equipment: Temporary steam and natural gas skids, service truck, ladders, drills, brooms, and various hand tools);
    • Installation of site fence around the early phase work construction area (Equipment: delivery truck, ladders, drills, brooms, and various hand tools);
    • Identify existing landscape for demolition;
    • Installation of SWPPP (Equipment: hammers and various hand tools).
    • Activities and access to loading docks will not be affected at SOM EDI, Boyce or Batchelor Hall.
    • Anticipated disturbances: Mid-level construction noise contained to surrounding west courtyard and GH/HH #6.
    • Please be advised that the southern building entrances to Webber and Boyce Hall will be temporarily closed for the duration of the early make ready construction phase of work which is anticipated between mid-July and November. Appropriate signage will be provided inside the buildings to alert the occupants.

    Parking Lot 10 and Co-Location Trailer Area:

    • Site fence reconfiguration (Equipment: delivery truck, ladders, drills, brooms, and various hand tools).
    • Begin work to setup temporary construction trailer power (Equipment: ladders and various hand tools);
    • Delivery of additional temporary construction trailers (Equipment: delivery truck and various hand tools).
    • Anticipated disturbances: Low level construction noise at Lot 10.  
    • Please be advised that the eastern most row of parking spots in Lot 10 will be no longer available for the duration of the SOM ED II project (summer 2023), as this will be impacted by the construction trailers area.

    Logistics at Parking Lot 41 Laydown Area:

    • Continue sorting through storage containers (Conex Boxes) in fenced Lot 41 (Equipment: various hand tools);
    • Delivery of additional construction Conex box (Equipment: delivery truck, various hand tools).
    • Pedestrian access to Greenhouses/Headhouses #11-14 and surrounding buildings will remain open.
    • Activities and access to loading docks will not be affected.
    • Anticipated disturbances: Low level construction noise at Lot 41.

    Items listed in red: Please note that this activity may potentially disrupt the pedestrian and/or vehicular pathways and the occupants in adjacent buildings.     

    Continuous noises on site: Delivery trucks (back-up alarms), saws, screw guns, and hammers.

    The School of Medicine Education II Building Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.

  • 954045 SOM ED II Construction Alert #3

    954045 SOM ED II Construction Alert #3

    Please be advised that the following activities will be occurring from 6:00AM to 4:00PM on the School of Medicine Education Building II Site (SOM ED II), School of Medicine Education Building (SOM ED I) and adjacent areas on during the week of July 5th through July 10th. The activities will occur within the areas identified in the attached exhibit and as shown in the maps below.

    SOM ED I Ground Floor Tenant Improvement:

    • Finalize electrical rough-in (Equipment: ladders, drills, brooms, and various hand tools);
    • Begin metal stud infill at punch windows (Equipment: ladders, drills, impact driver, cut-off saw, brooms, and various hand tools);
    • Begin plumbing termination at head walls and at demolished sink locations (Equipment: ladders, drills, band saws, brooms, and various hand tools);
    • Begin drywall patching and taping (Equipment: ladders, drills, impact driver, brooms, and various hand tools);
    • Pedestrian access to surrounding buildings will remain open.
    • Activities and access to loading docks will not be affected.
    • Anticipated disturbances: Low level construction noise contained to Simulation rooms, Control rooms, and Exam rooms as indicated in the attached exhibit.

    Logistics at Lot 41 Laydown Area:

    • Continue sorting through storage containers (Conex Boxes) in fenced Lot 41 (Equipment: various hand tools).
    • Pedestrian access to Greenhouses/Headhouses #11-14 and surrounding buildings will remain open.
    • Activities and access to loading docks will not be affected.
    • Anticipated disturbances: Low level construction noise at Lot 41

    Greenhouse/Headhouse #6 and West Courtyard:

    • Site preparation for project fence installation (No equipment necessary).
      • Project fence installation is scheduled for 7/12 – 7/16.
    • Anticipated disturbances: No anticipated disturbances.
    • Please be advised that the southern building entrances to Webber and Boyce Hall will be temporarily closed for the duration of the early construction phase of work which is anticipated between mid-July and November. Appropriate signage will be provided inside the buildings to alert the occupants.

    Items listed in red: Please note that this activity may potentially disrupt the pedestrian/vehicular pathways.     

    Continuous noises on site: Delivery trucks (back-up alarms), saws, screw guns, and hammers.

    The School of Medicine Education II Building Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.

  • 954045 SOM ED II Construction Alert #2

    954045 SOM ED II Construction Alert #2

    Please be advised that the following activities will be occurring from 6:00AM to 4:00PM on the School of Medicine Education Building II Site (SOM ED II), School of Medicine Education Building (SOM ED I) and adjacent areas on during the week of June 28th through July 3rd. The activities will occur within the areas identified in the attached exhibit and as shown in the maps below.

    SOM ED I Ground Floor Tenant Improvements:

    • Continue demolition of existing flooring and punch windows (equipment: ladders, drills, saws, pneumatic tools, scrapers, wheel barrows, brooms, and various hand tools).
      • Anticipated disturbances: Low level construction noise contained to Simulation rooms, Control rooms, and Exam rooms as indicated in the attached exhibit.
    • Layout of added electrical outlets.
    • Demo drywall for added outlets.
    • Metal stud infill at punch windows.
    • Begin electrical rough in for added outlets.
    • Pedestrian access to surrounding buildings will remain open.
    • Activities and access to loading docks will not be affected.

    Logistics at Lot 41 Laydown Area:

    • Begin shaking out and sorting through storage containers (Conex Boxes) in fenced Lot 41 (equipment: various hand tools).
      • Anticipated disturbances: Low level construction noise at Lot 41.
    • Pedestrian access to Greenhouses 11-14 and surrounding buildings will remain open.
    • Activities and access to loading docks will not be affected.

    Items listed in red: Please note that this activity may potentially disrupt the pedestrian/vehicular pathways.     

    Continuous noises on site: Delivery trucks (back-up alarms), saws, screw guns, and hammers.

    The School of Medicine Education II Building Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.

  • 954045 SOM ED II Construction Alert #1

    Please be advised that the following activities will be occurring from 6:00AM to 4:00PM on the School of Medicine Education Building II Site (SOM ED II), School of Medicine Education Building (SOM ED I) and adjacent areas on during the week of June 21st through June 25th. The activities will occur within the areas identified in the attached exhibit and as shown in the maps below.

    SOM ED I Ground Floor Tenant Improvement:

    • Start of utility safe-off, abatement and demolition (equipment: ladders, drills, saws, pneumatic tools, scrapers, wheelbarrows, brooms and various hand tools).
      • Anticipated disturbances: (Low level construction noise contained to Simulation rooms, Control rooms, and Exam rooms as indicated in the attached exhibit)
    • Pedestrian access to surrounding buildings will remain open.
    • Activities and access to loading docks will not be affected.

    Logistics at Lot 41 Laydown Area:

    • Delivery of storage containers (Conex boxes) and perimeter fence set up. (equipment: Flatbed truck with winch and various hand tools).
      • Anticipated disturbances: (Low level construction noise at Lot 41)
    • Pedestrian and limited vehicular access to Greenhouses 11-14 and surrounding buildings will remain open.
    • Activities and access to loading docks will not be affected.

    Items listed in red: Please note that this activity may potentially disrupt the pedestrian/vehicular pathways.     

    Continuous noises on site: Delivery trucks (back-up alarms), saws, screw guns, and hammers.

    The School of Medicine Education II Building Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.

  • 954045 SEOM ED II Project Notification #6

    954045 SOM ED II Project Notification #6

    The following activities will be occurring from 6:00AM to 4:00PM on the School of Medicine Education Building II Site and adjacent areas on Monday, June 7th. The activities will occur within the areas identified in the attached exhibit.

    Underground Investigation/Potholing:

    • Site investigation potholing at designated areas per attached exhibit. (equipment: industrial vacuum truck, shovels, jackhammers, wheelbarrows, brooms and various hand tools).
      • Anticipated disturbances: minimal jackhammering – max 3 locations (12”x12”), slight vibrations and running engines.
    • Pedestrian access to surrounding buildings will remain open.
    • Activities and access to loading docks will not be affected.

    The Contractor and PD&C Project Management team will be overseeing these activities with the required support from our Facilities Services partners.

    Pot Hole Exhibit

    Items listed in red: Please note that this activity may potentially disrupt the pedestrian/vehicular pathways.     

    Our team is not anticipating any impact to the adjacent buildings and occupants or any disruptions to the campus activity outside of items listed above.

    Please let us know if you would like to be removed from the project notification emails. Also, please advise if you would like us to include additional recipients by responding to this email with the required information.

  • 954045 SOM ED II Project Notification #5

    954045 SOM ED II Project Notification #5

     

    The following activities will be occurring from 6:00AM to 4:00PM on the School of Medicine Education Building II Site and adjacent areas on Wednesday, May 26th  and Thursday, May 27th. The activities will occur within the areas identified in the attached exhibit.

    Underground Investigation/Potholing:

    • Site investigation potholing at designated areas per attached exhibit. (equipment: industrial vacuum truck, shovels, jackhammers, wheelbarrows, brooms and various hand tools).
      • Anticipated disturbances: minimal jackhammering – max 9 locations (12”x12”), slight vibrations and running engines.
    • Pedestrian access to surrounding buildings will remain open.
    • Activities and access to loading docks will not be affected.
    • Please be advised that parts of the accessible parking at SOM ED I, Boyce Hall and adjacent areas will be temporarily/intermittently unavailable on Thursday, May 27th between 6:00AM-2:00PM in order to complete the activities in this area.

    The Contractor and PD&C Project Management team will be overseeing these activities with the required support from our Facilities Services partners.

    Items listed in red: Please note that this activity may potentially disrupt the pedestrian/vehicular pathways.     

    Our team is not anticipating any impact to the adjacent buildings and occupants or any disruptions to the campus activity outside of items listed above.

  • 954045 SOM ED II Project Notification #4

    954045 SOM ED II Project Notification #4

    The following activities will be occurring from 6:30AM to 4:00PM on the School of Medicine Education Building II Site and adjacent areas on Friday, May 21st. The activities will occur within the areas identified in the attached exhibit.

    Underground Investigation/Potholing:

    • Site investigation potholing at designated areas per attached exhibit. (equipment: industrial vacuum truck, shovels, jackhammers, wheelbarrows, brooms and various hand tools).
      • Anticipated disturbances: minimal jackhammering – max 6 locations (12”x12”), slight vibrations and running engines.
    • Pedestrian access to surrounding buildings will remain open.
    • Activities and access to loading docks will not be affected.
    • Please be advised that the pedestrian and vehicular access to the ramp north of Lot 11, between Greenhouse 6 and Keen Hall, will be temporarily/ intermittently closed on Friday, May 21st between 6:30AM-4:00PM to complete the site investigation potholing activities in this area. Please see areas of activity within the Pothole Exhibit attachment

    The Contractor and PD&C Project Management team will be overseeing these activities with the required support from our Facilities Services partners.

    Items listed in red: Please note that this activity may potentially disrupt the pedestrian/vehicular pathways.     

    Our team is not anticipating any impact to the adjacent buildings and occupants or any disruptions to the campus activity outside of items listed above.

  • SOM Education Building 2 Project Notification #3

    954045 SOM ED II Project Notification #3

    The following activities will be occurring from 6:30AM to 4:00PM on the School of Medicine Education Building II site and adjacent areas on Thursday, May 13th. The activities will occur within the areas identified in the attached exhibit.

    Geotechnical boring operation

    • Drilling multiple geotechnical boring samples at the locations specified in the Geotechnical Boring Activity Exhibit (equipment: Drill-rig truck, shovels, wheelbarrows, brooms and various hand tools).
    • Pedestrian access will remain open.
    • Activities and access to loading docks will not be affected.
    • Please be advised that the vehicular access to the road north of Greenhouses 6 through 10 will be closed on Thursday, May 13th between 6:30AM-10:30AM to complete the activities in this area.
    • Please be advised that parking at the SOM modular and adjacent areas will be temporarily/intermittently unavailable on Thursday, May 13th between 10:30AM-3:30PM to complete the geotechnical boring activities in this area.

    The Contractor and PD&C Project Management team will be overseeing these activities with the required support from our Facilities Services partners.

    Items listed in red: Please note that this activity may potentially disrupt the pedestrian/vehicular pathways.     

    Our team is not anticipating any impact to the adjacent buildings and occupants or any disruptions to the campus activity outside of items listed above.

  • SOM Education Building 2 Project Notification #2

    954045 SOM ED II Project Notification #2

    Please be advised that the following activities will be occurring from 6:30AM to 5:00PM on the School of Medicine Education Building II Site and adjacent areas on Tuesday, May 4th and Wednesday, May 5th. The activities will occur within the areas identified in the attached exhibit.

    Underground utility location

    • Pothole designated areas per attached exhibit to locate and confirm underground utilities in preparation for geotechnical boring operations (equipment: shovels, vacuum potholing equipment).
    • Pedestrian access will remain open.
    • Activities and access to loading docks will not be affected.
    • Please be advised that the vehicular access to the road north of Greenhouses 6 through 10 will be closed on Tuesday, May 4th between 6:30AM-3:30PM to complete the potholing activities in this area.
    • Please be advised that parking at the SOM modular and adjacent areas will be temporarily/ intermittently unavailable on Wednesday, May 5th between 6:30AM-3:30PM to complete the potholing activities in this area

    The Contractor and PD&C Project Management team will be overseeing these activities with the required support from our Facilities Services partners.

    Items listed in red: Please note that this activity may potentially disrupt the pedestrian/vehicular pathways. 

    Our team is not anticipating any impact to the adjacent buildings and occupants or any disruptions to the campus activity outside of items listed above.

    Pathhole Exibit

  • SOM Education Building 2 Project Notification #1

    954045 SOM ED II Project Notification #1

    Please be advised that the following activities will be occurring from 6:30AM to 5:00PM on the School of Medicine Education Building II Site and adjacent areas on Wednesday, April 28th. The activities will occur within the areas identified in the attached exhibit.

    Geotechnical boring operation

    • Drilling multiple geotechnical boring samples at the locations specified in the Geotechnical Boring Operation Exhibit (equipment: geotechnical drilling truck);
    • Please be advised that parking will be temporarily unavailable at the SOM Modular Building and at Headhouse #6 as specified in the exhibit.

    The Contractor and PD&C Project Management team will be overseeing these activities with the required support from our Facilities Services partners.

    Our team is not anticipating any impact to the adjacent buildings and occupants or any disruptions to the campus activity.

    Geo-technical Boring Locations