Plant Growth Environment Facility


plant growth

  • Replace aged greenhouses with new state of the art greenhouses with the ability for greater temperature control.
  • Construct a facility that can be shared across CNAS departments & support a wide range of research functions & environments.
  • Balance the opportunities for segregated/isolated and shared/collaborative workspaces.
  • Space for both walk-in and cabinet growth chambers with adequate infrastructure
    .

 

Current Activities
Next Steps
Construction Notice
 Construction Mobilization  Removal of Trees and Shrubs

 5/16-5/17 Equipment Delivery (minimal impact)

  • Back up beeping
 Installation of Construction Fence - 5/13 Demolition and Removal of Existing Structures

 5/21 - 5/24 Tree Removal (moderate impact)

  • Chain saws
  • Wood chipper
  • Back up beeping
  • Overhead hazard (trees coming down)
  • Heavy equipment operation
  • Heavy haul trucks to the MLK exit
   Grading of Building Pad

 5/21 - 5/27 Demolition (significant impact)

  • Heavy equipment operation
  • Back up beeping
  • Jack hammering
  • Heavy haul trucks to the MLK exit
   Underground Utilities

 5/28 - 6/12 Grading & Excavation (significant impact)

  • Back up beeping
  • Heavy equipment operation
  • Soil excavation vibration

Sign up to receive Construction Updates