University of California, Riverside

Architects & Engineers



MRB1 Construction Information


Construction Image
  1. The MRB1 construction fence will enclose the open area directly north of the Materials Science & Engineering 1 Building and will extend to encompass much of Parking Lot 25, immediately east of the Student Recreation Center.
  2. All normal access to MS&E will be maintained.
  3. Pedestrian access from Parking Lot 24 to Parking Lot 25, via the sidewalk in between the track and the soccer fields, will be closed as of August 19, 2016.
  4. Pedestrian access to the Athletics track, soccer & softball fields will be maintained.
  5. Construction traffic will access the MRB1 construction site from the north, via Parking Lot 25. 2-hour parking at Parking Lot 25 will be taken off-line as of September 12 to allow all MRB1 construction traffic to access the site via this parking lot.
  6. Accessible parking spaces will be maintained at the northern end of Parking Lot 25.
  7. Pedestrian access to the Student Recreation Center will be maintained from Linden and Aberdeen.

Visits to MRB1 Site:

All University academic and staff personnel who are needing access to the construction site that is now in progress, should notify the Project Program Coordinator (Cathleen Stasik @ 909-781-0990) one week prior to intended visit. The Project Manager will advise the Contractor's superintendent, obtain necessary liability waivers, and ensure that proper protective safety equipment is used by all who enter the construction site. Safety is our main priority. 

The UCR MRB1 Team recognizes that construction activities will at time pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.



CONSTRUCTION ALERTS

Construction Alerts - December 2018

Construction Alert #109

The following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site on Dec 8th:

  •  MRI shielding installation (equipment: screw gun).

The following activities will be occurring from 6:00 AM to 4:00 PM PM on the MRB1 Café Buildout during the week of Dec 10th - Dec 14th::

  • Concrete pour for the interior slab and loading dock lift platform (equipment: concrete truck, concrete pump);
  • Partition wall framing (equipment: metal saws, screw guns)

The following activities will be occurring from 6:00 AM to 4:00 PM on the MRB1 Construction Site during the week of Dec 10th - Dec 14th:

  • Drywall on the Lower Level (equipment: screw guns);
  • MRI shielding installation (equipment: screw guns);
  • Place base for relocated blue emergency phone (equipment: concrete truck, vibrator);
  • Replace tree along North fire road;
  • Lift station/grease interceptor at Café (equipment: forklift);
  • Modify pavers at switchback ramp and café.


Continuous noises on site: Delivery Trucks (Back-up Alarms), Forklifts, boom lifts, scissor lifts, back up alarms, saws, screw guns, and hammers.

The UCR MRB1 Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.
Construction Alerts - September 2016 - November 2018

Construction Alert #108

The following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site on Dec 1st:

  • Place walkway at A&E trailer;
  • Seal North fire road.

The following activities will be occurring from 6:00 AM to 4:00 PM PM on the MRB1 Café Buildout on Dec 1st:

  • Concrete cutting and demo at MS&E loading dock (equipment: concrete skill saw, jack hammer)

The following activities will be occurring from 6:00 AM to 4:00 PM on the MRB1 Construction Site during the week of Dec 3rd - Dec 7th:

  • Wall/Ceiling rough-in on the Lower Level (equipment: screw guns);
  • Drywall on the Lower Level (equipment: screw guns);
  • Install floor on the Lower Level MRI Room;
  • Miscellaneous punch list items (various);
  • Place base for relocated blue emergency phone (equipment: concrete truck, vibrator);
  • Replace tree along North fire road;
  • Complete installation of foldable door at seminar room;
  • Install roller shades;
  • Install light poles along Aberdeen;
  • Lift station/grease interceptor at Café (equipment: forklift).

The following activities will be occurring from 6:00 AM to 4:00 PM PM on the MRB1 Café Buildout during the week of Dec 3rd - Dec 7th:

  • Underground backfilling and compaction (equipment: handheld compactor);
  • Concrete pour for the interior slab and loading dock lift platform (equipment: concrete truck, concrete pump).

Construction Alert #107

The following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site during the week of Nov 26th - Nov 30th:

  • Wall/Ceiling rough-in on the Lower Level (equipment: screw guns);
  • Drywall on the Lower Level (equipment: screw guns);
  • Miscellaneous punch list items (various);
  • Install power at seminar room foldable door;
  • Install light poles along Aberdeen;
  • Lift station/grease interceptor at Café;
  • Sandblast concrete on North fire road (equipment: sandblasters, trucks) – North fire road is expected to be closed off for the entire week.

The following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Café Buildout during the week of Nov 26th - Nov 30th:

  • Underground plumbing and trenching (equipment: jack hammer);
  • Underground backfilling and compaction (equipment: jack hammer, handheld compactor);
  • Concrete cutting and demo (equipment: concrete skill saw, jack hammer);
  • Concrete forming (equipment: wood saw, nail gun);
  • Concrete pouring (equipment: concrete truck, concrete pump).

Construction Alert #106

The following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site during the week of Nov 19th - Nov 23rd:

  • Wall/Ceiling Rough-In on the Lower Level (equipment: screw guns);
  • Drywall on the Lower Level (equipment: screw guns);
  • Miscellaneous punch list items (various);
  • Cleaning of pavers on Level 3 terrace (equipment: pressure washer);
  • Sandblast temporary stripe off Aberdeen (equipment: sandblaster).

Construction Alert #105

The following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site during the week of Nov 5th - Nov 9nd:

  • Punchlist items Lower Level - 4 and site (various);
  • Tile demo at atrium (equipment: jack hammer);
  • Planting shrubs/trees/mulch (equipment: skip loader);
  • Install wood benches (equipment: saw, screw guns);
  • Removal of temporary construction trailers;
  • Framing on the Lower Level (equipment: screw guns and chop saws);
  • Wall and ceiling rough-in on the Lower Level (equipment: screw guns).

Construction Alert #104

The following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site during the week of Oct 29th - Nov 2nd:

  • Punchlist painting (equipment: sprayer);
  • Punchlist items Lower Level - 4 and site (various);
  • Tile patch at atrium;
  • Operable partition installation at Seminar Room (equipment: screw guns);
  • Planting shrubs /mulch (equipment: skip loader);
  • Framing and wall rough-in on the Lower Level (equipment: screw guns and chop saws);
  • Haul off dirt pile (equipment: loader, dump trucks);
  • Demo of last section of hammer throw on west end of site (equipment: jack hammer);
  • Punchlist of Café Plaster;
  • HP to move into LL Office 0135;
  • Removal of equipment and material (West laydown area).

Construction Alert #103

The following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site during the week of Oct 22nd - Oct 26th:

  • Punchlist painting (equipment: sprayer);
  • Punchlist items Level 1-4 and site (various);
  • Glazing at stair 2 (equipment: scissor lift);
  • Rework of radiant pipe in Atrium (equipment: jackhammer);
  • Operable partition installation at Seminar Room (equipment: screw guns);
  • Planting shrubs /mulch (equipment: skip loader);
  • Lab equipment (equipment: screw guns);
  • Glazing at the Café (equipment: screw guns);
  • Cleaning (equipment: swing stage and pressure washer);
  • Framing and wall rough-in on the Lower Level (equipment: screw guns and chop saws);
  • Removal of equipment and material (West laydown area).

Construction Alert #102

The following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site during the week of Oct 15th - Oct 19th:

  • Punchlist painting (equipment: sprayer);
  • Punchlist items Level 1-4 and site (various);
  • Window shade installation (screw guns);
  • Sealing concrete – Loading Dock (sprayer);
  • Temp fencing installation – West Site Entry Lower Level (DP-7) to South Fire Road Entry / Café;
  • Planting shrubs /mulch (equipment: skip loader);
  • Lab equipment (equipment: screw guns);
  • Glazing at the Café (equipment: screw guns);
  • Counter top install at Café (screw guns);
  • Cleaning (equipment: swing stage and pressure washer);
  • Framing on the Lower Level East Vivarium (equipment: screw guns and chop saws);
  • Removal of equipment and material (West laydown area);
  • Demobilize MEP trailers from Lot 25 (trucks, screw guns, air compressors).

Construction Alert #101

Please be advised that the following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site on Saturday, Oct 6th.

  • Landscaping;
  • General site cleaning;
  • Terrace pavers;
  • South canopy.

The following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site during the week of Oct 8th - Oct 12th:

  • Punchlist painting (equipment: sprayer);
  • Lab equipment (equipment: drill, hammer, forklift);
  • Planting shrubs (equipment: auger);
  • Glazing at the Café (equipment: screw guns);
  • Cleaning (equipment: swing stage and pressure washer);
  • Framing on the Lower Level East Vivarium.

Construction Alert #100

Please be advised that the following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site on Saturday, Sept 29th.

  • Landscaping;
  • General site cleaning;
  • Concrete cleaning;
  • South Canopy.

The following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site during the week of Oct 1st - Oct 5th:

  • Interior painting (equipment: sprayer);
  • Lab equipment installation (equipment: drill, hammer, forklift);
  • Planting shrubs (equipment: auger);
  • Glazing at the Café (equipment: screw guns);
  • Cleaning (equipment: swing stage and pressure washer).

Construction Alert #99

Please be advised that the following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site on Saturday, Sept 22nd.

  • Interior/exterior painting;
  • Placing concrete;
  • Lab casework;
  • Landscaping;
  • Pavers installation;
  • Elevator adjustments

The following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site on Sunday, Sept 23rd:

  • Elevator adjustments.

The following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site during the week of Sept 24th - Sept 28th:

  • Doors and hardware (equipment: screw guns);
  • Interior painting (equipment: sprayer);
  • T-Grid ceiling (equipment: screw guns, powder actuated tool);
  • Flooring (equipment: screw gun, mixer);
  • Lab equipment installation (equipment: drill, hammer, forklift);
  • Grading (equipment: Loader, sheep foot);
  • Digging for site utilities on North and South road (equipment: mini ex);
  • Running irrigation lines on South and East side (equipment: mini ex);
  • Placing concrete (equipment: concrete trucks and pump);
  • Pavers on South side (equipment: wet saws and mixers);
  • Grading of parking spaces at the South end of Parking Lot 25 (equipment: loader, sheep foot, bobcat);
  • Placing asphalt at the South end of Parking Lot 25 (equipment: skip loader and asphalt trucks);
  • Placing curb and gutter at the South end of Parking Lot 25 (equipment concrete trucks, vibrators, hammers);
  • Planting shrubs (equipment: auger);
  • Glazing at the Café (equipment: screw guns)

Construction Alert #98

Please be advised that the following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site on Saturday, Sept 15th.

  • Concrete cleaning;
  • Interior/exterior painting;
  • Lab casework;
  • Landscape watering;
  • Exterior cleaning;
  • Wood slat ceiling;
  • Plaster finish;
  • Precast replacement.

The following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site during the week of Sept 17th - Sept 21st:

  • Doors and hardware (equipment: screw guns);
  • Interior painting (equipment: sprayer);
  • T-Grid ceiling (equipment: screw guns, powder actuated tool);
  • Flooring (equipment: screw gun, mixer);
  • Lab equipment installation (equipment: drill, hammer, forklift);
  • Grading (equipment: Loader, sheep foot);
  • Digging for site utilities on North and South road (equipment: mini ex);
  • Running irrigation lines on South and East side (equipment: mini ex);
  • Placing stratified walls, concrete Paving and stairs (equipment: concrete trucks and pump);
  • Pavers on East and South side (equipment: wet saws and mixers);
  • Grading of parking spaces at the South end of Parking Lot 25 (equipment: loader, sheep foot, bobcat);
  • Scaffold Removal at Café.

Construction Alert #97

Please be advised that the following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site on Saturday, Sept 8th.

  • Demo of parking spaces at the South end of Parking Lot 25;
  • Interior paint;
  • Form stairs and stratified walls.

The following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site during the week of Sept 10th - Sept 14th:

  • Exterior glazing trim (equipment: forklift and boom lifts);
  • Interior framing (equipment: forklift, scissor lift, screw gun, hammer, chop saw);
  • In-wall / OH utilities (equipment: scissor lifts, screw guns);
  • Hang drywall (equipment: scissor lift, screw gun);
  • Tape & finish drywall (equipment: scissor lifts);
  • Doors and hardware (equipment: screw guns);
  • Interior painting (equipment: sprayer);
  • T-Grid ceiling (equipment: screw guns, powder actuated tool);
  • Flooring (equipment: screw gun, mixer);
  • Lab equipment installation (equipment: drill, hammer, forklift);
  • Grading South road (equipment: loader, sheep foot);
  • Digging for site utilities on North and South road (equipment: mini ex);
  • Running irrigation lines on South and East side (equipment: mini ex);
  • Placing stratified walls, concrete paving and stairs (equipment: concrete trucks);
  • Pavers on East side (equipment: wet saws and mixers);
  • Aberdeen paving and fence relocation (equipment: skip loaders, asphalt trucks, shake plates);
  • Conex box removal from site (equipment: flatbed trucks);
  • Grading of parking spaces at the South end of Parking Lot 25 (equipment: loader, sheep foot, bobcat).

Construction Alert #96

Please be advised that the following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site on Saturday, Sept 1st.

  • Flashing;
  • Interior paint;
  • Exterior caulking;
  • Casework.

The following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site during the week of Sept 3rd - Sept 7th:

  • Exterior glazing trim (equipment: forklift and boom lifts);
  • Interior framing (equipment: forklift, scissor lift, screw gun, hammer, chop saw);
  • In-wall / OH utilities (equipment: scissor lifts, screw guns);
  • Hang drywall (equipment: scissor lift, screw gun);
  • Tape & finish drywall (equipment: scissor lifts);
  • Doors and hardware (equipment: screw guns);
  • Interior painting (equipment: sprayer);
  • T-Grid ceiling (equipment: screw guns, powder actuated tool);
  • Flooring (equipment: screw gun, mixer);
  • Lab equipment installation (equipment: drill, hammer, forklift);
  • Grading South road (equipment: loader, sheep foot);
  • Digging for site utilities on North and South road (equipment: mini ex);
  • Running irrigation lines on South and East side (equipment: mini ex);
  • Placing stratified walls, concrete paving and stairs (equipment: concrete trucks);
  • Pavers on East side (equipment: wet saws and mixers).

Construction Alert #95

Please be advised that the following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site on Saturday, Aug 25th.

  • Flashing;
  • Interior paint;
  • Exterior caulking

The following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site during the week of August 27th - August 31st:

  • Exterior glazing trim (equipment: forklift and boom lifts);
  • Interior framing (equipment: forklift, scissor lift, screw gun, hammer, chop saw);
  • In-wall / OH utilities (equipment: scissor lifts, screw guns);
  • Hang drywall (equipment: scissor lift, screw gun);
  • Tape & finish drywall (equipment: scissor lifts);
  • Doors and hardware (equipment: screw guns);
  • Interior painting (equipment: sprayer);
  • T-Grid ceiling (equipment: screw guns, powder actuated tool);
  • Flooring (equipment: screw gun, mixer);
  • Lab equipment installation (equipment: drill, hammer, forklift);
  • Grading South road (equipment: loader, sheep foot);
  • Digging for site utilities on North and South road (equipment: mini ex);
  • Running irrigation lines on South and East side (equipment: mini ex);
  • Placing stratified walls and stairs on East side (equipment: concrete trucks);
  • Pavers on East side (equipment: wet saws and mixers).

Construction Alert #94

Please be advised that the following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site on Saturday, Aug 18th.

  • Metal panels;
  • Casework and equipment;
  • Interior paint;
  • Caulking of exterior vents;
  • Interior glazing;
  • Exterior caulking

The following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site during the week of August 20th - August 24th:

  • Exterior glazing trim (equipment: forklift and boom lifts);
  • Backfill of retaining wall B (equipment: loader, whackers, rollers);
  • Interior framing (equipment: forklift, scissor lift, screw gun, hammer, chop saw);
  • In-wall / OH utilities (equipment: scissor lifts, screw guns);
  • Hang drywall (equipment: scissor lift, screw gun);
  • Tape & finish drywall (equipment: scissor lifts);
  • Doors and hardware (equipment: screw guns);
  • Interior painting (equipment: sprayer);
  • T-Grid ceiling (equipment: screw guns, powder actuated tool);
  • Flooring (equipment: screw gun, mixer);
  • Lab equipment installation (equipment: drill, hammer, forklift);
  • Grading South road (equipment: loader, sheep foot);
  • Digging for site utilities on North and South road (equipment: mini ex);
  • Running irrigation lines on East side (equipment: mini ex);
  • Placing stratified walls and stairs on East side (equipment: concrete trucks);
  • Pavers on East side (equipment: wet saws and mixers).

Construction Alert #93

Please be advised that the following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site on Saturday, Aug 11th.

  • Metal panels;
  • Casework and equipment;
  • Interior painting;
  • Caulking of exterior vents

The following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site during the week of August 13th - August 17th:

  • Exterior glazing trim (equipment: forklift and boom lifts);
  • Backfill of retaining wall B (equipment: loader, whackers, rollers);
  • Interior framing (equipment: forklift, scissor lift, screw gun, hammer, chop saw);
  • In-wall / OH utilities (equipment: scissor lifts, screw guns);
  • Hang drywall (equipment: scissor lift, screw gun);
  • Tape & finish drywall (equipment: scissor lifts);
  • Doors and hardware (equipment: screw guns);
  • Interior painting (equipment: sprayer);
  • Ceramic tile in bathrooms (equipment: wet saw);
  • T-Grid ceiling (equipment: screw guns, powder actuated tool);
  • Flooring (equipment: screw gun, mixer);
  • Lab equipment installation (equipment: drill, hammer, forklift);
  • Doors (equipment: screw guns, hammers, and scissor lifts);
  • Grading North and South road (equipment: loader, sheep foot);
  • Building of ramp at retaining wall C (equipment: mini ex, concrete trucks, hammers, saws);
  • Digging for site utilities on North and South road (equipment: mini ex);
  • Running irrigation lines on East side (equipment: mini ex);
  • Placing stratified walls and stairs on East side (equipment: concrete trucks);
  • Epoxy flooring (equipment: grinders).

Construction Alert #92

Please be advised that the following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site on Saturday, Aug 4th.

  • Interior handrail;
  • Coping cap and metal panels;
  • Casework and equipment;
  • Interior painting.

The following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site during the week of August 6th - August 10th:

  • Exterior glazing (equipment: forklift and boom lifts);
  • Handrail at stair 4 (equipment: scissor lift, welders, hammers);
  • Backfill of retaining wall B (equipment: loader, whackers, rollers);
  • Interior framing (equipment: forklift, scissor lift, screw gun, hammer, chop saw);
  • In-wall / OH utilities (equipment: scissor lifts, screw guns);
  • Hang drywall (equipment: scissor lift, screw gun);
  • Tape & finish drywall (equipment: scissor lifts);
  • Doors and hardware (equipment: screw guns);
  • Interior painting (equipment: sprayer);
  • Ceramic tile in bathrooms (equipment: wet saw);
  • T-Grid ceiling (equipment: screw guns, powder actuated tool);
  • Flooring (equipment: screw gun, mixer);
  • Lab equipment installation (equipment: drill, hammer, forklift);
  • Doors (equipment: screw guns, hammers, and scissor lifts);
  • Grading North and South road (equipment: loader, sheep foot);
  • Building of ramp at retaining wall C (equipment: mini ex, concrete trucks, hammers, saws);
  • Placing bollards on East side (equipment: whacker and concrete trucks);
  • Running irrigation lines on East side (equipment: mini ex);
  • Placing stratified walls and stairs on East side (equipment: concrete trucks);
  • Epoxy flooring (equipment: grinders).

Construction Alert #91

Please be advised that the following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site on Saturday, July 28th.

  • Top coat finish
  • Interior painting

The following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site during the week of July 30th - August 3rd:

  • Exterior glazing (equipment: forklift and boom lifts);
  • Handrail at stair 4 (equipment: scissor lift, welders, hammers);
  • Backfill of retaining wall B (equipment: loader, whackers, rollers);
  • Interior framing (equipment: forklift, scissor lift, screw gun, hammer, chop saw);
  • In-wall / OH utilities (equipment: scissor lifts, screw guns);
  • Hang drywall (equipment: scissor lift, screw gun);
  • Tape & finish drywall (equipment: scissor lifts);
  • Doors and hardware (equipment: screw guns);
  • Interior painting (equipment: sprayer);
  • Ceramic tile in bathrooms (equipment: wet saw);
  • T-Grid ceiling (equipment: screw guns, powder actuated tool);
  • Flooring (equipment: screw gun, mixer);
  • Lab equipment installation (equipment: drill, hammer, forklift);
  • Scaffold removal in atrium (equipment: hammers and trucks);
  • Exterior doors (equipment: screw guns, hammers, and scissor lifts);
  • Grading North and South road (equipment: loader, sheep foot);
  • Building of ramp at retaining wall C (equipment: mini ex, concrete trucks, hammers, saws);
  • Placing bollards on East side (equipment: whacker and concrete trucks);
  • Running irrigation lines on East side (equipment: mini ex);
  • Placing stratified walls and stairs on East side (equipment: concrete trucks);
  • Epoxy flooring (equipment: grinders).

Construction Alert #90

Please be advised that the following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site on Saturday, July 21st.

  • Interior glazing;
  • Level 4 doors;
  • Flashing on roof.

The following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site during the week of July 23rd - July 27th:

  • Exterior glazing (equipment: forklift and boom lifts);
  • Handrail at stair 4 (equipment: scissor lift, welders, hammers)
  • Digging utilities, rebar, and formwork on North and East roads (equipment: mini ex., hammers, saws, concrete trucks);
  • Interior framing (equipment: forklift, scissor lift, screw gun, hammer, chop saw);
  • In-wall / OH utilities (equipment: scissor lifts, screw guns);
  • Hang drywall (equipment: scissor lift, screw gun);
  • Tape & finish drywall (equipment: scissor lifts);
  • Doors and hardware (equipment: screw guns);
  • Interior painting (equipment: sprayer);
  • Ceramic tile in bathrooms (equipment: wet saw);
  • T-Grid ceiling (equipment: screw guns, powder actuated tool);
  • Flooring (equipment: screw gun, mixer);
  • Lab equipment installation (equipment: drill, hammer, forklift);
  • Exterior doors (equipment: screw guns, hammers, and scissor lifts);
  • Grading North and South road (equipment: loader, sheep foot);
  • Building of retaining walls North road (equipment: mini ex, concrete trucks, hammers, saws);
  • Digging for site utilities (equipment: mini ex);
  • Office casework (equipment: screw guns, drill, hammers, saws).

Construction Alert #89

Please be advised that the following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site on Saturday, July 14th.

  • Exterior doors and interior glazing;
  • Level 3 doors;
  • Install flooring on Level 4

The following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site during the week of July 16th - July 20th:

  • Exterior glazing (equipment: forklift and boom lifts);
  • Misc. steel at exterior skin (scissor lifts, welders, hammers);
  • Digging utilities, rebar, and formwork on North and East roads (equipment: mini ex., hammers, saws, concrete trucks);
  • Interior framing (equipment: forklift, scissor lift, screw gun, hammer, chop saw);
  • In-wall / OH utilities (equipment: scissor lifts, screw guns);
  • Hang drywall (equipment: scissor lift, screw gun);
  • Tape & finish drywall (equipment: scissor lifts);
  • Doors and hardware (equipment: screw guns);
  • Interior painting (equipment: sprayer);
  • Ceramic tile / waterproofing in bathrooms (equipment: wet saw);
  • T-Grid ceiling (equipment: screw guns, powder actuated tool);
  • Flooring (equipment: screw gun, mixer);
  • Lab equipment installation (equipment: drill, hammer, forklift);
  • Exterior doors (equipment: screw guns, hammers, and scissor lifts);
  • Storm drain and water install (equipment: mini excavator, hammers, saws);
  • Cleaning of Level 1 (equipment: N/A);
  • Grading North road (equipment: loader, sheep foot);
  • Digging and building of retaining walls North road (equipment: mini ex, concrete trucks, hammers, saws);
  • Digging for site utilities (equipment: mini ex).

Construction Alert #88

Please be advised that the following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site on Saturday, July 7th.

  • East side terracotta;
  • Level 2 doors;
  • Install flooring on Level 4;
  • South side brick.

The following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site during the week of July 9th - July 13th:

  • Exterior glazing (equipment: forklift and boom lifts);
  • Masonry (equipment: wet saw, forklift);
  • Misc. steel at exterior skin (scissor lifts, welders, hammers);
  • Digging utilities, rebar, and formwork on South and East roads (equipment: mini ex., hammers, saws, concrete trucks);
  • Interior framing (equipment: forklift, scissor lift, screw gun, hammer, chop saw);
  • In-wall / OH utilities (equipment: scissor lifts, screw guns);
  • Hang drywall (equipment: scissor lift, screw gun);
  • Tape & finish drywall (equipment: scissor lifts);
  • Doors and hardware (equipment: screw guns);
  • Interior painting (equipment: sprayer);
  • Ceramic tile / waterproofing in bathrooms (equipment: wet saw);
  • T-Grid ceiling (equipment: screw guns, powder actuated tool);
  • Flooring (equipment: screw gun, mixer);
  • Lab equipment installation (equipment: drill, hammer, forklift);
  • Exterior doors (equipment: screw guns, hammers, and scissor lifts);
  • Storm drain and water install (equipment: mini excavator, hammers, saws);
  • Pavers at Level 3 terrace (equipment: forklift, wet saw);
  • Stone for stairs at Atrium (equipment: wet saw);
  • Cleaning of Level 1 (equipment: N/A);
  • Grading North road (equipment: loader, sheep foot);
  • Digging and building of retaining walls North road (equipment: mini ex, concrete trucks, hammers, saws);
  • Digging for site utilities (equipment: mini ex).

Construction Alert #87

Please be advised that the following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site on Saturday, June 30th.

  • East side terracotta;
  • Southeast concrete patching;
  • Level 2 doors;
  • Painting of west side exterior concrete sealer;
  • Install flooring on Level 3;
  • South side brick.

The following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site during the week of July 2nd - July 6th:

  • Metal panels and baguettes at exterior (equipment: screw guns, saws, boom lifts, fork lifts);
  • Exterior glazing (equipment: forklift and boom lifts);
  • Masonry (equipment: wet saw, forklift);
  • Misc. steel at exterior skin (scissor lifts, welders, hammers);
  • Digging utilities, rebar, and formwork on South and East roads (equipment: mini ex., hammers, saws, concrete trucks);
  • Interior framing (equipment: forklift, scissor lift, screw gun, hammer, chop saw);
  • In-wall / OH utilities (equipment: scissor lifts, screw guns);
  • Hang drywall (equipment: scissor lift, screw gun);
  • Tape & finish drywall (equipment: scissor lifts);
  • Doors and hardware (equipment: screw guns);
  • Interior painting (equipment: sprayer);
  • Ceramic tile / waterproofing in bathrooms (equipment: wet saw);
  • T-Grid ceiling (equipment: screw guns, powder actuated tool);
  • Flooring (equipment: screw gun, mixer);
  • Lab equipment installation (equipment: drill, hammer, forklift);
  • Steel erection for Café (equipment: forklift, welders, hammers);
  • Exterior doors (equipment: screw guns, hammers, and scissor lifts);
  • Storm drain and water install (equipment: mini excavator, hammers, saws);
  • Pavers at Level 3 terrace (equipment: forklift, wet saw);
  • Stone for stairs at Atrium (equipment: wet saw);
  • Cleaning of Level 1 (equipment: N/A);
  • Grading North road (equipment: loader, sheep foot).

Construction Alert #86

Please be advised that the following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site on Saturday, June 23rd.

  • East side glazing;
  • Painting of east side exterior;
  • Southeast concrete patching;
  • Level 1 & 2 doors;
  • Install flooring on Level 3.

The following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site during the week of June 25th - June 29th:

  • Metal panels and baguettes at exterior (equipment: screw guns, saws, boom lifts, fork lifts);
  • Exterior glazing (equipment: forklift and boom lifts);
  • Masonry (equipment: wet saw, forklift);
  • Misc. steel at exterior skin (scissor lifts, welders, hammers);
  • Digging utilities, rebar, and formwork on South and East roads (equipment: mini ex., hammers, saws, concrete trucks);
  • Interior framing (equipment: forklift, scissor lift, screw gun, hammer, chop saw);
  • In-wall / OH utilities (equipment: scissor lifts, screw guns);
  • Hang drywall (equipment: scissor lift, screw gun);
  • Tape & finish drywall (equipment: scissor lifts);
  • Doors and hardware (equipment: screw guns);
  • Interior painting (equipment: sprayer);
  • Ceramic tile / waterproofing in bathrooms (equipment: wet saw);
  • T-Grid ceiling (equipment: screw guns, powder actuated tool);
  • Flooring (equipment: screw gun, mixer);
  • Lab equipment installation (equipment: drill, hammer, forklift);
  • Steel erection for Café (equipment: forklift, welders, hammers);
  • Exterior doors (equipment: screw guns, hammers, and scissor lifts);
  • Storm drain and water install (equipment: mini excavator, hammers, saws);
  • Pavers at Level 3 terrace (equipment: forklift, wet saw);
  • Stone for stairs at Atrium (equipment: wet saw);
  • Cleaning of Level 1 (equipment: N/A);
  • Grading North road (equipment: loader, sheep foot);
  • Install curb and gutter on Aberdeen (equipment: concrete truck, hammers, saws).

Construction Alert #85

Please be advised that the following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site on Saturday, June 16th.

  • South lantern glazing;
  • North metal panels;
  • Painting of Level 1-4;
  • Southeast switch back valve relocation;
  • East concrete patching;
  • Level 1 doors;
  • West and South elevation ledger angle.

The following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site during the week of June 18th - June 22nd:

  • Exterior glazing (equipment: forklift and boom lifts);
  • Metal panels and baguettes at exterior (equipment: screw guns, saws, boom lifts, fork lifts);
  • Masonry (equipment: wet saw, forklift);
  • Misc. steel at exterior skin (scissor lifts, welders, hammers);
  • Digging utilities, rebar, and formwork on South and East roads (equipment: mini ex., hammers, saws, concrete trucks);
  • Interior framing (equipment: forklift, scissor lift, screw gun, hammer, chop saw);
  • In-wall / OH utilities (equipment: scissor lifts, screw guns);
  • Hang drywall (equipment: scissor lift, screw gun);
  • Tape & finish drywall (equipment: scissor lifts);
  • T-Grid ceiling (equipment: screw guns, powder actuated tool);
  • Flooring (equipment: screw gun, mixer);
  • Lab equipment installation (equipment: drill, hammer, forklift);
  • Doors and hardware (equipment: screw guns);
  • Interior painting (equipment: sprayer);
  • Ceramic tile / waterproofing in bathrooms (equipment: wet saw);
  • Scaffold removal (equipment: flatbed truck, forklift);
  • Exterior doors (equipment: screw guns, hammers, and scissor lifts);
  • Storm drain and water install (equipment: mini excavator, hammers, saws);
  • Stone for stairs at Atrium (equipment: wet saw);
  • Pavers at Level 3 terrace (equipment: forklift, wet saw);
  • Cleaning of Level 1 (equipment: N/A);
  • Grading east road (equipment: loader, sheep foot).

Construction Alert #84

Please be advised that the following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site on Saturday, June 9th.

  • South lantern glazing;
  • North metal panels;
  • East concrete patching;
  • Level 1 doors;
  • West and south elevation ledger angle;
  • Level 1 fire sprinklers;
  • North brick

The following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site during the week of June 11th - June 15th:

  • Metal panels and baguettes at exterior (equipment: screw guns, saws, boom lifts, fork lifts);
  • Exterior glazing (equipment: forklift and boom lifts);
  • Masonry (equipment: wet saw, forklift);
  • Misc. steel at exterior skin (scissor lifts, welders, hammers);
  • Digging utilities, rebar, and formwork on South and East roads (equipment: mini ex., hammers, saws, concrete trucks);
  • Interior framing (equipment: forklift, scissor lift, screw gun, hammer, chop saw);
  • In-wall / OH utilities (equipment: scissor lifts, screw guns);
  • Hang drywall (equipment: scissor lift, screw gun);
  • Tape & finish drywall (equipment: scissor lifts);
  • Doors and hardware (equipment: screw guns);
  • Interior painting (equipment: sprayer);
  • Ceramic tile / waterproofing in bathrooms (equipment: wet saw);
  • T-Grid ceiling (equipment: screw guns, powder actuated tool);
  • Flooring (equipment: screw gun, mixer);
  • Lab equipment installation (equipment: drill, hammer, forklift);
  • Scaffold removal (equipment: flatbed truck, forklift);
  • Exterior doors (equipment: screw guns, hammers, and scissor lifts);
  • Storm drain and water install (equipment: mini excavator, hammers, saws);
  • Pavers at Level 3 terrace (equipment: forklift, wet saw);
  • Stone for stairs at Atrium (equipment: wet saw);
  • Cleaning of Level 1 (equipment: na).

Construction Alert #83

Please be advised that the following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site on Saturday, June 2nd.

  • South Lantern Glazing
  • Patch Exterior Concrete

The following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site during the week of June 4th - June 8th:

  • Exterior glazing (equipment: forklift and boom lifts)
  • Metal panels at exterior (equipment: screw guns, saws, boom lifts, fork lifts)
  • Masonry (equipment: wet saw, forklift)
  • Misc. steel at exterior skin (scissor lifts, welders, hammers)
  • Digging and forming footings at tree walls and retaining wall at Southeast corner (equipment: mini ex., hammers, saws, concrete trucks)
  • In-wall / OH utilities (equipment: scissor lifts, screw guns)
  • Interior framing (equipment: forklift, scissor lift, screw gun, hammer, chop saw)
  • Hang drywall (equipment: scissor lift, screw gun)
  • Tape & Finish drywall (equipment: scissor lifts)
  • Interior painting (equipment: sprayer)
  • Ceramic tile / waterproofing in bathrooms (equipment: wet saw)
  • T-Grid ceiling (equipment: screw guns, powder actuated tool)
  • Flooring (equipment: screw gun, mixer)
  • Lab equipment installation (equipment: drill, hammer, forklift)
  • Scaffold removal (flatbed truck, forklift)
  • Exterior Doors (equipment: screw guns, hammers, and scissor lifts)
  • Storm Drain and Water install (equipment: mini excavator, hammers, saws)
  • Waterproofing hot fluid applied at Level 3 terrace (equipment: Hot kettle)
  • Stone for stairs at Atrium (equipment: wet saw)
  • Cleaning of Level 1 (equipment: n/a)

Construction Alert #82

Please be advised that the following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site on Saturday, May 26th.

  • Saturday: South Lantern Glazing and Flooring on Level 1

The following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site during the week of May 28th - June 1st:

  • Metal panels at exterior (equipment: screw guns, saws, boom lifts, fork lifts)
  • Exterior glazing (equipment: forklift and boom lifts)
  • Masonry (equipment: wet saw, forklift)
  • Misc. steel at exterior skin (scissor lifts, welders, hammers)
  • Backfill and Excavation Southeast Corner for ADA Switchback Ramp(equipment: loader, backhoe, Roller Compactor, vibrator, Super 10’s (Dirt Trucks), and Street Sweeper)
  • Interior framing (equipment: forklift, scissor lift, screw gun, hammer, chop saw)
  • In-wall / OH utilities (equipment: scissor lifts, screw guns)
  • Hang drywall (equipment: scissor lift, screw gun)
  • Tape & Finish drywall (equipment: scissor lifts)
  • Interior painting (equipment: sprayer)
  • Ceramic tile / waterproofing in bathrooms (equipment: wet saw)
  • T-Grid ceiling (equipment: screw guns, powder actuated tool)
  • Flooring (equipment: screw gun, mixer)
  • Lab equipment installation (equipment: drill, hammer, forklift)
  • Scaffold removal (Flatbed Truck, Forklift)
  • Exterior Doors (equipment: screw guns, hammers, and scissor lifts)
  • Storm Drain and Water install (equipment: mini excavator, hammers, saws)
  • Electrical sleeves at ADA switch back (equipment: mini excavator)
  • Irrigation sleeves at ADA switch back (equipment: mini excavator)
  • Waterproofing of North Road retaining wall (equipment: saws, screw gun)
  • Stone for stairs at Atrium (equipment: wet saw)

Construction Alert #81

Please be advised that the following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site on Saturday, May 19th.

  • Saturday: North Road Retaining Wall A & Scaffold removal

The following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site during the week of May 21st - May 25th:

  • Metal panels at exterior
  • Exterior glazing
  • Masonry
  • Misc. steel at exterior skin
  • Backfill and Excavation Southeast Corner for ADA Switchback Ramp (equipment: loader, backhoe, Roller Compactor, vibrator, Super 10’s (Dirt Trucks), and Street Sweeper)
  • North Road retaining wall
  • Interior framing
  • In-wall / OH utilities
  • Hang drywall
  • Tape & Finish drywall
  • Interior painting
  • Ceramic tile / waterproofing in bathrooms
  • T-Grid ceiling
  • Flooring
  • Lab equipment installation
  • Scaffold removal
  • Exterior Doors
  • Storm Drain and Water install
  • Electrical sleeves at ADA switch back
  • Irrigation sleeves at ADA switch back
  • Waterproofing of North Road retaining wall

Construction Alert #80

Please be advised that the following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site on Saturday, May 12th.

  • Saturday: North Lantern Glazing

The following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site during the week of May 14th - May 18th:

  • Metal panels at exterior
  • Exterior glazing
  • Masonry
  • Plaster
  • Misc. steel at exterior skin
  • Backfill and Excavation Southeast Corner for ADA Switchback Ramp ***Note that this may result in periodic vibration throughout the week (North of MS&E)***
  • North Road retaining wall
  • Interior framing
  • In-wall / OH utilities
  • Hang drywall
  • Tape & Finish drywall
  • Interior painting
  • Ceramic tile / waterproofing in bathrooms
  • T-Grid ceiling
  • Floor float and Flooring
  • Lab equipment installation
  • Scaffold removal
  • Exterior Doors

Construction Alert #79

Please be advised that the following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site on Saturday, May 5th.

  • Saturday: Plaster, Sheet metal flashing, Metal Panels, Masonry

The following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site during the week of May 7th - May 11th:

  • Metal panels at exterior
  • Exterior glazing
  • Masonry
  • Plaster
  • Misc. steel at exterior skin
  • Backfill and Excavation ***Note that this may result in periodic vibration throughout the week (North of MS&E)***
  • Interior framing
  • In-wall / OH utilities
  • Hang drywall
  • Tape & Finish drywall
  • Interior painting
  • Ceramic tile / waterproofing in bathrooms
  • T-Grid ceiling
  • Floor float and Flooring
  • Lab equipment installation
  • Scaffold removal

Construction Alert #78

Please be advised that the following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site on Saturday, April 28th.

  • Saturday April 28th: Plaster, Sprinkler drops, Equipment connections

The following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site during the week of April 30th - May 4th:

  • Metal panels at exterior (equipment: screw guns)
  • Exterior glazing (equipment: forklift)
  • Masonry (equipment: wet saw)
  • Plaster (equipment: pump)
  • Misc. steel at exterior skin (scissor lifts, welders)
  • Backfill (equipment): loader
  • Interior framing (equipment: forklift, scissor lift, screw gun, hammer, chop saw)
  • In-wall / OH utilities (equipment: scissor lifts, screw guns)
  • Hang drywall (equipment: scissor lift, screw gun)
  • Tape & Finish drywall (equipment: scissor lifts)
  • Interior painting (equipment: sprayer)
  • Ceramic tile / waterproofing in bathrooms (equipment: wet saw)
  • T-Grid ceiling (equipment: screw guns, powder actuated tool)
  • Floor float (equipment: screw gun, mixer)
  • Lab equipment installation (equipment: drill, hammer, forklift)

Construction Alert #77

Please be advised that the following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site on Saturday, April 21st.

  • Saturday: Tape / Finish and Exterior Framing, Exterior Glazing, Brick

The following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site during the week of April 23rd - April 27th:

  • Metal panels at exterior
  • Exterior glazing
  • Masonry
  • Plaster
  • Misc. steel at exterior skin
  • Backfill
  • Interior framing
  • In-wall / OH utilities
  • Hang drywall
  • Tape & Finish drywall
  • Interior painting
  • Ceramic tile / waterproofing in bathrooms
  • T-Grid ceiling
  • Floor float
  • Lab equipment installation

Construction Alert #76

Please be advised that the following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site on Saturday, April 14th.

  • Saturday: Tape / Finish and Exterior Framing (Nevell), Exterior Glazing (Sunset)

The following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site during the week of April 16th - April 20th:

  • Metal panels at exterior
  • Exterior glazing
  • Sealant at windows
  • Masonry
  • Plaster
  • Misc. steel at exterior skin
  • Interior framing
  • In-wall / OH utilities
  • Hang drywall
  • Tape & Finish drywall
  • Interior painting
  • Ceramic tile / waterproofing in bathrooms
  • T-Grid ceiling
  • Floor float
  • Lab equipment installation
  • Install of elevators
  • Scaffold install on West side

Construction Alert #75

  • Saturday: No work scheduled

The following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site during the week of April 9th - April 13th:

  • Exterior PMA waterproofing
  • Metal panels at exterior
  • Exterior glazing
  • Sealant at windows
  • Masonry
  • Misc. steel at exterior skin
  • Interior framing
  • In-wall / OH utilities
  • Hang drywall
  • Tape & Finish drywall
  • Interior painting
  • Ceramic tile / waterproofing in bathrooms
  • T-Grid ceiling
  • Install of elevators
  • Repair below grade waterproofing / backfill
  • Scaffold install on West side

Construction Alert #74

Please be advised that the following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site on Saturday, March 31st.

  • Saturday: Sheetmetal (Letner), Curtainwall (Sunset), Air barrier (Nevell)

The following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site during the week of April 2nd - April 6th:

  • Exterior PMA waterproofing
  • Metal panels at exterior
  • Exterior glazing
  • Sealant at windows
  • Masonry
  • Water and air barrier tests
  • Misc. steel at exterior skin
  • Interior framing
  • In-wall / OH utilities
  • Hang drywall
  • Tape & Finish drywall
  • Interior painting
  • Ceramic tile / waterproofing in bathrooms
  • T-Grid ceiling
  • Install of elevators
  • North road excavation for below grade waterproofing
  • Scaffold removal on West side

Construction Alert #73

Please be advised that the following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site on Saturday, March 24th.

  • Saturday: Sheet metal (Letner), Curtainwall (Sunset), Air barrier (Nevell)

The following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site during the week of March 26th - March 30th:

  • Exterior PMA waterproofing
  • Metal panels at exterior
  • Exterior glazing
  • Sealant at windows
  • Misc. steel at exterior skin
  • Interior framing
  • In-wall / OH utilities
  • Hang drywall
  • Tape & Finish drywall
  • Interior painting
  • Ceramic tile / waterproofing in bathrooms
  • T-Grid ceiling
  • Install of elevators
  • North road excavation for below grade waterproofing
  • Scaffold removal on West side

Construction Alert #72

The following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site during the week of March 19th - March 23rd:

Saturday, March 19th,: NO WORK
  • Exterior PMA waterproofing
  • Metal panels at exterior
  • Exterior glazing
  • Sealant at windows
  • Misc. steel at exterior skin
  • Interior framing
  • Overhead duct
  • In-wall utilities
  • Hang drywall
  • Tape & Finish drywall
  • Interior painting
  • Ceramic tile / waterproofing in bathrooms
  • T-Grid ceiling
  • Install of elevators
  • North road excavation for below grade waterproofing
  • Scaffold removal on West side

Construction Alert #71

Please be advised that the following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site on Saturday, March 10th.

  • Saturday: Roof mechanical Piping (CMI)

The following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site during the week of March 12th - March 16th:

  • Exterior PMA waterproofing
  • Metal panels at exterior
  • Exterior glazing
  • Sealant at windows
  • Misc. steel at exterior skin
  • Interior framing
  • Overhead duct
  • In-wall utilities
  • Hang drywall
  • Tape & Finish drywall
  • Interior painting
  • Ceramic tile / waterproofing in bathrooms
  • T-Grid ceiling
  • Install of elevators

Construction Alert #70

Please be advised that the following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site on Saturday, March 3rd.

  • Adjusting concrete deck at Elevator 1 & 2

The following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site during the week of March 5th - March 9th:

  • Exterior PMA waterproofing
  • Insulation / topping slab at roof
  • Metal panels at exterior
  • Exterior glazing
  • Sealant at windows
  • Misc. steel at exterior skin
  • Interior framing
  • Overhead duct
  • In-wall utilities
  • Hang drywall
  • Tape & Finish drywall
  • Interior painting
  • Ceramic tile / waterproofing in bathrooms
  • T-Grid ceiling
  • Install of elevators

Construction Alert #69

Please be advised that there will be no weekend work.

The following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site during the week of February 26th - March 2nd:

  • Exterior PMA waterproofing
  • Insulation / topping slab at roof
  • Metal panels at exterior
  • Exterior concrete coating (WARNING: THIS WILL HAVE A STRONG ODOR)
  • Exterior glazing
  • Sealant at windows
  • Misc. steel at exterior skin
  • Interior framing
  • Hang drywall
  • Tape & Finish drywall
  • Interior painting
  • Ceramic tile / waterproofing in bathrooms
  • Overhead duct
  • In-wall utilities
  • Install of elevators
  • Crane will be here Tuesday for the removal of the man hoist

Construction Alert #68

The following activities will be occurring from 6:00 am to 3:00 pm on the MRB1 Construction Site on Saturday, February 17th:

  • Duct installation at roof level;
  • • Fire Sprinkler Piping installation.

Note that there will be construction activity on Monday 2.19.2018 (President’s Day). The following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site during the week of February 19th - February 23th:

  • Install Air Barrier waterproofing
  • Exterior PMA waterproofing
  • Insulation / topping slab at roof
  • Metal panels at exterior
  • Exterior concrete coating WARNING: THIS WILL HAVE A STRONG ODOR
  • Exterior glazing
  • Sealant at windows
  • Misc. steel at exterior skin
  • Interior framing
  • Hang drywall
  • Tape & Finish drywall
  • Overhead duct
  • In-wall utilities
  • Install of elevators
  • Crane on Tuesday for Terra Cotta Frames on South side

Construction Alert #67

The following activities will be occurring from 6:00 am to 3:00 pm on the MRB1 Construction Site on Saturday, February 10rd:

  • Exterior wall metal panel installation;
  • Electrical Wire installation;
  • Misc. steel installation.

The following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site during the week of February 12th - February 16th:

  • Install Air Barrier waterproofing
  • Install Brick Veneer
  • Exterior PMA waterproofing
  • Insulation / topping slab at roof
  • Metal panels at exterior concrete coating
  • Exterior concrete coating WARNING: THIS WILL HAVE A STRONG ODOR
  • Exterior glazing.
  • Sealant at windows.
  • Misc. steel at exterior skin.
  • Install of scaffolding in atrium
  • Interior framing.
  • Hang drywall.
  • Tape & Finish drywall.
  • Overhead duct.
  • In-wall utilities.
  • Install of elevators.

Construction Alert #66

The following activities will be occurring from 6:00 am to 3:00 pm on the MRB1 Construction Site on Saturday, February 3rd:

  • Exterior wall metal panel installation;
  • Sheet metal Duct installation;
  • Misc. steel installation.

The following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site during the week of February 5th - February 9th:

  • Install Air Barrier waterproofing
  • Install Brick Veneer
  • Exterior PMA waterproofing
  • Cell-crete slurry / insulation / topping slab at roof
  • Metal panels at exterior Exterior concrete coating
  • Paint louver support steel east of MS&E – at future ADA ramp
  • Exterior glazing
  • Sealant at windows
  • Misc. steel at atrium and exterior skin
  • Install of scaffolding in atrium
  • Interior framing
  • Hang drywall
  • Overhead duct
  • In-wall utilities
  • Install of elevators
  • Crane onsite on Monday for delivery of generator

Construction Alert #65

The following activities will be occurring from 6:00 am to 3:00 pm on the MRB1 Construction Site on Saturday, January 27th:

  • Plumbing installation;
  • Sheet metal Duct installation;
  • Misc. steel installation.

The following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site during the week of January 29th - February 2nd:

  • Installation of air barrier waterproofing;
  • Installation of brick veneer;
  • Installation of exterior PMMA waterproofing;
  • Installation of cellular concrete, insulation, and topping slab at roof;
  • Installation of metal panels at exterior;
  • Exterior glazing and sealant;
  • Miscellaneous steel at atrium and lower level;
  • Interior framing, hang drywall, install MEP hangers and overhead utilities;
  • Installation of in-wall utilities;
  • Elevator installation.

Construction Alert #64

The following activities will be occurring from 6:00 am to 3:00 pm on the MRB1 Construction Site on Saturday, January 20th:

  • Plumbing installation
  • Metal panel installation.

The following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site during the week of January 22nd - January 26th:

  • Installation of air barrier waterproofing;
  • Installation of brick veneer;
  • Installation of exterior PMA waterproofing;
  • Installation of cellular concrete, insulation, and topping slab at roof;
  • Installation of metal panels at exterior;
  • Exterior glazing and sealant;
  • Miscellaneous steel at atrium and lower level;
  • Interior framing, hang drywall, install MEP hangers and overhead utilities;
  • Elevator installation.

Construction Alert #63

The following activities will be occurring from 6:00 am to 3:00 pm on the MRB1 Construction Site on Saturday, January 13th:

  • Plumbing and ductwork installation
  • Concrete placement on roof.

The following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site during the week of January 15th - January 19th:

  • Installation of air barrier waterproofing;
  • Installation of brick veneer;
  • Installation of exterior PMA waterproofing;
  • Installation of cellular concrete, insulation, and topping slab at roof;
  • Installation of metal panels at exterior;
  • Sealant at windows;
  • Exterior concrete cleaning;
  • Interior framing;
  • Hang drywall;
  • Install MEP hangers and overhead utilities;
  • Install of elevators.

Construction Alert #62

The following activities will be occurring from 6:00 am to 3:00 pm on the MRB1 Construction Site on Saturday, January 6th:

  • Installation of rooftop equipment;
  • Installation of duct at Lower Level;
  • Demolition of concrete on roof;

The following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site during the week of January 8th - January 12th:

  • Installation of air barrier waterproofing;
  • Installation of brick veneer;
  • Installation of exterior PMA waterproofing;
  • Installation of metal panels at exterior;
  • Sealant at windows;
  • Clean up of exterior concrete;
  • Interior framing;
  • Hang drywall;
  • Install MEP hangers and overhead utilities;
  • Install of elevators.

Construction Alert #61

The following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site during the week of January 2nd - January 6th:

  • Install Air Barrier waterproofing
  • Install Brick Veneer
  • Exterior PMA waterproofing
  • Metal panels at exterior
  • Vapor barrier at roof
  • Interior framing
  • Hang drywall
  • Install MEP hangers
  • Overhead utilities
  • Install of elevators
  • Install of electrical room equipment
  • Crane on site Friday afternoon to be assembled. Crane will be lifting the remainder of the mechanical equipment onto the roof on Saturday, 01/06.

Construction Alert #60

The following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site during the week of December 26th - Decwember 29th:

  • Continue exterior framing and sheathing and air barrier waterproofing;
  • Install brick veneer;
  • Exterior PMA waterproofing;
  • Metal panels at exterior;
  • Interior framing (equipment: forklift, scissor lift, screw gun, hammer, chop saw
  • Hang drywall, install MEP hangers and overhead utilities;
  • Install of elevators;
  • Crane on site Thursday to lift duct supports and mechanical equipment to the roof.

Construction Alert #59

The following activities will be occurring from 6:00 am to 3:00 pm on the MRB1 Construction Site on Saturday, December 9th:

  • Install mechanical duct at Lower Level;
  • Install rooftop equipment.

The following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site during the week of December 11th - Decwember 15th:

  • Continue exterior framing and sheathing and air barrier waterproofing;
  • Install brick veneer;
  • Installation of exterior PMA waterproofing;
  • CMU & Grout;
  • Metal panels at exterior;
  • Roof vapor barrier;
  • Interior framing and drywall installation;
  • Install MEP hangers and overhead utilities;
  • Installation of elevators;
  • Demolition of existing landscape and hardscape north of the MS&E lecture halls; please note that this work will include the use of jackhammers and backhoes, so noise will be evident.

Construction Alert #58

The following activities will be occurring from 6:00 am to 3:00 pm on the MRB1 Construction Site on Saturday, December 9th:

  • Install mechanical duct at Lower Level;
  • Install steel framing at roof

The following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site during the week of December 11th - Decwember 15th:

  • Install window frames/ and glass;
  • Install exterior framing and sheathing;
  • Install air barrier waterproofing;
  • Install brick veneer;
  • Install exterior PMA waterproofing;
  • CMU & grout;
  • Metal panels at exterior;
  • Reinforce / place loading dock topping slab;
  • Install roof vapor barrier;
  • Install large electrical equipment;
  • Elevator steel installation;
  • Continue interior framing and drywall hanging;
  • Install MEP hangers and overhead utilities;
  • Elevator installation;
  • Installation of air handling units onto roof.

Construction Alert #57

The following activities will be occurring from 6:00 am to 3:00 pm on the MRB1 Construction Site on Saturday, December 2nd:

  • Install mechanical duct at Lower Level

The following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site during the week of December 4th - Decwember 8th:

  • Install window frames & glass;
  • Exterior framing & sheathing;
  • Install air barrier waterproofing;
  • Install brick veneer;
  • Exterior PMA waterproofing;
  • Install CMU & grout;
  • Install metal panels at exterior;
  • Roof steel structure;
  • Interior framing and hang drywall;
  • Install MEP hangers & overhead utilities;
  • Install decking at roof top doghouses;
  • Install insulation at roof top doghouses;
  • Elevator installation;
  • TENTATIVE FOR THURSDAY: Install air handling units onto roof.

Construction Alert #56

The following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site during the week of November 27th - Decwember 1st:

  • Install window frames & glass;
  • Exterior framing & sheathing;
  • Install air barrier waterproofing;
  • Install brick veneer;
  • Exterior PMA waterproofing;
  • Install CMU & grout;
  • Install metal panels at exterior;
  • Roof steel structure;
  • Interior framing and hang drywall;
  • Install MEP hangers & overhead utilities;
  • Install decking at roof top doghouses;
  • Install insulation at roof top doghouses;
  • TENTATIVE FOR THURSDAY: Install air handling units onto roof.

Construction Alert #55

The following activities will be occurring from 6:00 am to 3:00 pm on the MRB1 Construction Site on Saturday, November 18th:

  • Installation of Ductwork (CMI).
  • Installation of Roof Steel (Pro Steel)

The following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site during the week of November 20th:

  • Install window frames/glass
  • Exterior framing and sheathing
  • Install Air Barrier waterproofing
  • Install Brick Veneer
  • Exterior PMA waterproofing
  • CMU & Grout
  • Metal panels at exterior
  • Scaffold erection
  • Roof steel structure
  • Interior framing
  • Hang drywall
  • Install MEP hangers
  • Overhead utilities
  • Roof install decking at doghouses
  • Roof install dens glass at doghouses

Construction Alert #54

The following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site during the week of November 13th – November 17th:

  • Install window frames/glass
  • Exterior framing and sheathing
  • Install Air Barrier waterproofing
  • Install Brick Veneer
  • Exterior PMA waterproofing
  • Concrete Masonry Unit (CMU) & Grout Installation
  • Roof steel structure
  • Interior framing
  • Hang drywall
  • Install MEP hangers
  • Overhead utilities
  • Roof install decking at doghouses
  • Roof install dens glass at doghouses
  • Backfill dirt

Construction Alert #53

The following activities will be occurring from 6:00 am to 3:00 pm on the MRB1 Construction Site on Saturday, November 4th:

  • Installation of roof screen and brick ledgers.
  • Installation of Lower Level ducts

The following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site during the week of November 6th – November 10th:

  • Form, reinforce, place stair 2;
  • Form, reinforce, place boardform walls in atrium;
  • Install window frames and glass;
  • Continue exterior framing and sheathing;
  • Install air barrier waterproofing;
  • Install brick veneer;
  • Install exterior PMA waterproofing;
  • CMU & Grout;
  • Install roof steel structure;
  • Interior framing and drywall installation;
  • Install MEP hangers and overhead utilities;
  • Install decking at Roof doghouses;
  • Install sheathing at Roof doghouses.

Construction Alert #52

The following activities will be occurring from 6:00 am to 3:00 pm on the MRB1 Construction Site on Saturday, October 28th:

  • Installation of roof screen and brick ledgers.

The following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site during the week of October 30th – November 3rd:

  • Form, reinforce, place stair 2 ;
  • Form, reinforce, place boardform walls in atrium;
  • Install window frames and glass;
  • Continue exterior framing and sheathing;
  • Install air barrier waterproofing;
  • Install brick veneer;
  • Install exterior PMA waterproofing;
  • Erect scaffolding;
  • CMU & Grout;
  • Install roof steel structure;
  • Interior framing and drywall installation;
  • Install MEP hangers and overhead utilities;
  • Form, reinforce, place transformer pad on north fire road.

Construction Alert #51

The following activities will be occurring from 6:00 am to 3:00 pm on the MRB1 Construction Site on Saturday, October 21st:

  • Installation of roof screen;

The following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site during the week of October 23rd – October 27th:

  • Close, place, strip upturn beams & pads on roof;
  • Set interior stairs;
  • Form, reinforce, and place stair 4; form stair 2
  • Form, reinforce, place boardform walls in atrium;
  • Install window frames/glass;
  • Exterior framing;
  • Exterior PMA waterproofing;
  • Install scaffolding;
  • Install CMU & grout;
  • Install roof steel structure;
  • Form, reinforce, place roof pads;
  • Interior framing and hang drywall;
  • Install MEP hangers and overhead utilities;
  • Site water tie-in;
  • Install underground electrical.

Construction Alert #50

The following activities will be occurring from 6:00 am to 3:00 pm on the MRB1 Construction Site on Saturday, October 14th:

  • Installation of roof screen;

The following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site during the week of October 16th – October 20th:

  • Removal of reshores on Level 3;
  • Close, place, strip beams and pads on roof;
  • Set interior stairs;
  • Form, reinforce, and place stair 4 ;
  • Install window frames/glass;
  • Install exterior framing;
  • Install exterior PMA waterproofing;
  • Roof steel structure;
  • Form, reinforce, place roof pads;
  • Interior framing;
  • Hang drywall;
  • Install MEP hangers and overhead utilities;
  • Site water tie in /tank installation;
  • Underground electrical

Construction Alert #49

The following activities will be occurring from 6:00 am to 3:00 pm on the MRB1 Construction Site on Saturday, October 7th:

  • Installation of roof screen;
  • Installation of brick ledger.

The following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site during the week of October 9th – October 13th:

  • Removal of reshores on Level 3;
  • Close, place, strip beams and pads on roof;
  • Set interior stairs;
  • Form, reinforce stair 4 ;
  •  Waterproof loading dock;
  • Waterproof loading dock;
  • Install window frames on Level 2;
  • Install exterior framing;
  • Install exterior PMA waterproofing;
  • Install roof steel structure;
  • Form, reinforce, place roof pads;
  • Interior framing;
  • Hang drywall; install MEP hangers and overhead utilities;
  • Site water tie in /tank installation.

Construction Alert #48

The following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site during the week of October 2nd – October 6th:

  • Removal of reshores on Level 3;
  • Close, place, strip beams and pads on roof;
  • Set interior stairs;
  • Form, reinforce stair 4 ;
  • Backfill east side of project site;
  • Waterproof loading dock;
  • Install window frames on Level 2;
  • Exterior framing;
  • Exterior PMA waterproofing;
  • Install roof steel structure;
  • Interior framing, hang drywall; paint;
  • Install MEP hangers and overhead utilities;
  • Continue site water connection.

Construction Alert #47

The following activities will be occurring from 6:00 am to 3:00 pm on the MRB1 Construction Site on Saturday, September 23rd:

  • Removal of reshores on Level 3;
  • MEP layout and inserts on roof deck;
  • Form Stair 4 at the west side of the building.

The following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site during the week of September 25th – September 29th:

  • Continue installation of Lower Level catwalk steel;
  • Strip column pads;
  • Remove reshores on Levels 3;
  • Form, Reinforce and place roof deck;
  • From, reincorce Stair 4;
  • Install deck angle anchors at the loading dock;
  • Install sheet metal flashing at Lower Level;
  • Install canopy steel at Lower Level;
  • Exterior framing and waterproofing;
  • Install Roof steel structure;
  • Install sheathing & exterior framing;
  • Install interior framing at Lower Level; hang drywall;
  • Install water site utilities.

Construction Alert #46

The following activities will be occurring from 4:00 am to 6:00 am on the MRB1 Construction Site on Saturday, September 16th:

  • Removal of reshores on Level 2; strip shoring/install reshores on Level 3; strip Level 4 columns/walls; reinforce Level 4 deck;
  • MEP layout and inserts on roof deck;
  • Installation of Lower Level catwalk steel.

The following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site during the week of September 18th – September 22nd:

  • Continue installation of Lower Level catwalk steel;
  • Reinforce/form column pads;
  • Strip forms/install reshores on Levels 3 & 4;
  • Reinforce and place roof deck;
  • Place and strip Level 4 columns and walls;
  • Set Stairs 1 & 3; reinforce and place Stair 1, 3, & 4; form and reinforce Stair 4;
  • Install sheathing & exterior framing;
  • Install interior framing at Lower Level; hang drywall;
  • Install MEP hangers and overhead sprinkler pipe at Levels 1 & 2;
  • Install water site utilities.

Construction Alert #45

The following activities will be occurring from 4:00 am to 6:00 am on the MRB1 Construction Site on Friday, September 9th:

  • Removal of reshores on Level 2; strip shoring/install reshores on Level 3; Strip and reinforce Level 4 columns;
  • Form roof deck;
  • Form Stair 4;
  • Installation of Lower Level catwalk steel,

The following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site during the week of September 11th – September 15th:

  • Continue installation of Lower Level catwalk steel;
  • Reinforce/form column pads;
  • Removal of reshores on Level 2, strip forms and install reshores on Level 3;
  • Form, reinforce and place roof deck;
  • Form, reinforce and place Level 4 columns and walls;
  • Set Stairs 1 & 3; reinforce and place Stair 1; form and reinforce Stair 4;
  • Install exterior framing;
  • Install interior framing at Lower Level; hang drywall;
  • Install MEP hangers and overhead sprinkler pipe;
  • Install sanitary sewer site utilities.

Construction Alert #44

The following activities will be occurring from 4:00 am to 6:00 am on the MRB1 Construction Site on Friday, September 1st:

  • On Friday, September 1, between the hours of 4 AM to 6 AM, the MRB1 General Contractor will close a portion of the west side of Aberdeen Drive in order to stage a crane to facilitate the loading of steel to the upper deck. Safety flagmen will redirect pedestrians and vehicles during this period.

The following activities will be occurring from 6:00 AM to 3:00 PM on the MRB1 Construction Site during the week of September 5th – September 8th:

  • Form, reinforce, and place brick ledgers along the perimeter of the building;
  • Continue installation of catwalk steel;
  • Removal of reshores on Level 2, strip forms and install reshores on Level 3;
  • Reinforce and place Level 4 deck; place Level 4 columns and walls;
  • Continue forming roof deck; reinforce, form Level 4 columns and walls;
  • Set a Stairs 1 & 3; reinforce and place Stair 3;
  • Form and reinforce Stair 4;
  • Form, reinforce, and place loading dock support walls;
  • Install window support steel at Lower Level;
  • Sheathing and exterior framing;
  • Install MEP hangers and overhead sprinkler pipe at level 1;
  • Install interior framing and drywall at Lower Level;
  • Form, reinforce, and place brick ledgers along the perimeter of the building;
  • Install sanitary sewer site utilities.

Construction Alert #43

The following activities will be occurring from 6:00 am to 3:00 pm on the MRB1 Construction Site on Saturday, August 26th , and from 7:00 am to 4:00 pm during the week of August 28th – September 1st :

      Saturday, August 26th:
    • Remove reshores on Level 1, install reshores on Level 2 & Level 3;
    • Install catwalk streel at Interstitial Level;

 

    August 28th - September 1st:
  • Form, reinforce, and place slab on grade at ground level;
  • Continue installation of catwalk steel;
  • Continue removal of reshores on Level 1, strip forms and install reshores on Level 2 & 3; place level 3 columns/walls;
  • Form and place Level 4 deck; place Level 4 columns and walls;
  • Form roof deck;
  • Set and place Stair 3; form and reinforce Stair 4;
  • Form, reinforce, and place loading dock support walls;
  • Place rock and slurry slab in Lower Level;
  • Install window support steel at Lower Level;
  • Sheathing and exterior framing;
  • Install MEP hangers and overhead sprinkler pipe;
  • Install manhoist;
  • Form, reinforce, and place brick ledgers along the perimeter of the building;
  • Install sanitary sewer site utilities.

Construction Alert #42

The following activities will be occurring from 6:00 am to 3:00 pm on the MRB1 Construction Site on Saturday, August 19th , and from 7:00 am to 4:00 pm during the week of August 21st – August 25th :

      Saturday, August 19th:
    • Remove reshores on Level 1, install reshores on Level 2 & Level 3;
    • Install catwalk streel at Interstitial Level;
    • Form/reinforce Level 3 columns and walls;

 

    August 21st - August 25th:
  • Continue installation of catwalk steel;
  • Continue removal of reshores on Level 1, strip forms and install reshores on Level 2 & 3; place level 3 columns/walls;
  • Place rock and slurry slab in Lower Level;
  • Demolition slab at Lower Level for installation of floor drains;
  • Form/reinforce/place concrete at Level 3 deck columns and walls;
  • Reinforce Level 4 deck, place Level 4 deck;
  • Form, reinforce, and place brick ledgers along the perimeter of the building;

Construction Alert #41

The following activities will be occurring from 6:00 am to 3:00 pm on the MRB1 Construction Site on Saturday, August 12th , and from 7:00 am to 4:00 pm during the week of August 14th – August 18th :

    Saturday, August 12:
  • Remove reshores on Level 1, install reshores on Level 2 & Level 3;
  • Place Level 3 deck concrete;
  • Form Level 4 deck;
  • Install catwalk steel at Interstitial Level.
  • August 14th - August 18th:
  • Continue installation of catwalk steel;
  • Continue removal of reshores on Level 1, strip forms and install reshores on Level 2 & 3;
  • Place rock and slurry slab in Lower Level;
  • Form/reinforce/place concrete at Level 3 deck columns and walls;
  • Reinforce Level 4 deck, place Level 4 deck;
  • Form, reinforce, and place brick ledgers along the perimeter of the building;
  • Continue installation of Stair 3; form, reinforce, and place Stair 4 concrete.

Construction Alert #40

The following activities will be occurring from 6:00 am to 3:00 pm on the MRB1 Construction Site on Saturday, August 5th , and from 7:00 am to 4:00 pm during the week of August 7th – August 11th :

  • Early next week Contractor will be installing hot mop asphalt waterproofing at the loading dock This work will create asphalt odor on site as well as near adjacent buildings.
  • Remove reshores on level 1.
  • Remove forms, install reshores, and reinforce at Level 2 and Level 3, place Level 2 columns and walls, and form level 4 deck.
  • Place rock and slurry slab in Lower Level.
  • Form/reinforce/and place concrete at Level 3 deck columns and walls.
  • Drill and epoxy, form/reinforce and place column pedestals.
  • Form, reinforce, and place brick ledgers along the perimeter of the building.
  • Embed install and Reinforce Level 3, Area 1 deck.
  • Continue installation of Stair 1 , Stair 3, and Stair 4.
  • Install interior framing, MEP hangers, ad interstitial catwalk inside the Ground Level.
  • Exterior framing Lower Level & Level 1.

Construction Alert #39

The following activities will be occurring from 6:00 am to 3:00 pm on the MRB1 Construction Site on Saturday, July 29th , and from 7:00 am to 4:00 pm during the week of July 31st – August 4th :

  • Early next week Contractor will be installing hot mop asphalt waterproofing at the loading dock This work will create asphalt odor on site as well as near adjacent buildings.
  • Remove reshores inside Ground level.
  • Remove forms, install reshores, and reinforce at Level 2 and Level 3, place Level 2 columns and walls, and form level 4 deck.
  • Form/reinforce/and place concrete at Level 3 deck columns and walls.
  • Drill and epoxy, form/reinforce and place column pedestals.
  • Form, reinforce, and place brick ledgers along the perimeter of the building.
  • Embed install and Reinforce Level 3, Area 1 deck.
  • Continue installation of Stair 1 , Stair 3, and Stair 4.
  • Install interior framing, MEP hangers, ad interstitial catwalk inside the Ground Level.
  • Exterior framing Lower Level & Level 1.

Construction Alert #38

The following activities will be occurring from 6:00 am to 3:00 pm on the MRB1 Construction Site on Saturday, July 22nd , and from 7:00 am to 4:00 pm during the week of July 24th – July 28th :

  • Form/reinforce/and place concrete at Level 3 deck;
  • Form, reinforce, and place brick ledgers along the perimeter of the building;
  • Embed install and Reinforce Level 3, Area 1 deck;
  • Set Stair 1 at interior of the building;
  • Install interior framing and interstitial catwalk inside the Ground Level;
  • Exterior framing Lower Level & Level 1.

Construction Alert #37

The following activities will be occurring from 6:00 am to 3:00 pm on the MRB1 Construction Site on Saturday, July 15th , and from 7:00 am to 4:00 pm during the week of July 17th – July 21st :

  • Form and place loading dock perimeter walls at the west area of the building.
  • Strip and reshore Level 2 area 2 deck
  • Place vertical Level 1 area 3, Level 2 Area 2
  • Form/Reinforce Columns and Walls Level 2 Area 3, Level 3 Area 1
  • Place Concrete Decks – Level 2 Area 3, Level 3 Area 1
  • Embed install and Reinforce Level 3, Area 1 deck
  • Form Level 3, Area 2 deck
  • Set Stair 1 & 3
  • Install exterior framing Lower Level & Level 1
  • Drill and epoxy curbs and pads in Lower Level

Construction Alert #36

The following activities will be occurring from 6:00 am to 3:00 pm on the MRB1 Construction Site on Saturday, July 8th , and from 7:00 am to 4:00 pm during the week of July 10th – July 14th :

  • Forming, embed install, and reinforcement of Level 3 deck.
  • Stripping of forms and re-shore of Level 2, placement of columns and walls at Level 2.
  • Form, reinforce, and place brick ledgers along the perimeter of the building and reinforcing of perimeter walls.
  • Form and place loading dock perimeter walls at the west area of the building.
  • Install exterior framing at the Lower Level.

Construction Alert #35

The following activities will be occurring from 6:00 am to 3:00 pm on the MRB1 Construction Site on Saturday July 1st:

  • Level 1 column and shear wall placement.
    On Saturday, July 1, please be aware that noise levels and some vibration will be noticeable at the MRB1 site from Level 1 column and shear wall concrete placement.

The following activities will be occurring from 7:00 am to 4:00 pm on the MRB1 Construction Site on Saturday July 3rd - July 7th:

  • Installation of sanitary sewer Line at the west side of the project site.
    The MRB1 General Contractor will be excavating , placing site utilities, and backfilling on the west side of the site.
  • Other activities include:
    • Stripping of forms, re-shore of Level 1 and Level 2, forming, reinforcement and placement of columns, walls, and decks at Level 2.
    • Forming Level 3 deck.
    • Form, reinforce, and place brick ledgers along the perimeter of the building and reinforcing of perimeter walls.

Construction Alert #34

The following activities will be occurring from 6:00 am to 3:00 pm on the MRB1 Construction Site on Saturday June 24th:

  • Level 2 Deck Forming and Reinforcement:
    On Saturday, June 24th, please be aware that noise levels and some vibration will be noticeable at the MRB1 site from Level 2 deck forming and placement of rebar.

The following activities will be occurring from 7:00 am to 4:00 pm on the MRB1 Construction Site on Saturday June 26th - June 30th:

  • Installation of sanitary sewer Line at the west side of the project site.
    The MRB1 General Contractor will be excavating and placing site utilities on the west side of the site.
  • Waterproofing and backfill on the north side of the building.
    Trucks will be entering and leaving the MRB1 Construction site, via the entrance at Linden Street and Parking Lot 25; flagmen, signage, and caution tape will be present.
  • Other activities include:
    • Stripping of forms, re-shore of Level 1 and Level 2, forming, installation, and placement of columns, walls, and decks at Level 2.
    • Forming Level 3 deck
    • Form, reinforce, and place brick ledgers along the perimeter of the building and reinforcing of perimeter walls.
    • Exterior framing along the Lower Level at the south area of the building pad.

Construction Alert #33

The following activities will be occurring from 6:00 am to 3:00 pm on the MRB1 Construction Site on Saturday June 17th:

  • Level 2 Deck Forming and Reinforcement:
    On Saturday, June 17th, please be aware that noise levels and some vibration will be noticeable at the MRB1 site from Level 2 deck forming and placement of rebar.

The following activities will be occurring from 7:00 am to 4:00 pm on the MRB1 Construction Site on Saturday June 19th - June 23rd:

  • Installation of sanitary sewer Line at the west side of the project site.
    The MRB1 General Contractor will be excavating and placing site utilities on the west side of the site.
  • Waterproofing and backfill on the north side of the building.
    Trucks will be entering and leaving the MRB1 Construction site, via the entrance at Linden Street and Parking Lot 25; flagmen, signage, and caution tape will be present.
  • Waterproofing and Backfill on the north side of the building:
    Trucks will be entering and leaving the MRB1 Construction site, via the entrance at Linden Street and Parking Lot 25; flagmen, signage, and caution tape will be present.
  • Other activities include:
    • Stripping of forms, re-shore of Level 1 and Level 2, forming, installation, and placement of columns, walls, and decks at Level 2.
    • • Installation of mechanical, electrical, and plumbing sleeves, embeds, and equipment pads.

Construction Alert #32

The following activities will be occurring from 6:00 am to 3:00 pm on the MRB1 Construction Site on Saturday June 10th:

  • Level 2 Deck Forming and Reinforcement:
    On Saturday, June 10th, please be aware that noise levels and some vibration will be noticeable at the MRB1 site from Level 2 deck forming and placement of rebar.

The following activities will be occurring from 7:00 am to 4:00 pm on the MRB1 Construction Site on Saturday June 12th - June 16th:

  • Stripping of Forms, Re-shore of Level 1, Forming and Installation and placement of Columns, Walls, and Decks at Level 2.
  • Setting of Loading Dock Canopy Vertical Steel & Stair 1 at Lower Level.
  • Waterproofing and Backfill on the north side of the building:
    Trucks will be entering and leaving the MRB1 Construction site, via the entrance at Linden Street and Parking Lot 25; flagmen, signage, and caution tape will be present.

Construction Alert #31

The following activities will be occurring from 7:00 am to 4:00 pm on the MRB1 Construction Site on Saturday June 3rd:

  • Stripping of Forms, Re-shore of Level 1, Forming and Installation of Rebar at Level 2:On Saturday, June 3rd, please be aware that noise levels and some vibration will be noticeable at the MRB1 site.

The following activities will be occurring from 7:00 am to 4:00 pm on the MRB1 Construction Site on Saturday June 5th - June 9th:

  • Stripping of Forms, Re-shore of Level 1, Forming and Installation of Columns and Decks at Level 1& 2:Please be aware that noise levels and some vibration will be noticeable at the MRB1 site.

Construction Alert #30

The following activities will be occurring from 7:00 am to 4:00 pm on the MRB1 Construction Site on May 30th – June 2nd:

    • Forming and Installation of Rebar, Forming and Placement of Columns and Decks at Level 1 and Level 2:
      During the week of May 30th – June 2nd, please be aware that noise levels and some vibration will be noticeable at the southern areas of the MRB1 site from rebar installation and placement of lower level columns within the building pad.

Construction Alert #29

The following activities will be occurring from 7:00 am to 4:00 pm on the MRB1 Construction Site on Saturday May 20th:

  • Level One Deck and Column Forming
    On Saturday May 20h, please be aware that noise levels may be noticeable as the MRB1 General Contractor will be forming the Level One Deck and columns on the northwest and southeast area of the job site.

The following activities will be occurring from 7:00 am to 4:00 pm on the MRB1 Construction Site on May 22nd – May 26th:

  • Forming, Rebar Installation, Placement of Lower Level Columns:
    During the week of May 22ndth – May 26th, please be aware that noise levels and some vibration will be noticeable at the southern areas of the MRB1 site from rebar installation and placement of lower level columns within the building pad.
  • Level One Deck Forming, Rebar and Embed Installation, and Concrete Placement:
    During the week of May 22ndth – May 26th, please be aware that noise levels may be noticeable as the MRB1 General Contractor will be placing rebar, forming decks and columns, and placing the Level One Deck in all areas of the building footprint.

    There is a large crane on the jobsite to support loading of deck activities.

Construction Alert #28

The following activities will be occurring from 7:00 am to 4:00 pm on the MRB1 Construction Site on May 13th:

  • Level One Deck and Column Forming
    On Saturday May 13th, please be aware that noise levels may be noticeable as the MRB1 General Contractor will be forming the Level One Deck and columns on the northwest and northeast edges of the job site. There will be a large crane setting up in the southeast corner of the jobsite to support loading of deck activities.

The following activities will be occurring from 7:00 am to 4:00 pm on the MRB1 Construction Site on May 15th – May 19th:

  • Site Utility Installation:
    During the week of May 13th – May 19th, please be aware that that noise levels may be noticeable as the MRB1 General Contractor will be backfilling site utilities on the south side of the project, just north of the MS&E Building.
  • Forming, Rebar Installation, Placement of Lower Level Columns:
    During the week of May 13th – May 19th, please be aware that noise levels and some vibration will be noticeable at the southern areas of the MRB1 site from rebar installation and placement of lower level columns within the building pad.
  • Level One Deck Forming, Rebar and Embed Installation, and Concrete Placement:
    During the week of May 13th – May 19th, please be aware that noise levels may be noticeable as the MRB1 General Contractor will be forming and placing the Level One Deck on the southeast and west edge of the job site. There will be a large crane setting up in the southeast corner of the jobsite to support loading of deck activities.

Construction Alert #27

The following activities will be occurring from 7:00 am to 4:00 pm on the MRB1 Construction Site on May 6th 29th – May 12th:

  • Slab on Grade Preparation and Concrete Removal
    On Saturday, May 6th, please be aware that noise levels may be noticeable as the MRB1 General Contractor will be saw cutting slab on grade at the northwest area of the site and performing limited concrete removal at the south edge of the building pad.
  • Site Utility Installation:
    During the week of May 8th-12th, please be aware that that noise levels may be noticeable as the MRB1 General Contractor will be excavating and placing site utilities on the south side of the project, just north of the MS&E Building.
  • Forming, Rebar Installation, Placement of Lower Level Columns:
    During the week of May 8th-12th, please be aware that noise levels and some vibration will be noticeable at the western areas of the MRB1 site from rebar installation and placement of lower level columns within the building pad.
  • Level One Deck Forming, Rebar Installation, and Concrete Placement
    During the week of May 8th-12th, please be aware that noise levels may be noticeable as the MRB1 General Contractor will be forming the Level One Deck on the southeast and west edge of the job site. There will be a large crane setting up in the southeast corner of the jobsite to support loading of deck activities.

Construction Alert #26

The following activities will be occurring from 6:00 am to 4:00 pm on the MRB1 Construction Site on April 29th – May 5th:

  • Slab on Grade Preparation
    On Saturday, April 29th, please be aware that the MRB1 General Contractor will be placing vapor barrier in preparation for slab on grade placement.
  • Site Utility Installation:
    During the week of May 1st-5th, please be aware that that noise levels may be noticeable as the MRB1 General Contractor will be excavating and placing site utilities on the south side of the project.
  • Fine Grading & Vapor Barrier Installation:
    During the week of May 1st-5th, please be aware that that noise levels may be noticeable as the MRB1 General Contractor prepares for Slab on Grade placement, with fine grading activities and vapor barrier installation.
  • Forming, Rebar Installation, Placement of Lower Level Columns:
    During the week of May 1st-5th, please be aware that noise levels and some vibration will be noticeable at the western areas of the MRB1 site from excavation, rebar placement, and concrete column placement within the building pad.
  • Level One Deck Forming, Rebar Installation, and Level 1 Deck Concrete Placement
    During the week of May 1st-5th, please be aware that noise levels may be noticeable as the MRB1 General Contractor will be forming the Level One floor deck which will include hammering and saw cutting and embed placement. There will be a large crane setting up in the southeast corner of the jobsite to these activities.

Construction Alert #25

The following activities will be occurring from 6:00 am to 4:00 pm on the MRB1 Construction Site on April 22nd – April 28th:

  • Site Utility Excavation and Rebar Placement
    On Saturday, April 22nd, please be aware that the MRB1 General Contractor will be excavating and placing site utilities on the south and west side of the project and placing rebar in preparation for shotcrete. The General Contractor will also be removing a concrete slab near the south of the building pad. Some noise will be evident from this process.
  • Site Utility Installation:
    During the week of April 24th – 28th, please be aware that that noise levels may be noticeable as the MRB1 General Contractor will be excavating and placing site utilities on the south and west side of the project.
  • Rebar Installation, Placement of Lower Level Walls:
    During the week of April 24th – 28th, please be aware that noise levels and some vibration will be noticeable at the western areas of the MRB1 site from excavation, rebar placement, and concrete wall placement within the building pad.
  • Level One Deck Forming
    During the week of April 24th – 28th, please be aware that noise levels may be noticeable as the MRB1 General Contractor will be forming the Level One floor deck which will include hammering and saw cutting and embed placement.

Construction Alert #24

The following activities will be occurring from 6:00 am to 4:00 pm on the MRB1 Construction Site on April 15th – April 21th:

  • Preparation for Slab on Grade Placement
    On Saturday, April 15th, please be aware that the MRB1 General Contractor will be placing rebar and excavating and backfilling in preparation for slab on grade placement.
  • Excavation and Site Utility Installation:
    During the week of April 17th – 21st, please be aware that that noise levels may be noticeable as the MRB1 General Contractor will be excavating and placing site utilities on the south and west side of the project.
  • Excavation, Rebar Installation, Placement of the Concrete for Foundations, and Lower Level Vertical Columns and Walls:
    During the week of April 17th – 21st, please be aware that noise levels and some vibration will be noticeable at the western areas of the MRB1 site from excavation, rebar placement, shotcrete wall and foundation placement within the building pad.
  • Slab on Grade Placement:
    During the week of April 17th – 21st, please be aware that the MRB1 General Contractor will be placing part of the lower level slab on grade. Concrete trucks will be entering the site from the Linden Street entrance to Parking Lot 25.
  • Forming Level 1 Deck:
    During the week of April 17th – 21st, please be aware that that noise levels may be noticeable as the MRB1 General Contractor begins forming the Level 1 floor deck.

In all instances, the Contractor will monitor activities in order to minimize any impacts to Campus operations.

Construction Alert #23

The following activities will be occurring from 6:00 am to 4:00 pm on the MRB1 Construction Site on April 8th – April 14th:

  • Site Utility Installation:
    On Saturday, April 8th, please be aware that the MRB1 General Contractor will be placing site utilities on the south side of the project. The Contractor will also be placing rebar and excavating and backfilling in preparation for slab on grade placement.
  • Excavation, Rebar Installation, Placement of the Concrete for Foundations, and Lower Level Vertical Columns and Walls:
    During the week of April 8th-April 14th, please be aware that noise levels and some vibration will be noticeable at the western areas of the MRB1 site from excavation, rebar placement, and foundation placement within the building pad.
  • Excavation and Site Utility Installation:
    During the week of April 8th-April 14th, please be aware that the MRB1 General Contractor will be excavation for placing site utilities on the west side of the project during the entire week.
  • Slab on Grade Placement:
    On Wednesday, April 12th, please be aware that the MRB1 General Contractor will be placing part of the lower level slab on grade. This will be a large concrete pour and work will commence very early Wednesday morning.

In all instances, the Contractor will monitor activities in order to minimize any impacts to Campus operations.

Construction Alert #22

The following activities will be occurring from 6:00 am to 4:00 pm on the MRB1 Construction Site on April 1st – April 7th:

  • Rebar Installation and Excavation and Backfill:
    On Saturday, April 1st, please be aware that the MRB1 General Contractor will placing rebar and excavating and backfilling in preparation for slab on grade placement. The Contractor will monitor these activities in order to minimize any impacts to Campus operations.
  • Excavation, Rebar Installation, Placement of the Concrete for Foundations, Shotcrete Walls, and Lower Level Vertical Columns and Walls:
    During the week of April 3-April 7, please be aware that noise levels and some vibration will be noticeable at the western areas of the MRB1 site from excavation, rebar placement, and foundation placement within the building pad. The Contractor will monitor these activities in order to minimize any impacts to Campus operations.
  • Site Utility Installation:
    During the week of April 3-April 7, please be aware that the MRB1 General Contractor will placing site utilities on the south of the project during the entire week. The Contractor will monitor these activities in order to minimize any impacts to Campus operations.

Construction Alert #21

The following activities will be occurring from 6:00 am to 4:00 pm on the MRB1 Construction Site on Thursday, 30th:

  • Utility Vault Installation
    Please be aware that on Thursday, March 30th, there will be a crane set up in the existing fire lane north of the MS&E building which will be used for setting a new utility vault. While emergency access will be maintained, general service lane access east of the crane will be temporarily closed for the day to allow this work to complete.

Construction Alert #20

The following activities will be occurring from 7:00 am to 4:00 pm on the MRB1 Construction Site for the period March 25th-March 31st:

  • Rebar Installation and Pouring of Foundations:
    On Saturday, March 25th, please be aware that the MRB1 General Contractor will be placing rebar and excavating and backfilling in preparation for slab on grade placement at the west area of the building pad. The Contractor will monitor these activities in order to minimize any impacts to Campus operations.
  • Excavation, Rebar Installation, Placement of the Concrete for Foundations, Shotcrete Walls, and Lower Level Vertical Columns and Walls:
    During the week of March 27th-March 31th please be aware that noise levels and some vibration will be noticeable at the western areas of the MRB1 site from excavation, rebar placement, and foundation placement within the building pad. The Contractor will monitor these activities in order to minimize any impacts to Campus operations.
  • Excavation for Site Utilities and Site Utilities Installation:
    During the week of March 27th-March 31th please be aware that noise levels and some vibration will be noticeable on the MRB1 site from Contractor operations excavating at the western and southern areas of the site for installation of utilities. The Contractor will monitor these activities in order to minimize any impacts to Campus operations from earth moving equipment and trucks by the most expedient methods.

Construction Alert #19

The following activities will be occurring from 7:00 am to 4:00 pm on the MRB1 Construction Site for the period March 18th-March 24th:

  • Rebar Installation and Pouring of Foundations:
    On Saturday, March 18th, please be aware that the MRB1 General Contractor will placing rebar and pouring spread footings in the northern site areas. The Contractor will monitor these activities in order to minimize any impacts to Campus operations.
  • Forming and Rebar Installation, Placement of the Shotcrete Walls and Lower Level Vertical Columns and Walls:
    During the week of March 20th-March 24th please be aware that noise levels and some vibration will be noticeable at the northern and western areas of the MRB1 site from rebar placement and shotcrete wall and column placement within the building pad. The Contractor will monitor these activities in order to minimize any impacts to Campus operations.
  • Excavation for Site Utility Installation:
    During the week of March 20th-March 24th please be aware that noise levels and some vibration will be noticeable on the MRB1 site from Contractor operations excavating on the north area for site utilities and concrete foundations. The Contractor will monitor these activities in order to minimize any impacts to Campus operations from earth moving equipment and trucks by the most expedient methods.

Construction Alert #18

The following activities will be occurring from 7:00 am to 4:00 pm on the MRB1 Construction site for the period of March 11th - March 17th:

  • Rebar Installation and Pouring of Foundations:
    On Saturday, March 11th, please be aware that the MRB1 General Contractor will be placing rebar and excavating for spread footings in the north and south site areas. The Contractor will monitor these activities in order to minimize any impacts to Campus operations by the most expedient methods.
  • Forming and Rebar Installation, Placement of the Shotcrete Walls and Lower Level Vertical Columns and Walls:
    During the week of March 13th – March 17th, please be aware that noise levels and some vibration will be noticeable on the north and south areas of MRB1 site from shotcrete wall placement and concrete column placement within the building pad. The Contractor will monitor these activities in order to minimize any impacts to Campus operations.
  • Excavation for, and Installation of Site Utilities:
    During the week of March 13th – March 17th, please be aware that noise levels and some vibration will be noticeable on the MRB1 site from Contractor operations excavating on the north and south areas for site utilities. Chilled water and steam pipe installation will occur on the south of the project, just north of the MS&E Building. The Contractor will monitor these activities in order to minimize any impacts to Campus operations from earth moving equipment and trucks by the most expedient methods.

Construction Alert #17

The following activities will be occurring from 7:00 am to 4:00 pm on the MRB1 Construction site for the period of March 4th - March 10th:

  • Rebar Installation and Pouring of Foundations:
    On Saturday, March 4th, please be aware that the MRB1 General Contractor will placing rebar and pouring spread footings in the north and south site areas. The Contractor will monitor these activities in order to minimize any impacts to Campus operations by the most expedient methods.
  • Forming and Rebar Installation, Placement of the Shotcrete Walls and Lower Level Vertical Columns and Walls:
    Please be aware that noise levels and some vibration will be noticeable on the MRB1 site from Contractor operations excavating on the north area for site utilities and concrete foundations. The Contractor will monitor these activities in order to minimize any impacts to Campus operations from earth moving equipment and trucks by the most expedient methods.
  • Excavation Site Utility Installation:
    Please be aware that noise levels and some vibration will be noticeable on the MRB1 site from Contractor operations excavating on the north and south site areas for site utilities and concrete foundations. The Contractor will monitor these activities in order to minimize any impacts to campus operations from earth moving equipment and trucks by the most expedient methods.

Construction Alert #16

The following activities will be occurring from 7:00 am to 4:00 pm on the MRB1 Construction site for the period of Feb 25th - March 3rd:

  • Soil Export Trucking:
    On Saturday, February 25th, high numbers of trucks will be entering and leaving the MRB1 Construction site, via the entrance at Linden Street and Parking Lot 25; flagmen, signage, and caution tape will be present.
  • Forming and Rebar Installation, Placement of the Shotcrete Walls and Lower Level Vertical Columns and Walls:
    Please be aware that noise levels and some vibration will be noticeable on the north and east areas of MRB1 site from shotcrete wall and column placement within the building pad. The Contractor will monitor these activities in order to minimize any impacts to campus operations.
  • Excavation for Concrete Foundations, Rebar Installation, Pouring of Foundations, and Site Utility Installation on the North and South Areas of the Project:
    Please be aware that noise levels and some vibration will be noticeable on the MRB1 site from Contractor operations excavating on the north and south site areas for site utilities and concrete foundations. The Contractor will monitor these activities in order to minimize any impacts to campus operations from earth moving equipment and trucks by the most expedient methods.

Construction Alert #15

The following activities will be occurring from 7:00 am to 4:00 pm on the MRB1 Construction site for the period of Feb 20th - 24th:

  • Excavation for Concrete Foundations, Rebar Installation, Pouring of Foundations, and Site Utility Installation on the North and South Areas of the Project:
    Please be aware that noise levels and some vibration will be noticeable on the MRB1 site from Contractor operations excavating on the north and south site areas that are slightly north of the MS&E for site utilities and concrete foundations. This will include the elevator pits located near the southeast corner and western part of the building pad along with backfilling of utility trenches. The Contractor will monitor these activities in order to minimize any impacts to campus operations.
  • Forming and Rebar Installation, Placement of the Shotcrete Walls and Lower Level Vertical Columns and Walls:
    Please be aware that noise levels and some vibration will be noticeable on the north and east areas of MRB1 site from shotcrete wall and column placement within the building pad. The Contractor will monitor these activities in order to minimize any impacts to campus operations.

Construction Alert #14

The following activities will be occurring from 7:00 am to 4:00 pm on the MRB1 Construction site for the period of Feb 13th - 17th:

  • Excavation for Concrete Foundations, Rebar Installation, Pouring of Foundations, and Site Utility Installation on the North and South Areas of the Project:
    Please be aware that noise levels and some vibration will be noticeable on the MRB1 site from Contractor operations excavating on the north and south site areas that are slightly north of the MS&E for site utilities and concrete foundations. This will include the elevator pits located near the southeast corner and western part of the building pad along with backfilling of utility trenches. The Contractor will monitor these activities in order to minimize any impacts to campus operations from earth moving equipment and trucks by the most expedient methods.
  • Forming and Rebar Installation of the Shotcrete Walls and Lower Level Vertical Columns and Walls:
    Please be aware that noise levels and some vibration will be noticeable on the north and east areas of MRB1 site from shotcrete wall and column placement within the building pad. The Contractor will monitor these activities in order to minimize any impacts to campus operations from crane moving equipment and trucks by the most expedient methods.

Construction Alert #13

The following activities will be occurring from 7:00 am to 4:00 pm on the MRB1 Construction site:

  • Excavation for Concrete Foundations and Utility Trench Backfill: Saturday, February 4th
  • Excavation for Concrete Foundations, Rebar Installation, Pouring of Foundations, and Site Utility Installation: February 6 – February 10, 2017
    Please be aware that noise levels and some vibration will be noticeable on the MRB1 site. The Contractor will monitor these activities in order to minimize any impacts to campus Operations from earth moving equipment and trucks by the most expedient methods.

Construction Alert #12

The following activities will be occurring from 7:00 am to 4:00 pm on the MRB1 Construction site:

  • Site Utility Installation during the entire Week January 30th – February 3rd
    Site infrastructure work for utility installation on the south side of the MRB1 Site and just north of the MS&E building will provide minimal noise during the entire week. The Contractor will make every effort to oversee the work in order to minimize any noise from the underground site utilities.
  • Excavation and Rebar Installation of Foundations during the entire Week: January 30th – February 3rd
    Please be aware that noise levels and some vibration will be noticeable on the MRB1 site from Contractor operations including excavation, rebar installation and pouring concrete for the foundations in the northeast corner of the project. Construction activities will include removal of soils at elevator pits located near the southeast corner and western part of the building footprint. Construction equipment and methods will generate some additional noise during this period. The contractor will monitor these activities in order to minimize any impacts to campus Operations from earth moving equipment and trucks by the most expedient methods.

Construction Alert #11

The following activities will be occurring from 7:00 am to 4:00 pm on the MRB1 Construction site:

  • Delivery of (2) Single Wide Subcontractor Job Trailers on Monday January 16th, 2017
    The Contractor does not anticipate heavy traffic due to the holiday, but they will be providing traffic control at the end of Parking Lot 25 and monitoring on Linden Street.
  • Site Utility Installation during the entire Week January 16th – 20th, 2017
    Site infrastructure work for utility installation on the south side of the MRB1 Site and just north of the MS&E building will provide minimal noise during the entire week. The Contractor will make every effort to oversee the work in order to minimize any noise from the underground site utilities.
  • Excavation and Rebar Installation of Foundations during the entire Week: January 16th – 20th, 2017
    Please be aware that noise levels and some vibration will be noticeable on the MRB1 site from Contractor operations including excavation and rebar installation of the foundations in the northeast corner of the project. Construction activities will include removal of soils at elevator pits located near the southeast corner and western part of the building footprint. Construction equipment and methods will generate some additional noise during this period. The Contractor will monitor these activities in order to minimize any impacts to Campus operations from earth moving equipment and trucks by the most expedient methods.

Construction Alert #10

The following activities will be occurring from 7:00 am to 4:00 pm on the MRB1 Construction site:

  • Over-excavation, Compaction, and Grading: January 7, 2017
    Please be aware that noise levels and some vibration will be noticeable on the MRB1 site. Contractor operations will endeavor to minimize noise and vibration impacts from earth moving equipment and trucks by the most expedient methods.

Construction Alert #9

The following activities will be occurring from 7:00 am to 4:00 pm on the MRB1 Construction site:

  • Over-excavation, Compaction, and Grading: January 3rd – 4th
    Please be aware that noise levels and some vibration will be noticeable on the MRB1 site. Contractor operations will endeavor to minimize noise and vibration impacts from earth moving equipment and trucks by the most expedient methods.
  • Installation of New Storm Drain Lines and Water Lines: January 4th
    Contractor activities will include site infrastructure work for storm drain and water lines with construction equipment and methods which will add to the noise level on this day. The Contractor will make every effort to oversee the work in order to minimize any noise from the installation of underground site utilities. Any vibration from these activities shall be monitored, but is not expected to present an impact to campus operations.
  • Excavation of Footings and Elevator Pits: January 3rd – 11th
    Construction activities will include removal of soils at all elevator pits within the building footprint. Construction equipment and methods will generate some additional noise during this period. The Contractor will monitor these activities in order to minimize any impacts to campus operations.

Construction Alert #8

The following activities will be occurring from 7:00 am to 4:00 pm on the MRB1 Construction site:

  • Loud Noise and Vibration from Demolition Activities: December 27–29
    Please be aware that noise levels and vibration will be extremely noticeable on the MRB1 site. The contractor will be complete the removal of concrete footings and bench north of the MS&E building. (Due to inclement weather, the removal of the concrete footings and bench was delayed and will continue 12/27-12/29.) This will be accomplished by using a jackhammer and breaker. Where alternative means and methods could be also utilized, the contractor will make every effort to employ them to minimize the noise and vibration as much as possible.
  • Transport Crane: December 30
    Truck transport will load and remove crane at Linden Avenue entrance to Parking Lot 25.
  • Over-excavation, Compaction, and Grading: December 29- 30, January 3-4
    Please be aware that noise levels and some vibration will be noticeable on the MRB1 site. Contractor operations will endeavor to minimize noise and vibration impacts from earth moving equipment and trucks by the most expedient methods.

Construction Alert #7

The following activities will be occurring from 7:00 am to 4:00 pm on the MRB1 Construction site December 21st-23rd:

  • Loud Noise and Vibration from Demolition Activities
    Please be aware that noise levels and vibration will be extremely noticeable on the MRB1 site. The contractor will be removing concrete footings and bench north of the MS&E building. This will be accomplished by using a jackhammer and breaker. Where alternative means and methods could be also utilized, the contractor will make every effort to employ them to minimize the noise and vibration as much as possible.

Construction Alert #6

The following activities will be occurring on the MRB1 Construction Site over the weekend period of 12/14-12/16:

  • Soil Export Trucking
    Location: high numbers of trucks entering and leaving the MRB1 Construction site, via the entrance at Linden Street and Parking Lot 25; flagmen, signage, and caution tape will be present.


The UCR MRB1 Team recognizes that construction activities will at times pose inconveniences and disruption to the surrounding neighborhood. We thank you for your patience during construction of this project.

Construction Alert #5

The following activities will be occurring on the MRB1 Construction Site over the weekend period of 12/3-12/4:

  • Over-excavation, compaction, and grading
    Please be aware that noise levels and some vibration will be noticeable on the MRB1 site. Contractor operations will endeavor to minimize noise and vibration impacts from earth moving equipment and trucks by the most expedient methods.

Construction Alert #4

The following activities will be occurring on the MRB1 Construction Site over the period of 11/28 and 12/2:

  • Soil export trucking
    • Location: high numbers of trucks entering and leaving the MRB1 Construction site, via the entrance at Linden Street and Parking Lot 25; flagmen, signage, and caution tape will be present.
  • Rough grading and site compaction
    • Location: MRB1 building pad, associated noise and vibration.

Construction Alert #3

The following activities will be occurring on the MRB1 Construction Site over the period of 11/18, 11/21 & 11/22:

  • Soil export trucking
    • Location: high numbers of trucks entering and leaving the MRB1 Construction site, via the entrance at Linden Street and Parking Lot 25.

Construction Alert #2

The following activities will be occurring on the MRB1 Construction Site over the period of 11/7-11/16:

  • Construction site ramp compaction: 11/07-11/09
    • Location: at the northwest corner of construction site
  • Temporary fire lane compaction: 11/08-11/10
    • Location: north of MS&E
  • Various demolition activities: 11/09-11/16
    • Location: north, east and south ends of project
      • Concrete cutting of portion of existing fire lane north of MS&E
      • Limited tree removal
      • Existing athletic lighting pole footing removal
      • Break up of concrete debris to remove rebar for transport

Construction Alert

Project Construction fencing will be installed from September 22 - September 23, 2016. Please reference the construction logistics map above.

Visits to MRB1 Site:

All University academic and staff personnel who are needing access to the construction site that is now in progress, should notify the Project Program Coordinator (Cathleen Stasik @ 909-781-0990) one week prior to intended visit. The Project Manager will advise the Contractor's superintendent, obtain necessary liability waivers, and ensure that proper protective safety equipment is used by all who enter the construction site. Safety is our main priority. 


To sign up to receive construction updates click on this link

More Information 

General Campus Information

University of California, Riverside
900 University Ave.
Riverside, CA 92521
Tel: (951) 827-1012

Related Links

Footer